Smappee Pay Station Installation Manual

Version: 1.04.1 | Date: August 2025

Document Accuracy

The specifications and other information in this document were verified to be accurate and complete at the time of its publication. Due to ongoing product improvement, this information is subject to change at any time without prior notice. For the latest information, see our online documentation: smappee.com/downloads

Table of Contents

1 Introduction

With the Pay Station, an electric vehicle driver has an additional payment option to use a charging station. One time per month, the charging station owner will be reimbursed for all charging sessions on the charging square via the Smappee CPO services.

This installation manual tells you how to install, configure and use the Pay Station. We recommend that you read the contents of this manual carefully, to ensure a safe and proper installation and enable you to use all the advanced features of this product to their full extent.

Support

Only qualified electricians or equivalent may install the Smappee Pay Station. If you have any questions, please contact your service partner.

Please have the following information ready to hand to speed up the process: Article number and serial number which you can find on the identification label of the Pay Station. For more information, refer to Position of the identification label (page 8).

Should your local distributor be unable to help you, or you have a suggestion for us, you can contact Smappee at: support@smappee.com.

Smappee NV
Evolis 104
8530 Harelbeke
Belgium

2 Safety Instructions

2.1 Safety Warnings and Precautions

WARNING

Carrying out electrical work in a home or workplace can be dangerous. The dangerous parts of the electric equipment of the Pay Station are installed behind the protective cover. The user can safely operate the payment terminal of the Pay Station.

Only certified electricians may carry out the installation, which must be in accordance with the national safety regulations.

CAUTION

Risk of electric shock. Refer to the accompanying documentation whenever you see this symbol [electric shock symbol].

Please observe the following safety precautions to avoid potential electric shock, fire, or personal injury:

2.2 Maintenance

2.3 Transport and Storage

3 Overview of the Pay Station

3.1 Models

Pay Station

Article no.EANDescription
PAY-STATION5425036934467Smappee Pay Station

Accessories (not included)

Article no.EANDescription
FLOOR-PLATE-TUBE1205425036934719Floor plate for EV One or Pay Station 120 mm x 120 mm

3.2 Components

The Smappee Pay Station has the following primary components:

3.3 Directional Determination

Image 1: Directional determination

Diagram showing the Pay Station with numbered points indicating directions:

IdDescription
1Front
2Rear
3Left
4Right
5Top
6Bottom

3.4 Identification Label of the Pay Station

Position of the identification label

The identification label is attached to the inner structure. To remove the outer housing, refer to page 13.

Image 2: Position of the identification label

Diagram showing the internal structure of the Pay Station with the identification label attached.

Content of the identification label

Image 3: Identification label

Diagram of the identification label with numbered fields:

No.Description
1Manufacturer
2Article number
3Serial number
4IP rating and IK rating
5Operating temperature
6Electrical rating
7Manufacturing date
8Address of the manufacturer
9QR code containing article number and serial number
10Waste disposal symbol [recycle symbol]
11CE marking
12EAN code

3.5 Technical Specifications of the Pay Station

FeatureDescription
Physical properties
Dimensions1450 mm x 120 mm x 120 mm
Weight (excluding packaging)11.6 kg
Power supply3G2.5 (1P + N + PE)
Stationary / moveableFixed installation
External designEnclosed assembly
Mounting methodFloor mounted
Technical features
Rating110 / 240 V – 20 W – 50 / 60 Hz
Required external circuit breaker1 x 2P (single-phase) breaker of maximum 20A, type B or C
Product certificationsCE, PCI PTS 6.X, EMVL1/L2, payWave, PayPass, ExpressPay, D-PAS, InteracFlash, J-Speedy, FeliCa, UnionPay UICS, TQM, Mifare, DESfire
Interfaces & Connectivity
Display of the payment terminal5" colour TFT LCD with capacitive touch panel 1280 x 720 pixels
ConnectivityEthernet 100BASE-T, 4G LTE
Environment
Enclosure materialMagnelis (structure), aluminium (housing)
Enclosure standard coloursRAL 7021 (black grey)
Protection degreeIP 54
Mechanical impact protectionIK 10
Environmental conditionsIndoor and outdoor use
Operating temperature-25 °C to 50 °C
Storage temperature-25 °C to 60 °C
Relative humidity0% – 95%, non-condensing
Maximum installation altitude0 – 2000 m
AccessLocations with restricted and non-restricted access

NOTE

The operating temperature assumes the ambient temperature of a product delivered in the default enclosure colour RAL 7021 (black grey). Direct exposure to sunlight may have an adverse effect on the temperature range.

