Savant Power Storage Generator Installation and ATS Integration Guide

Document Number: 009-2450-00

Document Date: August 2024

Document Supports: da Vinci 10.5.5 and higher

Introduction

This document serves as a supplemental guide and guides the installer through the process of installing a generator and/or automatic transfer switch with an existing Savant Power Storage system (PS20 or PS50) configured using the Savant Power Storage App and either RacePoint™ Blueprint or the Savant Power & Light App. Visit the Getting Started - Installer page, or the Savant Power Documentation Portal for Savant Community users to review the relevant documentation listed below before continuing with the steps outlined in this guide:

Copyright © 2024 Savant Systems Inc.

Address: 45 Perseverance Way, Hyannis, MA 02601

Website: Savant.com/power | Phone: 508.683.2500

1. Before You Begin

NOTE: It is the design engineer and installer's responsibility to ensure that appropriate provisions are in place at the customer's site to allow the SPS system to connect, control, and communicate with the generator. This also includes any additional generator controller programming coordination required by the generator manufacturer. Always check the generator manual or contact the generator manufacturer for the engine start requirements and generator exercising procedures.

It is the design engineer's responsibility to ensure the generator, and any associated Over Current Protection (OCP) devices are appropriately sized to handle charging each battery stack while ensuring the downstream critical loads are also powered.

A 120V/240V line is required from utility to the generator for the battery charger transformer inside the generator.

2. Generator to GEN Terminal Installation

Installation steps for a Generator to GEN Terminal design include physical wiring, configuration with the Savant Power Storage app, and configuration using the Savant Power & Light app or RacePoint Blueprint software.

When off grid, a Generator to GEN Terminal installation allows the batteries of the SPS system to be charged via a generator in the following manner:

  1. When an individual battery stack discharges and reaches its generator starting state of charge (determined by the Savant Power Storage app. See section 2.2), the inverter calls on the generator to start during a power outage.
  2. Once the generator has warmed up and the SPS unit has qualified the generator signal at the SPS GEN terminal, the generator then starts charging the battery stack while also supplying the downstream house loads.
  3. The inverter stops the generator once the battery reaches its generator stopping state of charge parameter (determined by the Savant Power Storage app. See section 2.2).

NOTE: In a Generator to GEN Terminal parallel system design, only one battery stack can be charged at a time. All other battery stacks go into "standby mode" and pass through generator power through the inverter to feed the loads.

IMPORTANT! The generator must be sized accordingly to feed all critical loads and charge the batteries at the same time.

2.1. Physical Installation

Follow the instructions below to install a generator with an existing Savant Power Storage system. See Appendix: Generator to GEN Terminal Wiring Diagram for wiring example.

  1. Connect the AC output and ground terminal of the generator into all SPS GEN terminals (L1/L2/N/G). This can be done either directly onto the SPS GEN terminals or through a Generator Combiner Breaker Panel for a parallel SPS configuration. Ensure an OCPD is present upstream of the each SPS GEN terminal, properly sized for the generator with a maximum rating of 100A/2P.
  2. Connect generator 2-wire START/STOP control wiring to every parallel SPS unit (see figure below). The SPS generator START/STOP functionality is controlled via a normally open (NO) dry contact.

NOTE: The inverter for both the PS20 and PS50 are identical.

Diagram Description: A diagram illustrates the physical connections for a Generator to GEN Terminal installation. It shows the Savant Power Director and Network Switch connected via Ethernet. The SPS Inverter is depicted with its GRID, LOAD, and GEN terminals. The generator's AC output and ground are connected to the GEN terminals (L1, N, L2, G). A 2-WIRE START/STOP control connection is shown from the generator to the "CONNECTIONS TO GENERATOR" block on the SPS Inverter. A LEGEND defines wire types: LOW VOLTAGE, LINE 2, LINE 1, NEUTRAL, GROUND, ETHERNET.

2.2. Generator to GEN Terminal Savant Power Storage App Setup

Use the Savant Power Storage (SPS) App to program the AUTO-START/STOP parameters of the connected generator for each SPS system.

