Bosch GV 64x Built-Under Dishwasher Installation Guide
This document provides detailed instructions for the installation of the Bosch GV 64x built-under dishwasher. Please follow these steps carefully to ensure proper setup and operation.
Step 1: Preparation and Cabinet Requirements
Before starting, ensure you have adequate space and the correct cabinet dimensions. The appliance is designed for built-under installation.
Diagram 1: Shows the dimensions of the built-under dishwasher unit. Height: 81.5 cm. Width: 570 mm. Depth: 570-600 mm. Water inlet hose length: 1.75 m.
Diagram 2: Illustrates cabinet requirements. Shows different cabinet configurations and required clearances. For standard installation, the cabinet height should be greater than 608 mm, and the depth should be a maximum of 600 mm. A minimum gap of 608 mm is indicated for the appliance height.
Diagram 3: Depicts the types of screws and their placement for mounting. Shows screws with dimensions [4x36 mm diameter] and [4x13 mm diameter].
Diagram 4: Illustrates positioning the dishwasher into the cabinet opening. Shows the appliance being leveled using adjustable feet. The adjustment range for the feet is indicated as [0-60 mm adjustment range].
Diagram 5: Shows the appliance being secured to the surrounding cabinets using screws.
Diagram 6: Illustrates connecting the water inlet and drainage hoses. A warning symbol indicates [do not pinch] the hoses.
Step 2: Mounting and Securing the Appliance
Follow these steps to securely mount the dishwasher within the cabinet.
Diagram 7: Details the process of attaching mounting brackets and securing the dishwasher to the cabinet. Shows a [click] mechanism for some components. Arrows indicate the direction of assembly.
Diagram 8: Shows a step to remove a disc. It also illustrates checking for leaks after one wash cycle. A warning symbol indicates a maximum torque of [max 10 Nm torque] for tightening screws. A symbol indicates a water flow rate of [10 liters per minute flow rate].
Step 3: Water and Electrical Connections
Connect the water supply, drainage, and electrical power according to the following instructions.
Diagram 9 (Page 2): Shows detailed connections for the water inlet and drainage hoses. The water inlet connection requires a G 3/4" or G 1/2" fitting. Various hose lengths are shown: max 1.1 m, 2 m, 2.2 m, and 5 m.
Diagram 10 (Page 2): Illustrates the electrical connection. A standard electrical plug [?] is shown, implying connection to a grounded outlet.
Diagram 11 (Page 2): Specifies water connection requirements. Diameter of water inlet connection: [38 mm diameter]. Minimum hose length: 280 mm. Minimum distance from floor for water connection: 10 mm. Water pressure: 0.05-1 MPa (0.5-10 bar). Maximum water temperature: 60°C.
Diagram 12 (Page 2): Shows a final check [✔️] of all connections and the appliance's position.
Diagram 13 (Page 2): Illustrates the use of tools, specifically wrenches for tightening nuts: [10mm wrench] and [13mm wrench].
Step 4: Final Checks
After installation, perform final checks to ensure everything is correctly installed and functional.
- Verify all water and electrical connections are secure.
- Ensure the appliance is level and stable.
- Check that no hoses are kinked or pinched.
- Run a short test cycle to check for leaks and proper operation.