Before using this product, please follow these basic guidelines:
- Please carefully read the manual before beginning the installation process.
- The EK fittings require only a small amount of force to screw them firmly in place, as the liquid seal is ensured by the rubber o-ring gaskets.
- The use of corrosion-inhibiting coolants is always recommended for any liquid cooling system. EKWB recommends any of the EK-Cryofuel for worry-free usage.
There are many ways to install your EK-Quantum Volume/Kinetic FLT as it utilizes a standard fan mounting hole pattern with 15mm spacing, the same as all EK radiators. The mounting holes have standard M4 threads with maximum engagement of 10mm. Use of longer screws or screws with incorrect threads, such as those intended for fans or radiators, may damage your product!
Mounting Directions
The FLT Reservoir can be mounted in multiple directions. Vertical and horizontal positioning is optional.
Note: Do not mount the FLT Reservoir when the pump is in a dead position.
[Image: Diagram showing correct vertical and horizontal mounting orientations for the FLT reservoir.]
[Image: Diagram showing incorrect mounting orientation for the FLT reservoir with a pump in a dead position.]
Installing EK-Quantum Volume / Kinetic FLT Directly
Using the included M4 screws, you can mount the reservoir directly to your chassis or any other standard fan mounting location.
[Image: Diagram illustrating direct mounting of the FLT reservoir using M4 x 10 DIN 7984 screws.]
Installing EK-Quantum Volume / Kinetic FLT with Supplied Mounts
To enable installation of the reservoir onto fans, radiators, or where clearance for the pump is required, EK supplies a pair of FLT mounts along with M4 nuts, washers, and additional screws. They can be positioned across any pair of mounting holes in several orientations.
STEP 1
Position the mounts as desired on the reverse side of the reservoir.
[Image: Diagram showing the placement of FLT mounts on the back of the reservoir.]
STEP 2
Screw the mounts in place using supplied M4x8 screws and a 2.5mm allen key.
[Image: Diagram illustrating screwing the FLT mounts to the reservoir using M4 x 8 DIN 7984 screws.]
Installing EK-Quantum Volume / Kinetic FLT Reservoir into the Case
3a.
Included M4 nuts, washers, and M4x10 screws can be used to mount the flat reservoir to a fan.
[Image: Diagram showing the FLT reservoir mounted to a 120 mm fan using M4 screws, washers, and nuts.]
3b.
Using 30mm long screws supplied with your radiator, the reservoir can be mounted onto the radiator and 25mm thick fans together.
[Image: Diagram showing the FLT reservoir mounted to a radiator and 25mm thick fans using 30mm long screws.]
3c.
Alternatively, the shorter 5mm long screws from the radiator may be used to mount only the reservoir.
[Image: Diagram showing the FLT reservoir mounted to a radiator using shorter 5mm screws.]
3d.
Lastly, the supplied M4 nuts, washers, and M4x10 screws may be used to secure the reservoir to a case with the mounts. This is useful when there is no clearance behind for the pump or to prevent airflow from being blocked.
[Image: Diagram showing the FLT reservoir mounted to a case using mounts, nuts, washers, and M4 screws.]
Attaching the Fittings
EK-Quantum Kinetic FLT
The EK-Quantum Kinetic FLT has two inlet and two outlet ports. One inlet and one outlet must be used. All 4 unused ports should be blocked using G1/4 plugs.
[Image: Diagram of EK-Quantum Kinetic FLT showing INLET, OUTLET, and FILL ports, with indications for unused ports.]
EK-Quantum Volume FLT
The EK-Quantum Volume FLT has two ports which can be used as inlet or outlet. The chosen outlet should connect directly to your pump. The reservoir should be positioned above the pump to ensure it does not run without coolant. Both unused ports should be blocked using G1/4 plugs.
[Image: Diagram of EK-Quantum Volume FLT showing INLET/OUTLET and FILL ports, with indications for unused ports.]
Connecting the D-RGB LED Strip
Plug the 3-pin connector from the water block's D-RGB LED light into the D-RGB HEADER on the motherboard. The LED will work if the pin layout on the header is as follows: +5V, Digital.
[Image: Diagram showing the D-RGB connector plugged into the D-RGB Header on a motherboard.]
Important: Please ensure that the arrow indicated on the connector is plugged into the +5V line as indicated on your motherboard. Failure to do so will damage your motherboard or LED strip.
Testing the Loop
To make sure the installation of EK components was successful, we recommend you perform a leak test for 24 hours.
When your loop is complete and filled with coolant, connect the pump to a PSU outside of your system. Do not connect power to any of the other components. Turn on the PSU and let the pump run continuously. It is normal for the coolant level to drop during this process as air collects in the reservoir.
Inspect all parts of the loop, and in the eventuality that coolant leaks, fix the issue and repeat the testing process. Ensure that all hardware is dry before the system is powered on in order to prevent any damage.