Where products are exposed to the elements of nature, the enclosure can be subject to gradual aging of the material, which can result in product discolouration over time. Therefore, wherever possible, place the product in a sheltered place to optimise the life of the materials.

4 Preparing the Installation of the Pay Station

The first step is to prepare the physical installation of the Pay Station as described in this chapter.

4.1 Installation Prerequisites

NOTE

Make sure that there is at least 100 cm 3G2.5 power supply and 150 cm network cable length available at the location of the Pay Station to be able to connect it easily.

4.2 Tools (not included)

4.3 Supplies (not included)

4.4 Prepare the Foundation for the Pay Station

Context

NOTE

This section is only relevant if you use the optional floorplate to attach the Pay Station. If you use the anchor, go to Prepare the Pay Station (page 13).

A stable and level ground needs to be prepared in advance and there must be a power supply cable and a network cable. The surface of the ground must be solid to allow the usage of concrete anchors and avoid moisture from the soil.

We recommend a levelled concrete foundation at ground level. This can be a polished concrete floor in a parking garage or a flat surface for installation of the charging stations and a Pay Station.

Instructions

Proceed as follows.

  1. Make a foundation hole large enough.

    Depending on the subsoil, the size may vary. Please refer to the technical specifications of size and weight to determine and construct a solid foundation for the Pay Station.

    When dimensioning the foundation, it is advisable to carry out a static load capacity analysis according to the relevant standards.

    Image 4: View on the minimum dimensions (A x B = 0.40 m x 0.40 m or 1.31 ft x 1.31 ft)

    Diagram showing minimum dimensions for the foundation hole.

  2. Route the power supply cable and the network cable to the location of the Pay Station.

    Image 5: Example of a solid foundation (C), with cables (D) in a flexible conduit system (E)

    Diagram showing a solid foundation with cables in a flexible conduit system.

  3. Fill foundation hole with concrete.

    Wait for the concrete to cure before going to the next steps.

4.5 Prepare the Pay Station

Context

For safe and compact transport of the Pay Station:

You need to prepare the Pay Station for installation.

Instructions

Proceed as follows.

  1. Remove the cardboard packaging.

    Keep in mind to store the cardboard, as this can be used to safely store the outer housing while installing the Pay Station.

  2. Unscrew the two bottom screws at the front that hold the outer housing.

    Make sure to keep the screws for later closure of the Pay Station.

    Image 6: Front view on the Pay Station

    Diagram showing the front view of the Pay Station with screws to be removed.

  3. Slide the outer housing upwards, of the internal structure.

    NOTE

    The internal structure can be divided into two parts in function of a smooth installation of the anchor. We recommend that you do not skip the next steps 4 and 5.

  4. Unscrew the four nuts that hold the top part of the Pay Station.

    Make sure to keep all fasteners.

    Image 7: Rear view on the Pay Station

    Diagram showing the rear view of the Pay Station with nuts to be removed.

  5. Remove the top part of the Pay Station and set it aside in a safe location.

    No wires need to be disconnected, nor components removed.

    As a result, the Pay Station is prepared for the next steps.

4.6 Assemble the Anchor of the Pay Station

Context

NOTE

This section is only relevant if you install the Pay Station at ground level with the supplied anchor. If you use the floorplate, go to Installation and configuration (page 17).

Instructions

Proceed as follows.

  1. Remove the anchor components from the inner structure.

    Unscrew the two nuts that hold the three anchor components to the inner structure.

    Image 8: Rear view on the bottom part of the Pay Station

    Diagram showing the bottom part of the Pay Station with anchor components.

  2. Attach the component (1) to the inner structure (3).

    • Use the supplied lock nuts.
    • Make sure it is attached to the open side of the inner structure.
    • Make sure its lip is at the outer side.
  3. Attach the two components (2) to the left and right of the inner structure (3).

    There is no specified left or right component.

    Image 9: Rear view on the anchor assembly

    Diagram showing the rear view of the anchor assembly with components 1, 2, and 3.

As a result, the anchor is ready for installation.

