RELAY KIT INSTALLATION FOR MULTIPLE HEATER CONTROL

OPTIONS CL31 AND CL32 FOR MODELS UBX, UBZ, UDX, UDZ, AND UEZ

Safety Precautions

  • ⚠️ CAUTION ⚠️
  • DO NOT use these multiple heater control options with a two-stage gas valve or a two-stage thermostat.
  • These instructions are designed to assist a qualified electrician in installing this multiple heater control kit.
  • All electrical wiring and connections, including electrical grounding, MUST be in accordance with the National Electric Code ANSI/NFPA No. 70 (latest edition) or, in Canada, with the Canadian Electrical Code, Part 1, CSA Standard C22.1. In addition, the installation must comply with local ordinances and applicable gas company requirements.
  • These relay kits are designed to permit the control of up to five heaters (one control unit and up to four additional non-control units) with one single-stage thermostat or with a time clock and single or multiple single-stage thermostats. For maximum safety, the multiple control is installed in the low voltage circuit. Interruption of the supply voltage is not recommended.
  • Refer to the installation manual provided with the heater for important safety information.
  • Pay attention to all dangers, warnings, cautions, and notes highlighted in this manual. Safety markings should not be ignored and are used frequently throughout to designate a degree or level of seriousness.
  • Model/option/voltage applicability is listed in Table 1 and kit components are listed in Table 2. Ensure that all components listed in Table 2 are available before beginning installation.

Model/Voltage/Option Applicability

ModelVoltage/PhaseOption for Control UnitOption for Non-Control Unit(s)No. of Non-Control Units Permitted
UBX, UBZ, UDX, UDZ115/1, 208/1, 230/1, 208/3, 230/3, 460/3, 575/3CL31CL324
UEZ115/1

Relay Kit Components

Note: Option CL31 includes components for one control unit and one additional unit. Option CL32 includes components for each additional non-control unit.

Item No.*ComponentDescriptionModel
UBX, UBZUDX, UDZ, UEZ
CL31CL32CL31CL32
Kit PNKit PNKit PNKit PN
1041281104128710412881041287
1Relay assemblyIncludes relay and specially-designed bracket197157 (2)197157 (1)197157 (2)197157 (1)
1ARelayWired and mounted on bracket18549 (2)18549 (1)18549 (2)18549 (1)
2ScrewSelf-drilling, for securing relay bracket195249 (2)195249 (1)195249 (2)195249 (1)
3Cable clamp3/1616228 (2)16228 (1)16228 (2)16228 (1)
4LabelWiring diagram197164 (2)197164 (1)197164 (2)197164 (1)
5Transformer40VA194808 (1)------
6Wiring harness assemblyBrown wires--197160 (1)----

*See Figure 1 and Figure 2.

**Option CL31 includes components for one control unit and one additional unit. Option CL32 includes components for each additional non-control unit.

Installation

  1. Turn OFF gas and electric power.
  2. Replace transformer on control unit (models UDX, UDZ, and UEZ):
    • Remove or open panel(s) as necessary and locate existing transformer (see Figure 1) mounted at top of control compartment for unit size 055–110 UEZ models or on control board at bottom of control compartment for unit size 130–310 UEZ and all UDX and UDZ models.
    • Mark and disconnect transformer wires.
    • Remove screws that secure existing transformer and remove transformer.
    • Install replacement transformer (5) and secure using existing screws.
    • Reconnect transformer wires.
    • Install or close panel(s) as necessary.

    Figure 1. Transformer Location (Refer to Table 2): This diagram illustrates the transformer's position within different heater models. For UEZ models (055-110), the transformer is at the top of the control compartment. For UDX, UDZ (030-125), and UDX, UDZ (150-400) / UEZ (130-310) models, the transformer is located on the control board at the bottom of the control compartment.

  3. Install relay assembly on control unit and on all non-control units (see Figure 2):
    • At rear of heater, remove screws from edge of cabinet bottom.
    • For model UBX, UBZ, UDX, and UDZ unit sizes 150–400 and all UEZ models, align relay assembly (1) bracket as shown and use bracket as template to drill hole in edge of cabinet bottom as shown.
    • Secure relay assembly (1 and 1A) and cable clamp (3) as shown using existing screws for model UBX, UBZ, UDX, and UDZ unit sizes 030–125 or one existing screw and one screw (2) from kit for model UBX, UBZ, UDX, and UDZ unit sizes 150–400 and all UEZ models.

    Figure 2. Relay Installation (Refer to Table 2): This diagram shows the relay assembly installation. For UBX, UBZ, UDX, and UDZ unit sizes 150-400 and all UEZ models, align the relay assembly bracket and drill a hole in the cabinet bottom edge. Secure the relay assembly (1 and 1A) and cable clamp (3) using existing screws for UBX, UBZ, UDX, UDZ (030-125) models, or one existing screw and one kit screw (2) for UBX, UBZ, UDX, UDZ (150-400) and all UEZ models.

