Affected System Operator (ASO) Report to Potentially Affected Customers

Date: April 15, 2024

Updates are Noted in Red

Introduction

This is Eversource's biweekly report to customers who have the potential to be included in a future Affected System Operator (ASO) study. In accordance with the MA DPU Orders D.P.U. 19-55-C, D.P.U. 19-55-D, and the DG Guidelines For Interconnection, these reports are issued on the first and fifteenth business day of each month. Eversource's Massachusetts service area in the Greater Boston, Upper Southeastern Massachusetts (“SEMA”), Cape, Springfield, and Pittsfield regions have all had ASO studies conducted in the past, and these regions will remain consistent for any future ASO study conducted.

New applications in western MA and Greater Boston areas eligible for Eversource's 2023 ASO study were reviewed for concurrence of study level determinations with ISO-New England and have been posted on Eversource's ASO website. The 2023 ASO study is in progress in Western MA and Greater Boston.

Eversource continues to explore, to the greatest extent possible, the ability for projects to have Level 0 studies.

Current ASO Study Projects

Eversource's current data as of this report reflects the following projects identified as needing a potential ASO study:

This total is a combination of new applications submitted and applications that opted out of a prior ASO study that still require completion.

These reports, along with general ASO information, can be found on the ASO Website: Eversource ASO Studies Website.

Please direct questions related to the ASO to your respective Account Executive. They can be circulated to the appropriate party for response and, if applicable, added to the ASO Website's FAQ section for others to review.

Active ASO Study Status

The current status of each active ASO study is reflected below.

SEMA/Cape:

The 2024 SEMA/Cape ASO study is being performed to complete before August 1, 2024, and get PPA approval at the October RC meeting.

Western MA:

Greater Boston:

Frequently Asked Questions (FAQ)

1. What additional information is needed to determine if an ASO study is necessary?

Eversource needs to complete any ASO studies underway in a region prior to assigning new projects in queue for a transmission study level and starting a new round of studies. At the start of each new study round, Eversource issues initial ASO Study notifications to potential customers impacted, requiring their project be reviewed for study level agreement by ISO-NE for either a Level 0 or a Level 3 ASO study. After there is concurrence on study level for each project between Eversource and ISO-NE, individual projects will be notified of their study level by their Account Executive through Powerclerk and posted on the ASO website.

Factors can impact these preliminary study level determinations, such as queue attrition and project size changes. If a project is initially assigned a Level 0 study, it is possible that during the Level 0 study process, some projects may be identified as requiring further Level 3 studies, and those projects (if any) will add to the final scope of the Level 3 study conducted.

2. When will the EDC know whether an ASO study is required?

Eversource is proceeding with a next round of ASO studies in the Western MA and Greater Boston areas (for applications deemed complete through 1/31/23). Eversource has received concurrence on study levels from ISO-NE for these projects.

Eversource is proceeding with a next round of ASO studies in the SEMA/Cape areas (for applications deemed complete through 2/5/22). Eversource has received concurrence on study levels from ISO-NE for these projects.

For projects submitted in these areas after the cutoff dates, the ASO Impact Screens will continue occurring for these newer projects, and at the earliest opportunity, the projects will be invited to opt in to a future ASO study. Results of the ASO Impact Screens are posted on Eversource's ASO website under Initial Study Level Determinations. Eversource has added the process diagram for ASO Impact Screens, which it developed with the other MA Electric Distribution Companies (EDCs), to its ASO website as an additional customer reference.

3. What are the potential impacts on interconnection timelines and costs?

Level 0 No Study:

Level 0 Transfer Limit Analysis (TLA):

Level 3 Study:

4. Are there any proposed resolutions that the EDC is exploring to enable some affected DG applicants to proceed with the interconnection process prior to completion of the ASO study?

Eversource is continuing to proceed with distribution-level studies, including distribution Group Studies authorized by D.P.U. 17-164, while ASO transmission-level studies are being conducted. This approach is being utilized to reduce the distribution-level study wait time and increase value to customers.

5. How does the EDC plan to address the situation and minimize delays to interconnection timelines of potentially affected DG applicants?

There are distribution study efficiencies that Eversource has implemented to minimize study timelines for highly congested areas warranting the formation of a Group Study. With distribution Group Studies, there will also be an associated group solution to support cost sharing potential amongst customers. For any future transmission studies, Eversource will be able to utilize load models and DER models aggregated by bus that have been set up for the ASO underway and anticipates the ramp-up time for any future ASO study to be shorter, as some preparation work has already been completed.

Eversource has also created technical guidance documentation for customers to utilize to proactively gather modeling data needed for an ASO study; this documentation is available on the ASO website. It is strongly recommended that customers use this documentation to work with their inverter manufacturers and other technical stakeholders early in the process (once an ASO study level is known) to obtain the necessary comprehensive and accurate technical files. All customers will see a benefit to schedule improvement and study commencement. As discussed in these biweekly reports, all projects, regardless of ASO study level, will require PSCAD models for the study.

PDF preview unavailable. Download the PDF instead.

aso-biweekly-report-apr-15-2024 Khederian, Melanie A Adobe PDF Library 17.11.238

Related Documents

Preview Eversource Eastern Massachusetts Net Metering Credit Pricing - August 2025
Eversource provides net metering credit pricing for Eastern Massachusetts, including South Shore, Cape Cod, and Martha's Vineyard, for August 2025. The data details rates across various tariff descriptions, seasons, and time-of-use periods for different customer classes.
Preview Eversource Interconnection Analysis Portal User's Guide
A comprehensive user guide for the Eversource Interconnection Analysis Portal, detailing account creation, organization management, and additional support resources.
Preview Connecticut Electric Vehicle Charging Program: Qualified Chargers & Vehicles
Explore the Connecticut Electric Vehicle Charging Program for residential single-family homes. Learn about incentives like Smart Charger rebates and enrollment incentives for qualifying Level 2 chargers and connected electric vehicles.
Preview Eversource 2020 Sustainability Report: Driving Clean Energy and ESG Excellence
Explore Eversource Energy's 2020 Sustainability Report detailing commitments to environmental stewardship, social responsibility, and robust governance, including clean energy initiatives and community engagement.
Preview Eversource Beebe River to Whitefield (X178) Line Rebuild Project
Information regarding the Eversource Beebe River to Whitefield (X178) Line Rebuild Project, focusing on construction permit maps and project scope.
Preview Mystic and Everett Underground Cable Modernization Project
Information about the Underground Cable Modernization Program for the Mystic and Everett areas, including project scope, timeline, and community engagement.
Preview Eversource 2025 Electric Rates Summary and Definitions
Comprehensive summary of Eversource's electric rates for 2025, detailing residential and commercial service charges, energy rates, and definitions of billing terms. Updated August 1, 2025.
Preview Eversource X178-1 Line Rebuild Project: Technical Specifications and Permit Maps
This document details the technical specifications and construction permit map information for the Eversource X178-1 Line Rebuild Project, aimed at enhancing electrical infrastructure reliability between Beebe River and Whitefield.