4.7 Install the Anchor of the Pay Station

Context

NOTE

This section is only relevant if you install the Pay Station at ground level with the supplied anchor. If you use the floorplate, go to Installation and configuration (page 17).

A stable and level ground needs to be prepared in advance. We advise a levelled concrete foundation at ground level minus the height of the anchor (40 cm).

The open side of the inner structure gives the rear of the Pay Station. The top of the lip gives the bottom of the Pay Station.

Instructions

Image 10: Rear view on the anchor installation

Diagram showing the anchor installation process.

Proceed as follows.

  1. Make a foundation hole large enough to accommodate the anchor.

    Depending on the subsoil, the size may vary. Please refer to the technical specifications of size and weight to determine the dimensions for a solid foundation for the Pay Station.

  2. Route the power supply and optional network cable in a flexible conduit system through the inner structure of the Pay Station.

  3. Fill the foundation hole with concrete.

    • It is normal that some concrete gets into the holes, which makes the anchor better attached to the foundation.
    • Make sure the top of the lip is above the concrete.
    • Make sure the inner structure is level in all directions.

    NOTE

    • Use two magnetic spirit levels to easily adjust the angle of the anchor.
    • Use concrete with very fast hardening to keep the angle of the anchor.

    Wait for the concrete to cure before going to the next steps.

5 Installation and Configuration

CAUTION

The installation must be carried out by a qualified professional who has read this manual and works in compliance with IEC 60364 standards. Neglecting this may lead to severe injuries or hazardous situations while working with electricity.

CAUTION

The electric system must be entirely disconnected from every power source prior to performing installation or maintenance work. Make sure it is not possible to connect the electric current during installation. Put up caution tape and warning signs to mark the work areas. Make sure no unauthorised people can enter the work areas.

CAUTION

The Pay Station contains electric components that may still contain electrical charge after being disconnected. Wait at least 10 seconds after disconnection before commencing work.

This procedure describes the required steps for the physical installation of the Pay Station:

  1. Attach the Pay Station (page 17)
  2. Connect the power supply of the Pay Station (page 21)
  3. Connect the Pay Station to the internet (page 22)
  4. Complete the installation of the Pay Station (page 23)

After the physical installation, the configuration can be done. For more information, refer to Configure the Pay Station (page 24).

5.1 Attach the Pay Station

The supplied anchor or a floorplate must be used to attach the Pay Station. For more information, refer to:

Attach the Pay Station to the Anchor

Context

NOTE

This section is only relevant if you use the supplied anchor to attach the Pay Station. If you use the floorplate, refer to Attach the Pay Station to the floorplate (page 19).

You have divided the Pay Station into two parts and used the bottom part during installation of the anchor. For more information, refer to:

Instructions

Attach the top part to the bottom part. Make sure to use the fasteners.

Image 11: Rear view on the Pay Station

Diagram showing how to attach the top part to the bottom part.

Attach the Pay Station to the Floorplate

Prerequisites

NOTE

This section is only relevant if you use the optional floorplate to attach the Pay Station. If you use the anchor, refer to Assemble the anchor of the Pay Station (page 13).

We recommend a levelled concrete foundation at ground level. This can be a polished concrete floor in a parking garage or a flat surface for installation of the charging stations.

Route the power supply cable and the network cable through the central opening of the floorplate.

Context

Image 12: View on the image from the quick install guide

Diagram illustrating the floorplate installation steps.

Instructions

  1. Put the floorplate in the correct position.

    Pay attention to turn it with the FRONT indication to the side where the payment terminal will come.

  2. Drill the four holes of Ø 8 x 70 mm.

    Make sure the hole is free of small particles.

  3. Attach the floorplate to the foundation.

    Insert the anchor screw until the head is at the same level as the floorplate. Use a hammer if necessary.

    Tighten the screws to 10 Nm with a hex key 4.

  4. Put the cover plate over the floorplate.

    There is only one direction the studs fit into the holes at the front.

  5. Put the structure over the floorplate.

    Move vertically in the slot and then move horizontally.

  6. Tighten the four nuts.

    The nuts are supplied with the Pay Station.

    Tighten the nuts to 5 Nm with an 8 mm socket.

As a result, the structure is locked to the floorplate.

5.2 Connect the Power Supply of the Pay Station

Context

A Pay Station has its own circuit breaker. For more information, refer to Installation prerequisites (page 11).

