Relay Kit Installation for Multiple Heater Control

Revision: OPT-CL31-CL32 (04-22) Supersedes: OPT-CL31-CL32 (01-22)

Options CL31 and CL32 for Models APD, F, B, UDAP, UDAS, UDBP, UDBS, UEAS, and VR

Important Safety Information

[!] CAUTION

[!] DO NOT use these multiple heater control options with a two-stage gas valve or a two-stage thermostat.

[!] These instructions are designed to assist a qualified electrician in installing this multiple heater control kit.

[!] All electrical wiring and connections, including electrical grounding, MUST be in accordance with the National Electric Code ANSI/NFPA No. 70 (latest edition) or, in Canada, with the Canadian Electrical Code, Part 1, CSA Standard C22.1. In addition, the installation must comply with local ordinances and applicable gas company requirements.

[!] These relay kits are designed to permit the control of up to five heaters (one control unit and up to four additional non-control units) with one single-stage thermostat or with a time clock and single or multiple single-stage thermostats. For maximum safety, the multiple control is installed in the low voltage circuit. Interruption of the supply voltage is not recommended.

[!] Refer to the installation manual provided with the heater for important safety information.

[!] Pay attention to all dangers, warnings, cautions, and notes highlighted in this manual. Safety markings should not be ignored and are used frequently throughout to designate a degree or level of seriousness.

Model/option/voltage applicability is listed in Table 1.

Table 1. Model/Voltage/Option Applicability

ModelVoltage/PhaseOption for Control UnitOption for Non-Control Unit(s)No. of Non-Control Units Permitted
APD, UDAP, UDAS, UDBP, UDBS115/1, 208/1, 230/1, 208/3, 230/3, 460/3, 575/3CL31CL324
F, B, VR115/1CL31
208/1, 230/1, 208/3, 230/3, 460/3CL32CL32
575/3CL31
UEAS115/1CL31CL31

*Except as follows: unit size 400 can have five (5) additional non-control units, unit size 800 can have three (3) additional non-control units, and unit size 1200 can have two (2) additional non-control units.

COMPONENTS

Ensure that all components listed in Table 2 are available before beginning installation.

Table 2. Relay Kit Components

APD, UDAP, UDAS, and UEAS Models

Item No.ComponentDescriptionOption CL31 PN (Qty)Option CL32 PN (Qty)
--Option package PN197155 (1)197156 (1)
1Relay assemblyIncludes relay and specially-designed bracket197157 (2)197157 (1)
1ARelayWired and mounted on bracket18549 (2)18549 (1)
2ScrewSelf-drilling, for securing relay bracket195249 (2)195249 (1)
3Cable clamp3/1616228 (2)16228 (1)
4LabelWiring diagram197164 (2)197164 (1)
5Transformer40VA194808 (1)
6Wiring harness assemblyBrown wires197160 (1)

UDBP and UDBS Models

Item No.ComponentDescriptionOption CL31 PN (Qty)Option CL32 PN (Qty)
--Option package PN202958 (2)197156 (1)
1Relay assemblyIncludes relay and specially-designed bracket197157 (2)197157 (1)
1ARelayWired and mounted on bracket18549 (2)18549 (1)
2ScrewSelf-drilling, for securing relay bracket195249 (2)195249 (1)
3Cable clamp3/1616228 (2)16228 (1)
4LabelWiring diagram197164 (2)197164 (1)

F and B Models

Item No.ComponentDescriptionOption CL31 PN (Qty)Option CL32 PN (Qty)
--Option package PN102248 (1)102249 (1)
1Relay assemblyIncludes relay and specially-designed bracket102243 (2)102243 (1)
1ARelayWired and mounted on bracket18549 (2)18549 (1)
2ScrewSheet metal, #6 x 1-1/2, for transformer103152 (2)
2ATinnerman clip#C1110-62, for transformer screws111233 (2)
3Cable clamp3/1616228 (2)16228 (1)
4LabelWiring diagram131127 (2)131127 (1)
5Transformer35VA102708 (1)

VR Models

Item No.ComponentDescriptionOption CL31 PN (Qty)Option CL32 PN (Qty)
--Option package PN205685 (1)205686 (1)
1Relay assemblyIncludes relay and specially-designed bracket102243 (2)102243 (1)
1ARelayWired and mounted on bracket18549 (2)18549 (1)
2Screw#8 x 1121033 (4)121033 (2)
2ASpacer98872 (4)98872 (2)
3Cable clamp3/1616228 (2)16228 (1)
4LabelWiring diagram197164 (2)197164 (1)
5Transformer40VA194808 (1)
5AWire connectorTwist-on, orange16354 (1)

*See Figure 1 and Figure 2.

