iStore Home CSIP-AUS Compliant Commissioning Guide
Required Commissioning Applications
- HiSolar: Local Commissioning of device.
- Univers EMS: Monitoring platform for fleet management and end user.
Required Hardware for CSIP-AUS sites
- WLAN Dongle
- Applicable iStore Smart Meter
Prior to first iStore installation please email: pv.support@istore.net.au to ensure your retailer/company has a fleet portal.
Technical Support: 08 9550 1585 (option 2)
8:00am EST – 5:00pm WAST
HiSolar Application - Commissioning Steps
- Open Hisolar Application.
- Scan the inverter QR code > login as the installer and set the inverter password (recommend implementing a standard password for all inverters such as istore00).
- Follow the prompts to set the basic parameter and continue to device management via quick settings.
3.1 Basic parameter settings
[Screenshot showing basic parameter settings: Grid code, Sync phone time, Time, Time zone]
3.2 Automatic Device Scan
[Screenshot showing automatic device scan: Inverter, Dongle, Power meter, Battery, Optimizer status]
TIP: To avoid waiting for optimizer scan, please turn inverter ON ten minutes prior to commissioning.
4. Communication networking settings
Authority from the user to connect to management system: Ticked for approval
Domain name: modbusbroker.istore.net.au
Port number: 27250
TLS Encryption: Enabled
4.1 Initial page settings
[Screenshot showing initial page settings for communication networking]
4.2 Page settings once amended
[Screenshot showing amended page settings for communication networking]
5. Use drop down arrow to select applicable WIFI network and password.
6. Once settings are complete, select finish and disconnect from inverter Wi-Fi access point.
[Screenshot showing final confirmation and completion]
Enabling MODBUS Communication via HiSolar
If the system requires additional CSIP-AUS DER controls, follow these steps to enable MODBUS communication via HiSolar:
- Select SET
- Select Dongle parameter settings
- Select Modbus TCP
- Select enabled (unrestricted)
[Screenshots demonstrating the steps to enable Modbus TCP]
Firmware Update Instructions
If the system requires additional CSIP-AUS DER controls, ensure the inverter has the applicable CSIP-AUS firmware installed. Contact tech support or download firmware from the iStore google drive.
Firmware Update Steps:
- Select the zip file received.
- Select "share file via".
- From the list of apps, select HiSolar.
[Screenshot showing file sharing process]
- Via HiSolar, select Maintenance.
- Select Upgrade.
- Select Inverter Update.
- Select the package previously uploaded.
- Select "Upgrade".
- The inverter will then do an update and reset itself.
[Screenshots showing inverter update process]
*This concludes the HiSolar Commissioning requirements.
Univers EMS Application - Commissioning Steps
- Open Univers EMS application.
- Once logged in to portal select plant guide > scan QR code of device.
- This will prompt you to the plant creation section.
[Screenshots showing plant creation process in Univers EMS]
4. Complete basic information and select next.
5. Ensure the correct NMI and Network Provider are listed (crucial for CSIP-AUS sites).
[Screenshot showing basic information input for a new plant]
Note: Country/Region refers to council region.
5. Set applicable tariffs (if known)
[Screenshot showing tariff settings]
6. Select save.
[Screenshot showing save options]
At this point, the plant will be set up and commissioned.
*Please follow the steps on the next page to add end user permissions.
Adding End User Permissions
- Select Management tab > Users tab > select + sign.
- Select "user" under role tab > select customer plant under related plant > username > email > authority tick. (Service provider will be pre-set to applicable fleet).
[Screenshots showing the process of adding a user]
Once complete, end user will receive an email from iStore prompting them to set their password.
File Info : application/pdf, 9 Pages, 1.02MB
DocumentDocumentReferences
Microsoft Word for Microsoft 365Related Documents
![]() |
iStore PV Products Warranty and Service Conditions Detailed warranty and service conditions for iStore solar inverters, batteries, and accessories, including product coverage, warranty periods, support services, and exclusions, as per Australian Consumer Law. |
![]() |
iStore Energy Storage User Manual: IS-BATT-5000-S0, IS-BATT-10000-S0, IS-BATT-15000-S0 Comprehensive user manual for iStore Energy Storage systems, covering installation, operation, maintenance, safety guidelines, and technical specifications for models IS-BATT-5000-S0, IS-BATT-10000-S0, and IS-BATT-15000-S0. |
![]() |
iStore Owner's Manual: Your Guide to Efficient Solar Hot Water Comprehensive owner's manual for the iStore solar hot water system, covering installation, operation, maintenance, troubleshooting, and warranty information. Learn how iStore technology provides efficient and environmentally friendly hot water. |
![]() |
iStore 270L Heat Pump Installation Diagrams Installation diagrams for the iStore 270L heat pump, detailing pre-lay plumbing and electrical requirements, clearances, and positioning guidelines. |
![]() |
iStore Heat Pump: Pre-Lay Plumbing and Electrical Installation Guide Comprehensive guide for iStore heat pump pre-lay plumbing and electrical installation, detailing unit dimensions, connection points, required clearances, and installer responsibilities. |
![]() |
iStore 180L R290 Heat Pump Water Heater Owner's Manual Comprehensive owner's manual for the iStore 180L R290 heat pump water heater, covering installation, operation, maintenance, safety, troubleshooting, and warranty information. |
![]() |
iStore 270L/R290 Heat Pump Hot Water System Installation Manual This installation manual provides comprehensive guidance for the iStore 270L/R290 heat pump hot water system. It covers essential safety precautions, installation procedures, dimensions, performance specifications, operational functionality, maintenance, troubleshooting, and warranty terms. Designed for licensed installers and end-users, it ensures safe and efficient operation. |