HFCL ion413_CPE UBR Quick Start Guide
Brand: IO Networks by HFCL
Product: ion413_CPE UBR
Tagline: ANYWHERE EVERYWHERE
Introduction
Thank you for choosing the IO's Unlicensed Band Radio (UBR). The Enterprise Grade point-to-point and point-to-multipoint solution is optimally designed to support low to medium capacity enterprise applications in unlicensed 5 GHz spectrum for short and long range links.
Packaging Content
The package includes:
- 2x2 UBR (Qty: 1)
- Quick Start Guide (Qty: 1)
Mounting Kit Components:
The mounting kit includes:
- 1. Hood (1)
- 2. M6 Hex Bolts with split washers (6)
- 3. M6 Flange Nuts with serrations (4)
- 4. M8 x 220 Bolts (2)
- 5. Riveted U clamps (1)
- 6. Pole clamp assembly (1)
- 7. Pole clamp (1)
- 8. Nuts M8 (4), M8 split washer (4) & M8 flat washers (4)
[Image: Diagram of the 2x2 UBR unit and Quick Start Guide booklet. Separate diagram shows various mounting hardware components.]
ion413_CPE Specifications
Peak Throughput (aggregate) | Up to 300 Mbps Aggregate UL/DL Throughput |
---|---|
MIMO | 2X2 |
Modulation | Upto 256 QAM |
Channel Bandwidth | 10/20/40 MHz |
Wireless QoS | 802.11e WMM |
Wireless Security | WPA, WPA2, & 128-bit AES-PSK with hardware acceleration |
Power Supply | IEEE 802.3af Active PoE |
Power Consumption (Max) | <15 W |
GPS Location | GNSS-1 (GPS+GLONASS) |
Antenna Type | Integrated High Performance Dish Antenna |
Antenna Gain | 25 dBi |
Management | Standalone (via GUI) or through appliance-based EMS or cloud-based |
Enclosure Dimensions | 465 x 465 x 235 mm or 18.3 x 18.3 x 9.25 inches |
Weight | 2 kg |
Operating Temperature | 0°C to 55°C |
Certifications | CE, FCC, RoHS 3.0, IP67 |
Product Overview
The 2x2 UBR features an integrated dish antenna with four studs on its backside for attaching the mounting bracket. This bracket is designed for pole mounting and allows for link alignment adjustments.
[Diagram: UBR unit showing Dish Antenna, Earthing Point, LAN + PoE Port, and LED. Text indicates power is supplied via PoE Adaptor and Ethernet Cable.]
Installation Set-up
The mounting bracket facilitates pole installation, allowing for precise link alignment.
- Attach the hood to the UBR using four M6 flange nuts. Ensure the cut in the hood aligns with the lug connector. [Image: UBR with hood attached using M6 flange nuts.]
- Attach the pole clamp assembly to the UBR using three M6 hex bolts and split spring lock washers. [Image: Pole clamp assembly attached to UBR.]
- Mount this assembly onto the UBR using three M6 hex bolts and split spring lock washers. [Image: Assembly mounted on UBR.]
- Mount the assembled UBR onto the pole using two M8 x 220 bolts, four split spring lock washers, and flat washers. [Image: UBR assembly being mounted on a pole.]
- Slightly loosen M6 bolts on the brackets, rotate to align the pointer mark for optimal azimuth and elevation. Securely tighten the six bolts with a spanner once the desired setting is achieved. [Images: Close-ups of mounting bracket bolts highlighting angle markings for adjustment.]
Getting the ion413_CPE Online
Step 1: Power up
The UBR can be powered using a 48V PoE adapter. For powering the UBR, only use HFCL POE adapters. Plug and adapter types may vary by country/region.
[Diagram: UBR connected to a PoE Adapter (48V) via an Ethernet Cable, which is then connected to a Laptop/Computer.]
Step 2: Login and Configure the UBR
Follow these steps to connect the UBR to a network:
- Connect an Ethernet cable from your laptop/computer to the UBR.
- Connect the other end of the Ethernet cable to the data port on the PoE adapter.
- Connect the UBR's PoE supported Ethernet port to the PoE adapter's power port. The device will be powered ON.
- Open a web browser and enter "UBR IP address" in the address bar. The default static IP address for the 2x2 UBR is set to "192.168.1.1".
- A login screen will appear.
- Enter the default login credentials: User:
admin
, Password:HFcl!@23#ion
- Refer to the user manual on io.hfcl.com for detailed configuration information.
[Image: Screenshot of the UBR login screen.]
Step 3: Check the LED status
LED Color | Status |
---|---|
Green LED (Power indication) | Green color notifies the user that the device is powered ON. |
BLUE LED (RSSI/Link indication) | Single blink: -1 to -50 dBm Double blink: -51 to -60 dBm Triple blink: Greater than -60 dBm NOTE: If the link is down, the Link LED will be in a continuous OFF state. |
BLUE LED (Alarm Indication) | Single blink: Minor Alarms Double blink: Major Alarms Triple blink: Critical Alarms NOTE: During Reboot and Factory Reset, all three LEDs will glow for 7 seconds, and the power LED will continue to glow. |
Safety Precautions
Observe the following safety precautions to avoid damage to the ion413_CPE UBR:
- ? Do not power the device during installation.
- ? Do not subject the device to high temperatures.
- ? Keep away from high voltage cables.
- ? Do not power off the unit in the middle of an upgrade process.
- ? The gland should be ground facing all the time.
- ? Make sure the earthing wire is connected properly to the earthing points.
- ? Do not open the enclosure when the UBR is working.
- ? Fasten the device tightly.