**Option CL31 includes components for one control unit and one additional unit. Option CL32 includes components for each additional non-control unit with the following exception: for 208V, 230V, and 460V F, B, and VR models, option CL32 is used for the control unit and each additional non-control unit (refer to Table 1).

INSTALLATION

Install the relay kit as follows. Item numbers refer to Table 2.

  1. Turn OFF gas and electric power.
  2. Replace transformer on control unit (all models except UDBP and UDBS):
    1. Remove or open panel(s) as necessary and locate factory-installed transformer (see Figure 1).
      1. For models APD, UDAP, UDAS, and UEAS, transformer is mounted on control board at bottom of control compartment.
      2. For models F and B, remove left (when facing rear of heater) outer side panel to expose inner side panel and wiring.
      3. For model VR, open control side only.
    2. Mark and disconnect transformer wires and remove existing transformer.
    3. Install replacement transformer:
      1. For models APD, UDAP, UDAS, UEAS, and VR, secure transformer (5) using same screws.
      2. For models F and B, slide Tinnerman clips (2A) over transformer (5) and secure transformer using screws (2) from kit.
      3. Reconnect transformer wires.
    4. Install or close panel(s) as necessary.
  3. Install relay assembly on control unit and on all non-control units (see Figure 2):
    1. For models APD, APD, UDAP, UDAS, UDBP, UDBS, and UEAS:
      1. At rear of heater, remove screws from edge of cabinet bottom.
      2. Secure relay assembly (1 and 1A) and cable clamp (3) as shown using existing screws for unit sizes 030-125 or one existing screw and one screw (2) from kit for unit sizes 150–400 and all UEAS models.
    2. For models F and B:
      1. At rear of heater, remove thermostat terminal strip screws and remove terminal strip.
      2. Slide relay assembly (1 and 1A) bracket underneath thermostat terminal strip and secure bracket, terminal strip, and cable clamp (3) as shown using existing screws.
      3. Secure blue and brown wires in cable clamp (3).
    3. For model VR:
      1. At end of burner/control box, remove thermostat terminal strip screws and remove terminal strip.
      2. Secure terminal strip, relay assembly (1 and 1A), and cable clamp (3) as shown using screws (2) and spacers (2A).
      3. Secure blue and brown wires in cable clamp (3).

CAUTION

Be careful not to short thermostat leads to a metal surface. Doing so will cause the transformer to fail and require replacement.

INSTALLATION—CONTINUED

Figure 1. Transformer Replacement (Refer to Table 2)

Textual description of Figure 1: The diagram shows three views of transformer replacement. The top left shows models APD, UDAP, UDAS, UEAS, unit sizes 030-125, with a transformer labeled '5' mounted on a control board. The top right shows APD, UDAP, UDAS, UEAS, unit sizes 150-400, also with a transformer labeled '5'. The bottom section shows models F and B with a transformer labeled '5' and wire connector '5A' visible after removing a side panel. The model VR view shows a transformer labeled '5' and wire connector '5A' within the control compartment.

Figure 2. Relay Installation (Refer to Table 2)

Textual description of Figure 2: This figure illustrates relay installation for different models. For APD, UDAP, UDAS, UDBP, UDBS, and UEAS, it shows a relay assembly (1, 1A) and cable clamp (3) being secured near the bottom rear of the unit. For F and B models, it shows the relay assembly (1, 1A) and cable clamp (3) installed under the thermostat terminal strip. For VR models, it shows the relay assembly (1, 1A), cable clamp (3), screws (2), and spacers (2A) installed near the burner/control box terminal strip.

NOTE: VR models do not have a W2 terminal. Splice between the DSI control COM and 24V on the transformer and use the twist-on wire connector (5A) to connect the wires.