From the Settings menu in the SPS App, navigate to Connected Power Sources and access the Generator Port page to configure the following fields:

  1. Select Generator mode.
  2. Input Maximum Power output value of the generator. This is the maximum usable continuous power budget that each SPS unit draws from the generator to supply the downstream load and charge its own battery stack (up to 24kW/100A). Priority is given to supplying the downstream loads first. Remaining power (within the constraints of this budget) goes to charging its own battery stack.
    • Single unit installation: This value equals the maximum usable size (kW) of the generator connected to the system.
    • Parallel unit installation: This value equals the maximum usable size (kW) of the generator divided by the number of SPS units connected in the system.
    NOTE: The maximum usable size of the generator shall be determined by the EOR "Engineer on Record” and/or per the generator manufacturer's instructions. Most generator manufacturers prefer their gensets run at 80% duty and therefore this value shall be taken into consideration when sizing the generator for handling downstream critical loads and charging each battery stack.
  3. Input Starting SOC value. This is the state of charge percentage the battery must reach before the SPS unit automatically starts the generator in an off-grid scenario.
  4. Input Stopping SOC value. This is the state of charge percentage the battery must reach before the SPS unit automatically stops the generator in an off-grid scenario.
  5. Select "GenType:1" for the Generator Type field.
  6. Set Control to "Automatic". This enables the SPS unit to automatically start or stop the generator as per the pre-programmed settings above.NOTE: "Manual" may also be selected to expose start/stop commands in the SPS app for generator testing and troubleshooting of the 2-wire start functionality.
  7. Toggle No-Disturb Enable to ensure that the generator will not be activated during a specified time.

Diagram Description: A screenshot of the "Generator Port Control" screen in the SPS App is shown, highlighting fields for Maximum Power, Starting SOC, Stopping SOC, Generator Type, Control (Automatic/Manual), and No-Disturb Enable.

3. Generator to GRID Terminal (Upstream ATS)

Installation steps for a Generator to GRID Terminal design include physical wiring, configuration with the Savant Power Storage app, and configuration using either Blueprint or the Savant Power & Light app. Once configuration has been completed in the Savant Power Storage app, additional configuration is required to properly automate generator functionality. Complete configuration using the Savant Power & Light app described in section 4 OR RacePoint Blueprint described in section 5.

A Generator to GRID Terminal installation allows the batteries of the SPS system to be charged via a generator in the following manner:

  1. When an individual battery stack discharges and reaches its generator starting state of charge the inverter calls on the generator to start during a power outage.
  2. The upstream generator ATS qualifies the generator signal and switches from “Normal/Utility” position to “Emergency/Generator” position.
  3. Once the generator has a stable output signal and the ATS has switched positions, the SPS unit starts qualifying the generator signal at the grid terminal.
  4. Once qualified, the generator then starts charging the battery stack while also supplying the downstream house loads.
  5. The inverter stops the generator once the battery reaches its Storm Watch SOC parameter as set in Blueprint or SP&L app.

NOTE: In a parallel Generator to GRID terminal system design, once one battery stack reaches the "Generator Charges Battery Threshold" parameter, all battery stacks in the system are charged at the same time. Meanwhile, all downstream loads are also being fed by the generator.

IMPORTANT! The generator must be sized accordingly to feed all critical loads and charge the batteries at the same time.

3.1. Physical Installation

Follow the instructions below to install a generator with an existing Savant Power Storage system. See Appendix: Generator to GRID Terminal Wiring Diagram for wiring example.

  1. Connect the Utility Power Source onto the Normal terminal of the generator ATS (L1/L2/N/G).
  2. Connect the Generator Power Source onto the Emergency terminal of the generator ATS (L1/L2/N/G).
  3. Connect the AC generator ATS load wires onto the GRID terminals of all SPS systems (L1/L2/N/G). This can be done either directly onto the SPS GRID terminals or through a Grid Combiner Breaker Panel for parallel SPS configurations. Install a properly sized OCP device upstream of each SPS GRID terminal.
  4. Refer to the ATS and generator wiring diagram/manual for auxiliary connection (NC/NO) locations.
    • Connect the generator 2-wire START to the SPS unit. See Appendix: Generator to GRID Terminal Wiring Diagram.
    • Connect a NC/NO auxiliary contact in the generator ATS to the GPIO port on the Savant Power Director. This NC/NO auxiliary contact gives the positional status of the generator ATS (Normal position vs Emergency).
    The Director can support ATS position sensing from either a NC or NO contact. During system setup, the director will be programmed to indicate the normal position of the auxiliary contact.NOTE: A dedicated Savant Controller (e.g. SSC-0012, SSC-0014) is required for systems using a different Savant Host than the Savant Power Director.
  5. Connect generator 2-wire START/STOP control wiring to the Leader SPS unit (see Appendix: Generator to GRID Terminal Wiring Diagram). The SPS generator START/STOP functionality is controlled via a normally open (NO) dry contact.