Instructions

  1. Guide the power supply cable through the cable gland.

    Tighten the cable gland.

    Image 13: View on the holes for the cable entry

    Diagram showing the cable entry point.

  2. Cut the power supply cable to the sufficient length.

    For stranded wires, add a wire end ferrule to each conductor.

  3. Connect the power supply wires as follows:

    Image 14: View on the power supply connection

    Diagram showing power supply connection terminals: PE (green/yellow), N (blue), L1 (brown).

    • Connect the neutral conductor to the blue terminal block N.
    • Connect the phase conductor to the brown terminal block L1.
    • Connect the protective earth conductor to the green/yellow terminal block PE.

As a result, the Pay Station is almost ready for power.

5.3 Connect the Pay Station to the Internet

Context

NOTE

This section is only relevant if you use a wired internet connection for the Pay Station. If you use wireless connection, go to Complete the installation of the Pay Station (page 23).

Instructions

Proceed as follows.

  1. Guide the network cable through the cable entry.

    For the optional network cable, you will need to cut a small cross into the rubber seal.

    Image 15: View on the holes for the cable entry

    Diagram showing the network cable entry point.

  2. Cut the network cable to the necessary length.

  3. Attach the RJ45 connector (not supplied).

  4. Put the connector in the RJ45 port.

    Image 16: View on the RJ45 port

    Diagram showing the RJ45 port connection.

As a result, the installation can be completed.

5.4 Complete the Installation of the Pay Station

Prerequisites

CAUTION

Risk of electric shock. Make sure no tools are in the Pay Station and people stand free from the Pay Station.

Instructions

Image 17: Front view on the Pay Station

Diagram showing the front view of the Pay Station during final steps.

Proceed as follows.

  1. Take a photo of the identification label.

    For more information, refer to Position of the identification label (page 8).

    The identification label has necessary information to configure the Pay Station.

  2. Slide the housing over the inner structure.

    Make sure the opening is in line with the payment terminal on the inner structure.

  3. Tighten the screws at the bottom of the housing.

    These screws are removed when preparing the installation (page 13).

  4. Start the power supply to the power supply cable.

    The display shows a QR code for configuration by your customer.

As a result, the Pay Station is ready to be configured.

5.5 Configure the Pay Station

Context

Smappee Services will configure the Pay Station on the charging square according to the needs of the charging station owner.

NOTE

The charging station owner:

  • Must be registered for Smappee CPO services. For more information, refer to dashboard.smappee.net/register-charging-host.
  • Must onboard the organisation for one or more payment terminals. For more information, refer to "How to onboard the Smappee Pay Station?" – Support.
  • Should put a marker of the connector number adjacent to each connector of the charging stations. If a charging station has displays, the connector number can be put on the display image.

Instructions

Send an email, refer to Necessary information to configure the Pay Station (page 27).

As a result, Smappee Services will configure the Pay Station of your charging square and contact you when the Pay Station can be used. For more information, refer to Using the Pay Station (page 25).

6 Using the Pay Station

The users of a charging square can start and stop charging sessions from the Pay Station.

6.1 Start a Charging Session

Use the payment terminal as follows to start charging:

  1. Connect your electric vehicle to the charging station.

    NOTE

    The charging station display shows:

    • The electric vehicle is connected, so you know you can go to the Pay Station.
    • The connector number, which you'll need to select on the payment terminal display.

    If the charging station has no display:

    • The LED of the charging point goes from white to blue, to show the vehicle is connected.
    • Read the connector number adjacent to the charging point, to select on the payment terminal display.
  2. Go to the Pay Station.

    The payment terminal display shows the following instructions.

  3. Select the connector number of your connected EV to start the charging session.

    NOTE

    The payment terminal display only shows connector numbers:

    • Which have a connected electric vehicle.
    • Where no charging session has been started.
  4. Offer your payment method, if applicable:

    • Tap your physical or digitalised payment card in front of the payment terminal display.
    • Insert your electronic payment card in the slot on the bottom of the payment terminal.
    • Swipe your electronic payment card through the slot on the right side of the payment terminal.

As a result, your charging session starts.

6.2 Stop a Charging Session

Context

You can stop charging:

Instructions

Proceed as follows.