  4. Connect relay (1A) to TEW-type control wiring in accordance with model-specific wiring diagram label (4) from kit. Do not exceed length and distance listed in Table 3.
    GaugeMaximum Length (Feet (Meters))*Maximum Distance (Feet (Meters))
    122100 (640)1050 (320)
    141300 (457)650 (198)
    18500 (152)250 (76)

    *For complete circuit.

  5. Install wiring diagram label:
    • For future reference, check appropriate box for heater function—PRIMARY HEATER for control unit or SECONDARY HEATER for non-control unit—on wiring diagram label (4).
    • Locate required wiring diagram label position on bottom rear corner of access panel.
    • Wipe surface with clean, dry cloth.
    • Remove label backing and adhere label to unit.
  6. Restore system to service:
    • Turn ON gas and electric power.
    • Light heater in accordance with lighting instructions.
    • Check for proper operation.

Be careful not to short thermostat leads to a metal surface. Doing so will cause the transformer to fail and require replacement.

Additional Information

Specifications and illustrations subject to change without notice or incurring obligations.

Latest version of this manual is available at www.reznorhvac.com.

©2022 Nortek Global HVAC LLC, O'Fallon, MO. All rights reserved.

Document Revision: UBX-UBZ-UDX-UDZ-UEZ-CL31,32 (05-22) 1041279-A

Models: UBX, Unit Heater, UBX Unit Heater, UBZ, UDX, UDZ, UEZ

File Info : application/pdf, 4 Pages, 275.00KB

PDF preview unavailable. Download the PDF instead.

UBX-UBZ-UDX-UDZ-UEZ-CL31,32 (05-22) 1041279-0

References

Adobe InDesign 17.2 (Windows) Adobe PDF Library 16.0.7

Related Documents

PreviewReznor Downturn Nozzle Kit Installation Guide for Unit Heaters
Installation instructions and component lists for Reznor downturn nozzle kits (OPT-CD2,3,4,5) for UBX, UBXC, UBZ, UDX, UDXC, UDZ, UEZ, and UWS unit heaters.
PreviewReznor Vertical Louver Kit Installation Guide for Gas-Fired Unit Heaters (OPT-CD1)
Installation instructions for the Reznor OPT-CD1 Vertical Louver Kit, designed for gas-fired unit heaters (models UBX, UBXC, UBZ, UDX, UDXC, UDZ, UEZ). Includes component list and step-by-step assembly guide.
PreviewReznor Downturn Nozzle Kit Installation Guide
This guide provides detailed instructions for installing Reznor downturn nozzle kits (CD2, CD3, CD4, CD5) on various Reznor unit heater models including UBX, UBXC, UBZ, UDX, UDXC, UDZ, UEZ, and UWS. It covers kit components and step-by-step installation procedures for both gas-fired and hydronic units.
PreviewReznor Vertical Louver Kit Installation Guide for Unit Heaters
Comprehensive installation guide for the Reznor Vertical Louver Kit (Option CD1) for gas-fired and hydronic unit heaters. Includes part lists, step-by-step instructions, and safety information.
PreviewReznor Vertical Louver Kit Installation Guide for Unit Heaters (Option CD1)
Installation instructions for the Reznor Option CD1 Vertical Louver Kit, designed for UBX, UBZ, UDX, UDZ, and UEZ model unit heaters. Includes component lists and step-by-step assembly guidance.
PreviewReznor CL31/CL32 Relay Kit Installation Guide for Multiple Heater Control
Comprehensive installation guide for Reznor CL31 and CL32 relay kits, enabling multiple heater control for models APD, F, B, UDAP, UDAS, UDBP, UDBS, UEAS, and VR. Includes component lists, safety precautions, and wiring specifications.
PreviewReznor Stepdown Transformer Kit Installation Guide for Gas-Fired Unit Heaters
Detailed installation instructions for Reznor stepdown transformer kits (CG1, CG2, CG4) for UDAP, UDAS, UDX, UDZ, UDBP, UDBS, UBX, and UBZ gas-fired unit heaters. Includes component lists, wiring guidance, and safety precautions.
PreviewReznor Gas Conversion Kit Installation for Gas-Fired Unit Heaters
This document provides installation instructions for Reznor gas conversion kits for various gas-fired unit heater models, including UBX, UBXC, UBZ, UDX, UDXC, UDZ, UDAP, UDAS, UDBP, and UDBS. It details component selection, safety precautions, and installation steps for converting between natural gas and propane, as well as for high-elevation installations.