Diagram Description: A diagram shows the Savant Power Director and Network Switch. The Generator ATS is depicted, with connections for Utility Power Source (to NORMAL) and Generator Power Source (to EMERGENCY). The ATS LOAD terminal connects to the SPS Inverter's GRID terminals. The 2-WIRE START/STOP connection runs from the generator to the SPS Inverter. An Auxiliary Contact from the Generator ATS is shown connecting to a GPIO port on the Power Director, enabling ATS status monitoring. A LEGEND defines wire types: LOW VOLTAGE, LINE 2, LINE 1, NEUTRAL, GROUND, ETHERNET. A close-up of the Power Director's GPIO ports is also shown.

3.2. Generator to GRID Terminal Savant Power Storage App Setup

When using the Generator to GRID Terminal option, the Generator Port is unused and must be deactivated.

From the Settings menu in the SPS App, navigate to Connected Power Sources and access the Generator Port screen to configure the following fields:

  1. Select Generator Mode.
  2. Select Manual for the control field.

Diagram Description: A screenshot of the "Generator Port Control" screen in the SPS App is shown, with "Generator" selected and "Manual" selected for the Control field.

4. Savant Power & Light App Configuration

Additional configuration is required to properly automate generator functionality once configuration in the Savant Power Storage app is completed. Only one configuration tool is needed (RacePoint Blueprint OR Savant Power & Light app). If the Savant Power & Light app is the configuration tool of choice, follow the instructions below. Alternatively, see the Blueprint Configuration section for configuration steps in RacePoint Blueprint. These steps assume the installer has an already configured Savant Power Storage system and is adding a generator to the SP&L configuration. For information configuring a Savant Power Storage system in the SP&L App, see the Savant Power System Deployment Guide - Savant Power & Light App on the Savant Customer Community.

  1. In the SP&L App, select Home.
  2. Select System Configuration.
  3. Once the SP&L App is finishing discovering, Select the Director for this installation. Get configuration from host if necessary.
  4. Select Power Sources.
  5. Select Battery Storage then tap Next.
  6. Select Savant Power Storage 20 or Savant Power Storage 50 as the power source profile then tap Next.
  7. Determine the configuration from the options below and continue onto steps:
    • No external generator configured. (There is no generator sitting on an upstream ATS). Continue to step 8.
    • External generator configured with a Normally Open ATS (Not ASCO). Continue to step 9.
    • External generator configured with a Normally Closed ATS. Continue to step 10.
  8. If no external generator configured, (there is no generator sitting on an upstream ATS) set Generator ATS Relay to Not Used. (The GPIO for ATS option will be unavailable).
  9. If there is an external generator configured with a Normally Open ATS, (Not ASCO) follow the steps below: [Details for step 9 are not provided in the OCR text, but the flow is indicated.]
  10. If there is an external generator configured with a Normally Closed ATS, (ASCO typically) follow the steps below:
    • A. Set Generator ATS Relay to Open on Normal if the ATS auxiliary connection is Open on Normal.
    • B. Set GPIO for ATS to the GPIO port on the network which the ATS auxiliary is connected to. In this example a standard director is displayed. The name is typically HST-DIRECTOR-00 Unconfigured #UUID Number#.
    • C. Both ports have been selected and are shown in the SP&L app. Select Next and Sync the configuration.

Diagram Description: A series of screenshots from the Savant Power & Light app illustrates the configuration process. These include the Home screen, System Configuration, Discovering Devices, Grid Control Director, Power Sources, Battery Storage selection, and Power Source profile selection (PS20/PS50). Detailed views show the configuration of Generator ATS Relay (options like Not Used, Open on Normal, Closed on Normal) and GPIO for ATS, depending on the ATS type.

5. Blueprint Configuration (Generator to GRID Terminal ONLY)

Additional configuration is required to properly automate generator functionality once configuration in the Savant Power Storage app is completed. Follow the instructions below. Alternatively, see the Savant Power & Light app section for configuration steps with the SP&L app.

  1. In Blueprint, select the controller that will be used for installation.
  2. Navigate to Tools > Settings > Microgrid Controller.
  3. Set the following parameters under Microgrid Controller Settings:
    • Set Generator Charges Battery Threshold to an SOC percentage that will turn on the generator when in an off-grid scenario.
    • Select Generator Charges Battery.
    • Select Generator and set generator size.
    NOTE: Maximum generator size is 24kWh.
  4. Select the ATS profile for the Generator Connection. The ATS will have a relay to represent its Normal State. If the Normal State is open, select the Normally Open profile. If it is closed, select the Normally Closed profile.
  5. Connect the ATS auxiliary contact to GPIO ports used in installation.