4. Connect relay (1A) to TEW-type control wiring in accordance with model-specific wiring diagram label (4) from kit. Do not exceed length and distance listed in Table 3.

Table 3. Control Wiring Specifications

GaugeMaximum Length (Feet (Meters))*Maximum Distance (Feet (Meters))
122100 (640)1050 (320)
141300 (457)650 (198)
18500 (152)250 (76)

*For complete circuit.

5. Install wiring diagram label:

  1. For future reference, check appropriate box for heater function—PRIMARY HEATER for control unit or SECONDARY HEATER for non-control unit—on wiring diagram label (4).
  2. Locate required wiring diagram label position on unit:
    1. For models APD, APD, UDAP, UDAS, UDBP, UDBS, and UEAS, label location is bottom rear corner of access panel.
    2. For models F and B, label location is lower right corner of outer left (when facing rear of heater) side panel.
    3. For model VR, label location is rear of burner box above terminal strip.
  3. Wipe surface with clean, dry cloth.
  4. Remove label backing and adhere label to unit.

6. Restore system to service:

  1. Turn ON gas and electric power.
  2. Light heater in accordance with lighting instructions.
  3. Check for proper operation.

Specifications and illustrations subject to change without notice or incurring obligations. Latest version of this manual is available at www.reznorhvac.com. ©2022 Nortek Global HVAC LLC, O'Fallon, MO. All rights reserved.

Models: APD Relay Kit, APD, Relay Kit

File Info : application/pdf, 4 Pages, 426.37KB

PDF preview unavailable. Download the PDF instead.

OPT-CL31-CL32 (04-22) 102247-B

References

Adobe InDesign 17.1 (Windows) Adobe PDF Library 16.0.5

Related Documents

Preview Reznor Relay Kit Installation Guide for Multiple Unit Control (CL31/CL32)
Comprehensive installation guide for Reznor CL31 and CL32 relay kits, enabling multiple unit control for various Reznor electric and gas-fired heaters. Includes component lists, detailed installation steps, and wiring specifications.
Preview Reznor Relay Kit Installation for Multiple Heater Control (CL31/CL32)
Installation guide for Reznor CL31/CL32 relay kits, enabling multi-heater control for UBX, UBZ, UDX, UDZ, and UEZ models. Covers safety, components, and wiring.
Preview Reznor Unit Heater Replacement Parts Catalog
Comprehensive catalog of replacement parts for Reznor APD, UDAP, UDBP, UDAS, and UDBS unit heaters, detailing electrical, blower, cabinet, venter, and burner assembly components, as well as various accessories and options.
Preview Reznor Stepdown Transformer Kit Installation Guide for Gas-Fired Unit Heaters
Detailed installation instructions for Reznor stepdown transformer kits (CG1, CG2, CG4) for UDAP, UDAS, UDX, UDZ, UDBP, UDBS, UBX, and UBZ gas-fired unit heaters. Includes component lists, wiring guidance, and safety precautions.
Preview Reznor Gas Conversion Kit Installation for Gas-Fired Unit Heaters
This document provides installation instructions for Reznor gas conversion kits for various gas-fired unit heater models, including UBX, UBXC, UBZ, UDX, UDXC, UDZ, UDAP, UDAS, UDBP, and UDBS. It details component selection, safety precautions, and installation steps for converting between natural gas and propane, as well as for high-elevation installations.
Preview Reznor Relay Replacement Kit (PN 259521) Installation Guide
Installation instructions for the Reznor Relay Replacement Kit (PN 259521), designed to replace time delay relays (PN 46233, PN 259518) in Reznor power-vented HVAC units. Includes detailed wiring diagrams and safety warnings for models F and B.
Preview Reznor Vertical Louver Kit Installation Guide for Gas-Fired Unit Heaters (OPT-CD1)
Installation instructions for the Reznor OPT-CD1 Vertical Louver Kit, designed for gas-fired unit heaters (models UBX, UBXC, UBZ, UDX, UDXC, UDZ, UEZ). Includes component list and step-by-step assembly guide.
Preview Reznor Fan Control Replacement Kit (PN 209184) Installation Guide
Instructions for installing the Reznor replacement kit (PN 209184) for discontinued fan controls on Thermocore® 1 heat exchanger duct furnaces and packaged systems. Includes component list and step-by-step installation procedures.