Dover to Needham Underground Cable Modernization Project FAQ

Stakeholder Questions & Answers

This document was last updated in August 2025

The Dover to Needham Underground Cable Modernization Project (UCMP) is designed to modernize and increase the capacity of existing underground transmission cable systems. The proposed project includes replacement of existing high-pressure fluid filled (HPFF) lines with cross-linked polyethylene (XLPE) electric transmission cables along a 1.3-mile existing route in the Dover, Needham and Westwood areas. The proposed route is between the Chestnut Street substation in Needham and Westfield Street substation in Westwood, along the Westwood-Dover town boundary. Construction is expected to begin in 2026 after receipt of all necessary permits and approvals.

Why is this project needed?

Eversource is taking a proactive approach to upgrade underground transmission lines to modernize infrastructure, boost capacity and better serve future demand. To learn more, visit https://bit.ly/EversourceUCMP.

What is the anticipated timeline of the project and how long will it take?

We plan to file a report with the Department of Public Utilities in Q3 of 2025. Upon receipt of all necessary permits and approvals, construction is planned to start in late 2026 and be complete as early as late 2028. Please note this timeline is dependent on approvals and subject to change based on unforeseen circumstances.

What is a transmission line?

Transmission lines carry high-voltage electricity between substations. For more information, please visit: https://www.eversource.com/content/residential/about/transmission-distribution/electric-distribution

What is the line voltage?

The voltage of the transmission lines will be 115-kilovolts (kV), which is the same voltage as the existing lines.

How many manholes will be placed along the route?

Approximately four manholes will be installed, three in Needham and one in Dover. Please note there will be additional handholes constructed for communication wiring access when necessary and these are sometimes called handholes.

What are the construction phases, generally?

Construction on an underground transmission line replacement project typically follows three different phases. The first phase of construction starts with work crews setting up safe work zones and often performing surveys and other field work. From there, work crews excavate the roadway, install vaults (often also called manholes), backfill and perform temporary restoration efforts. The second phase could involve trenching, installation of cable and temporary backfill. The third phase includes running cable between vaults and splicing.

Will Eversource backfill the roadway during construction?

Yes. As work progresses, crews will backfill pavement over completed work as part of the temporary restoration phase. Steel plates will also be utilized where needed. At the end of construction, a final review for restoration will be coordinated with local officials.

Will there be fluid in the new cables?

No. The new XLPE cables will contain solid dielectric cables rather than fluid. The dielectric fluid within the existing HPFF cables will be removed and the line retired in place as a spare.

What is the age of the existing transmission line?

The line was constructed in 1967, which makes it one of the oldest transmission lines on the Eversource system. System reliability warrants replacement of the current HPFF transmission lines.

What is the depth Eversource will be excavating to during construction to install the new transmission line?

The average excavation depth along most of the roadway will be five feet, while manholes will be about 15 feet deep. Please note that depths will vary due to underground conditions and to accommodate other existing utilities.

Will the project affect any water sources?

The project is not anticipated to affect any water resources. The replacement transmission line duct banks and associated construction workspaces are proposed to be located primarily within existing paved roadways.

What mitigation measures will be taken near the Charles River Crossing?

Soil erosion and sediment control devices such as straw wattles/bales, siltation fencing, and/or chip bales will be installed in accordance with approved plans, permit requirements and Eversource Best Management Practices (BMP) Manual. The use of timber construction matting will likely be used in environmentally sensitive areas or areas with uneven terrain. The installation of sediment control devices will be overseen by Eversource's environmental monitor. During construction, these BMP devices will be periodically inspected by the environmental monitor, and the findings will be reported regularly to Eversource's Environmental Specialist and Construction Supervisor. Soil testing will be conducted in accordance with Massachusetts standards throughout the project. Testing of existing line's fluid for polychlorinated biphenyls (PCB) will also occur.

Will there be road closures?

Currently, there are no planned closures along major roadways, and we are requesting police details to assist with any traffic impacts. Single lane alternating traffic will likely be implemented. Traffic management plans are dependent on input and approval from the affected Town(s).

More information?

For the most up to date information sign up for our email updates via constant contact by clicking here. For general information please visit our website at https://bit.ly/DoverNeedhamUCMP or contact our hotline at 833-836-0302 or email ProjectInfoMA@eversource.com

PDF preview unavailable. Download the PDF instead.

dover-needham-ucmp-faq

Related Documents

Preview Eversource Underground Cable Modernization: Dover & Needham Project Overview
Eversource is modernizing its 115 kV underground electric transmission line in Dover, Needham, and Westwood, replacing aging fluid-filled cable with advanced XLPE technology for improved reliability and capacity.
Preview Mystic and Everett Underground Cable Modernization Project
Information about the Underground Cable Modernization Program for the Mystic and Everett areas, including project scope, timeline, and community engagement.
Preview Eversource Beebe River to Whitefield (X178) Line Rebuild Project
Information regarding the Eversource Beebe River to Whitefield (X178) Line Rebuild Project, focusing on construction permit maps and project scope.
Preview Eversource X178-1 Line Rebuild Project: Technical Specifications and Permit Maps
This document details the technical specifications and construction permit map information for the Eversource X178-1 Line Rebuild Project, aimed at enhancing electrical infrastructure reliability between Beebe River and Whitefield.
Preview Eversource X178 Line Rebuild Project: Beebe River to Whitefield
Details on the Eversource X178 line rebuild project connecting Beebe River to Whitefield, focusing on infrastructure improvements and project scope.
Preview Eversource 2020 Sustainability Report: Driving Clean Energy and ESG Excellence
Explore Eversource Energy's 2020 Sustainability Report detailing commitments to environmental stewardship, social responsibility, and robust governance, including clean energy initiatives and community engagement.
Preview Eversource 2025 Electric Rates Summary and Definitions
Comprehensive summary of Eversource's electric rates for 2025, detailing residential and commercial service charges, energy rates, and definitions of billing terms. Updated August 1, 2025.
Preview Current BTU Factors for Connecticut Gas Suppliers - Eversource
A comprehensive table detailing daily BTU factors for Connecticut gas suppliers, provided by Eversource, covering various dates and days.