HÖRMANN BFT3 Casting Frame Installation Guide

This document provides detailed instructions for the installation of the HÖRMANN BFT3 casting frame. Please read and follow all instructions carefully to ensure safe and proper operation.

1. About This Manual

This manual is valid for the BFT3 casting frame. Dimensions are in millimeters.

2. Safety

2.1 Intended Use

The product is used in commercial areas and serves the following purposes:

2.2 Suitable Personnel

Only allow trained personnel to work on the product, provided they are authorized and instructed by the operator. The assembly includes:

Special assembly work must only be carried out by qualified personnel from specialized companies. This includes work on the building's structural integrity or ventilation system.

3. Scope of Delivery

The scope of delivery for the casting frame includes:

A visual representation of the frame components is provided.

4. Installation Requirements

4.1 Pit Forms

Depending on the door guide, various pit forms are possible:

4.2 Pit Requirements

For permanently flawless functioning, the pit must be designed as follows:

CAUTION: Danger of breakout due to insufficient anchoring

If the pit cannot withstand the load, the loading bridge will break out. In case of an emergency stop, the load is particularly high. Example: a truck drives away while the loading bridge is still in operation. Ensure sufficient connection to the building structure, especially in areas where load forces occur.

NOTE: The reinforcement must extend laterally to the edge of the pit. Alternatively, install posts according to the manufacturer's pit drawings.

4.2.1 Checking Pit Dimensions

Check the dimensional accuracy (in mm):

The lengths of the diagonals (C) must not differ by more than 10 mm.

NOTE: A gradient of maximum 2% towards the door opening is acceptable for the casting frame. The casting frame must be installed precisely horizontally in width. Otherwise, the functionality of the loading bridge may be impaired, especially when loading below the ramp level.

Pit dimensions:

5. Assembly

The assembly of the loading bridge may only be carried out if the requirements for the installation site are met.

NOTE: Deviations from the depicted pit shape are possible. The illustrations do not account for the extension and adaptation of the pit for the door guide before the loading bridge.

5.1 Safety Instructions for Assembly

Assembly only by qualified personnel. Ensure that the following conditions are met during assembly:

5.2 Required Tools

Gather the required tools. We recommend performing the assembly with 2 people.

Lifting aids are required for assembly. If ordered accordingly, they are included.

5.3 Unloading

CAUTION: Damage from impact

The casting frame must not deform, as this can impair its functionality.

5.4 Assembly

Assemble the casting frame in the specified order.

Figure 1: Positioning components

Place the components near the pit according to the illustration.

Figures 2 and 3: Mounting the front beams

Align a side panel and screw it firmly to the front beam. Ensure that all edges are flush.

Repeat the process on the other side.

Figure 4: Mounting the rear edge angle

Screw the rear edge angle to the two side panels.

Figure 5: Mounting positioning aids

Screw the four positioning aids to the casting frame.

Figure 6: Mounting the back plate

Screw the back plate to the casting frame.

Figure 7: Mounting lifting aids

Screw the lifting aids to the specified points on the casting frame. Brace the frame with a wooden beam parallel to the front beam as required. Remove the lifting aids.

IMPORTANT! The lifting aids must be attached exactly at right angles to the side panels. Otherwise, the frame will deform. Use the same holes on both sides for fastening.

5.5 Installation

The welding symbols correspond to ISO 2553 (E). The BFT3 casting frame is either cast with prefabricated concrete parts (A) or cast into a pit with a sufficiently wide casting joint (B).

5.5.1 Setting Up

Position the casting frame.

A:

B:

5.5.2 Welding

WARNING: Health hazard when welding galvanized components

Zinc fumes are released during welding of galvanized parts, which can cause health impairments if inhaled. Grind off the zinc layer at the welding points.

The frame has anchors on the sides and rear.

IMPORTANT! All rear anchors must be welded! You do not have to weld all side anchors if the following conditions are met:

In this case, weld the following anchors:

Bend all anchors. Connect the anchors to the posts or the reinforcement. Weld the anchors to the reinforcement or the posts.

5.5.3 Casting

Concrete quality: at least C20/25.

Before casting, ensure that the positioning and anchoring of the casting frame are still intact. Pour the concrete casting compound.

5.6 Removing Aids

Remove and dispose of the aids for assembly.

CAUTION: Damage due to deformation

The casting frame must not deform, as this can impair its functionality. Ensure that the lateral pressure during pouring and compacting does not become too high.

CAUTION: Danger due to insufficient anchoring

If the anchoring is insufficient, the pit cannot withstand the load. The loading bridge will break out. Ensure sufficient connection to the building structure, especially in areas where load forces occur.

The edge angle must be completely backfilled. You can check this through the opening in the edge angle.

5.7 Final Inspection

Check if any frame deformations have occurred during installation.

PDF preview unavailable. Download the PDF instead.

Anleitung BFT3 1200026785 DE 07 2025 Adobe PDF Library 17.0

Related Documents

Preview Hörmann BFT3 Embedding Frame Assembly Instructions
Comprehensive assembly and installation guide for the Hörmann BFT3 Embedding Frame, detailing safety, requirements, and step-by-step procedures for industrial loading dock applications.
Preview HÖRMANN HTL3 Loading Ramp: Installation, Use, and Maintenance Manual
Comprehensive guide for the HÖRMANN HTL3 loading ramp, covering installation procedures, safe usage instructions, maintenance schedules, troubleshooting tips, and technical specifications. Includes safety warnings and compliance information.
Preview Hormann HTL3 Dock Leveler: Installation, Operation, and Maintenance Manual
Comprehensive guide for the Hormann HTL3 dock leveler, covering installation, operation, maintenance, safety, and troubleshooting. Includes technical specifications and compliance information.
Preview HORMANN HTL2 ISO Dock Leveller: Fitting, Operation, and Maintenance Manual
This manual provides comprehensive instructions for the fitting, operation, and maintenance of the HORMANN HTL2 ISO dock leveller. It covers essential safety guidelines, technical specifications, and troubleshooting for industrial loading bay environments.
Preview Hormann HTL3: Manual de Montaj, Funcționare și Mentenanță
Ghid complet pentru montajul, operarea și întreținerea rampei de egalizare Hörmann HTL3. Asigurați funcționarea sigură și eficientă a echipamentului.
Preview HÖRMANN HTL2 ISO Lastbrygga: Bruksanvisning för Montering, Drift och Underhåll
En komplett guide för HÖRMANN HTL2 ISO lastbrygga, som täcker installation, säker användning och underhållsprocedurer för optimal prestanda och säkerhet.
Preview Hormann AWB Automatic Wheel Blocking System - Installation, Operation, and Maintenance Manual
Comprehensive guide for the Hormann AWB automatic wheel blocking system, covering installation, operation, maintenance, safety, and technical specifications.
Preview Hormann AWB Automatic Wheel-Blocking System: Fitting, Operation & Maintenance Instructions
Comprehensive guide for the Hormann AWB Automatic Wheel-Blocking System, covering installation, operation, maintenance, safety, and technical specifications for industrial loading bays. Includes detailed diagrams and troubleshooting.