Diagram Description: Screenshots from Blueprint software show the navigation path to "Microgrid Controller Settings" and the configuration options within it, including "Generator Charges Battery Threshold", "Generator Charges Battery", and "Generator" size. Another diagram illustrates selecting the ATS profile (e.g., "ATS (normal closed)", "ATS (normal open)") and connecting the ATS auxiliary contact to GPIO ports on a Savant Extender ATS.

Appendices

Appendix: Generator to GEN Terminal Wiring Diagram

Description: This diagram illustrates the wiring for a Generator to GEN Terminal installation. It shows the Savant Power Director and Network Switch connected via Ethernet. The SPS Inverter is depicted with its GRID, LOAD, and GEN terminals. The generator's AC output and ground are connected to the GEN terminals (L1, N, L2, G). A 2-WIRE START/STOP control connection is shown from the generator to the SPS Inverter. A LEGEND defines wire types: LOW VOLTAGE, LINE 2, LINE 1, NEUTRAL, GROUND, ETHERNET.

Appendix: Generator to GRID Terminal Wiring Diagram

Description: This diagram shows the wiring for a Generator to GRID Terminal installation. It includes the Savant Power Director and Network Switch. The Generator ATS is central, with Utility Power Source connected to its NORMAL terminal and Generator Power Source to its EMERGENCY terminal. The ATS LOAD terminal connects to the SPS Inverter's GRID terminals. The 2-WIRE START/STOP connection runs from the generator to the SPS Inverter. A key feature is the NC/NO AUX CONTACT from the Generator ATS connected to a GPIO port on the Power Director, providing ATS status. A LEGEND defines wire types: LOW VOLTAGE, LINE 2, LINE 1, NEUTRAL, GROUND, ETHERNET.

Appendix: Parallel SPS System Network Wiring Diagram

Description: This diagram illustrates the network wiring for a parallel Savant Power Storage System. It shows multiple SPS Inverters connected to a central Power Director (or licensed Savant Host) via a Network Switch. The connections are shown using Ethernet cables. The diagram also includes various port labels on the SPS Inverters and Power Director.

Models: PS20, PS50, PS20 PS50 Power Storage Generator, PS20 PS50, Power Storage Generator, Storage Generator, Generator

File Info : application/pdf, 18 Pages, 3.20MB

PDF preview unavailable. Download the PDF instead.

009-2450-00 Savant Power Storage Generator Installation and ATS Integration Guide

References

Adobe PDF Library 17.0 Adobe InDesign 19.5 (Macintosh)

Related Documents

Preview Savant da Vinci 10.1 Release ReadMe
This document provides comprehensive release notes for Savant da Vinci 10.1, detailing new features, system requirements, product enhancements, and resolved issues for Savant smart home automation systems. Includes compatibility information and support resources.
Preview Savant Apple TV HomeKit Deployment Guide: IP Control and Siri Integration
A comprehensive guide for installers detailing the deployment and configuration of Savant systems with Apple TV for IP control and Siri integration. Covers requirements, pairing, HomeKit setup, RacePoint Blueprint configuration, and troubleshooting.
Preview Savant Power Storage 20 Shared Battery Configuration Technical Brief
Technical guide for installing and configuring Savant Power Storage 20 systems with shared battery configurations, including physical setup, system programming, and firmware updates.
Preview Savant da Vinci 10.5 Release ReadMe: New Features and System Requirements
Comprehensive release notes for Savant da Vinci 10.5, detailing new software features, product enhancements, resolved issues, and system requirements for various Savant Hosts and Development Environments.
Preview Savant Power Storage 20 [100A] Quick Reference Guide
Concise guide to Savant Power Storage 20 [100A], covering box contents, specifications, installation, and wiring for efficient energy management.
Preview Savant SmartControl RS232 Wi-Fi Controller (SSC-WO2R) Quick Reference Guide
Quick reference guide for the Savant SmartControl RS232 Wi-Fi Controller (SSC-WO2R), detailing box contents, specifications, front panel indicators, RS-232 wiring, and network connection setup.
Preview Savant da Vinci 10.5.1 Release Notes and System Requirements
Official release notes for Savant da Vinci version 10.5.1, detailing software versions, system requirements, resolved issues, and compatibility matrices for Savant Pro, SDE, and various host models.
Preview Savant Power System Deployment Guide: Sol-Ark & HomeGrid Installation and Configuration
This Savant Power System Deployment Guide provides comprehensive instructions for installers on the wiring and configuration of Sol-Ark inverters and HomeGrid battery solutions. It details safety procedures, installation steps, and technical parameters for systems supporting da Vinci 10.2 or higher, including components like ASCO ATS and Savant's smart energy devices.