  1. Offer your payment method.

    For more information, refer to page 25.

    The payment terminal display shows the following instructions.

  2. Select the charging station with your connected EV to stop the charging session.

As a result, you can disconnect the charging cable.

Annexes

Necessary Information to Configure the Pay Station

Mail to: Onboarding@smappeeservices.com

Subject: Necessary information to configure my Pay Station

Hi there,

The Smappee Partner completed the installation of the Pay Station(s). Please find below the necessary information for the configuration:

The configuration should be as follows, so that only these charging points can start a charging session from the related Pay Station:

Connector number (A)Serial number of the charging station (B)Pay Station 1 (C)Pay Station 2 (D)
1
2
3
4
5
6
7
8
9
10

(*) Each Pay Station has a serial number in the format with 7000xxxxxx. See the photo taken during installation, refer to Complete the installation of the Pay Station (page 23).

(A) Each connector gets a number, which will be shown on the payment terminal display.

(B) Each charging station has a serial number in the format 6xxxxxxxxx. If the charging station has two connectors, repeat the serial number in the next row.

(C), (D) Put an X in the column if the charging point must be shown on this Pay Station. Pay Station 2 and any additional columns are optional.

Declaration of Conformity

We, Smappee nv, Evolis 104, B-8530 Harelbeke, Belgium, following the provision of the following EC Directives:

hereby declare that the product: SMAPPEE PAY STATION is in conformity with the applicable requirements.

Harelbeke, Belgium, April 16, 2024

Authorized signatory

Stepan Sporzion
CEO Smappee

Maintenance Schedule

To ensure safe and reliable operation, periodic maintenance and inspections are recommended. The frequency depends on usage and environmental conditions.

WARNING

Before starting maintenance activities, consider all safety precautions as listed in Safety instructions (page 5).

TaskMore Information
Visual inspection of the Pay StationCheck for visible damage or wear. If necessary, consult an installer for assessment or replacement.
CleaningCleaning is optional and does not affect the operation of the Pay Station. For aesthetic reasons, you may wipe the unit with a dry, clean cloth. Do not use water jets, solvents, or abrasive materials.
Models: Navigating EV Charging Costs, EV Charging Costs, Charging Costs

File Info : application/pdf, 29 Pages, 1.22MB

PDF preview unavailable. Download the PDF instead.

installation-manual pay-station 1.04.1 en

References

Adobe PDF Library 25.1.150

Related Documents

Preview Smappee Pay Station Installation Manual
Comprehensive installation manual for the Smappee Pay Station, covering setup, configuration, safety guidelines, and usage for electric vehicle charging points. Includes technical specifications and compliance information.
Preview Smappee EV Charging, Energy Management & Battery Storage Catalogue
Comprehensive catalogue of Smappee's advanced EV charging solutions, energy management systems, and battery storage products, including EV One, EV Wall, EV Ultra, Genius, BESS, and more.
Preview Smappee Pay Station : Manuel d'installation - Guide Complet pour Bornes de Recharge Électrique
Ce manuel d'installation détaillé guide les professionnels dans la mise en place, la configuration et l'utilisation de la Smappee Pay Station, une solution de paiement pour bornes de recharge de véhicules électriques. Retrouvez toutes les spécifications, procédures et conseils pour une installation réussie.
Preview Smappee EV Wall: Compact AC Charging Station for Home and Business
Discover the Smappee EV Wall, a compact and wall-mounted AC charging station designed for home and business use. Learn about its key features, technical specifications, and installation simplicity.
Preview Smappee EV Wall Technical Specifications and Features
Detailed technical specifications, features, and operational details for the Smappee EV Wall, a compact AC charging station for home and business use. Covers dimensions, weight, operating conditions, connectivity, charging capabilities, and safety features.
Preview Smappee EV One Technical Specifications and Features
Detailed information on the Smappee EV One, a floor-mounted EV charging station for home and business use. Covers features, technical specifications, installation, and charging capabilities.
Preview Smappee EV One Technical Specifications and Features
Detailed information on the Smappee EV One, a ground-mounted EV charging station for home and business. Covers features, specifications, dimensions, and connectivity.
Preview Smappee EV Base Technical Specifications and Features
Detailed information on the Smappee EV Base, an AC charging station for home and business. Covers features, technical specifications, enclosure details, charging capabilities, and connectivity.