Hörmann BFT3 Embedding Frame Assembly Instructions

Model: BFT3

Manufacturer: Hörmann

About This Guide

This guide is valid for the Embedding Frame BFT3. Dimensions are in millimeters.

Safety

Failure to follow this guide may result in personal injury or product damage.

Intended Use

The product is used in commercial areas and serves the following purposes:

Qualified Personnel

Only allow trained personnel authorized and instructed by the operator to work on the product. Assembly involves:

Specialized assembly work must only be performed by qualified personnel from specialized companies. This includes work on building statics or ventilation systems.

Scope of Delivery

The scope of delivery for the embedding frame includes:

Installation Requirements

Pit Shapes

Depending on the door guidance, various pit shapes are possible:

Door Guidance Up to the Loading Bridge

The door closes on the platform of the loading bridge. This door guidance has no impact on the pit design.

Door Guidance in Front of the Loading Bridge

The door guidance requires a longer pit with a recess for the door. The embedding frame is installed further back in the pit. The door closes on the insulation panel (customer-provided) below the loading bridge. For loading ramps without underfloor access, the door closes on the concrete floor.

Note: Reinforcement must extend to the pit edge on the sides. Alternatively, install dowels according to the manufacturer's pit drawings.

Diagram Description: Illustrates two pit configurations: one simple rectangular pit and one longer pit with a recess for the door. Also shows installation using precast concrete parts and installation with a casting joint.

Pit Requirements

For permanently faultless functioning, the pit must be executed as follows:

⚠️ ATTENTION: Risk of breakout due to insufficient anchoring. If the pit cannot withstand the load, the loading bridge will break out. The load is particularly high during emergency stops. Example: a truck drives away while the loading bridge is still in operation. Ensure sufficient connection to the building structure, especially in areas where load forces occur.

Check Pit Features

Control the dimensional accuracy (in mm):

The lengths of the diagonals (C) must not deviate from each other by more than 10 mm.

Note: A slope of up to 2% towards the door opening is acceptable for the embedding frame. However, the embedding frame must be installed exactly horizontally in width. Otherwise, the functionality of the loading bridge may be impaired, especially when loading below the ramp level.

Diagram Description: Shows three pit configurations (no recess, wide recess, narrow recess) with dimensions labeled PL, PL1, PW, PH, and diagonals C1, C2.

Key for dimensions:

Assembly

The loading bridge may only be assembled if the requirements for the installation location are met.

Note: Deviations from the depicted pit shape are possible. The illustrations do not account for the extension and adaptation of the pit for door guidance in front of the loading bridge.

Safety Instructions for Assembly

Assembly only by qualified personnel. Ensure the following conditions are met during assembly:

Required Tools

Gather the necessary tools. We recommend performing the assembly with 2 people.

Diagram Description: Illustration of tools including a spirit level, measuring tape, hammer, drill, wrenches, safety glasses, gloves, and ear protection. Also shows two workers and a forklift.

Lifting aids are required for assembly. Supplied upon corresponding order.

Unloading

Contact your supplier in case of deformation or damage. Minor damage to the paint or galvanization should only be repaired after assembly.

⚠️ ATTENTION: Damage from impact. The embedding frame must not deform, as this can impair its functionality. Always keep the embedding frame horizontal. Ensure the embedding frame does not get bumped or dropped.

Diagram Description: Shows a forklift lifting and placing the embedding frame.

Assembly

Assemble the embedding frame in the specified order.

Diagram Description (Figure 1: Positioning Components): Shows the components of the embedding frame laid out near a pit, ready for assembly.

Mounting Front Beams (Figures 2 & 3)

Align a side plate and screw it firmly to the front beam. Ensure all edges are flush.

Diagram Description: Shows side plates being attached to front beams, with a note to ensure flush edges.

Mounting Rear Edge Bracket (Figure 4)

Screw the rear edge bracket to the two side plates.

Diagram Description: Shows the rear edge bracket being attached to the side plates.

Mounting Positioning Aids (Figure 5)

Screw the four positioning aids to the embedding frame.

Diagram Description: Shows positioning aids being screwed onto the embedding frame.

Mounting Back Plate (Figure 6)

Screw the back plate to the embedding frame.

Diagram Description: Shows the back plate being screwed onto the embedding frame.

Mounting Lifting Aids (Figure 7)

Screw the lifting aids to the specified locations on the embedding frame.

Diagram Description: Shows lifting aids being attached to the embedding frame.

Brace the frame on-site with a wooden beam parallel to the front beam.

Important Note: The lifting aids must be attached exactly at a right angle to the side panels; otherwise, the frame will deform. Use the same holes on both sides for fastening.

Diagram Description: Shows a wooden beam bracing the frame and the removal of lifting aids.

Installation

The welding symbols comply with ISO 2553 (E).

The Embedding Frame BFT3 is either cast with precast concrete parts (A) or embedded in a pit with a sufficiently wide casting joint (B).

Erecting

Position the embedding frame. Ensure the frame is aligned horizontally.

Diagram Description: Shows the embedding frame being placed into the pit (A) and then leveled (B).

Welding

❗ WARNING: Health hazard when welding galvanized parts. Welding galvanized parts releases zinc fumes, which can cause health impairments if inhaled. Grind off the zinc layer at the welding points.

The frame has anchors on the sides and rear.

Important Note: All rear anchors must be welded! You do not need to weld all side anchors if the following conditions are met:

In this case, weld the following anchors:

Bend all anchors. Connect the anchors to the dowels or reinforcement.

Weld the anchors to the reinforcement or dowels.

Diagram Description: Shows bending anchors, connecting them to dowels/reinforcement, and welding details with dimensions (a4, 90 degrees).

Pouring/Casting

Concrete quality: minimum C20/25.

Before pouring, ensure that the positioning and anchoring of the embedding frame are still intact.

Pour the concrete casting compound.

Diagram Description: Shows concrete being poured into the pit around the frame.

Removing Aids

Remove and dispose of the assembly aids.

Diagram Description: Shows assembly aids being removed from the frame.

Final Check

Check if any frame deformations have occurred during installation.

⚠️ ATTENTION: Damage due to deformation. The embedding frame must not deform, as this can impair its functionality. Ensure that the lateral pressure from pouring and compacting does not become too high.

⚠️ ATTENTION: Risk of breakout due to insufficient anchoring. If the anchoring is insufficient, the pit cannot withstand the load, and the loading bridge will break out. Ensure sufficient connection to the building structure, especially in areas where load forces occur. The edge bracket must be completely backfilled. You can check this through the opening in the edge bracket.

Diagram Description: Shows checks for frame deformation and edge bracket filling, with visual indicators (red X, green checkmark).

PDF preview unavailable. Download the PDF instead.

Anleitung BFT3 1200026811 DE 07 2025 Adobe PDF Library 17.0

Related Documents

Preview HÖRMANN BFT3 Casting Frame Installation Guide
Comprehensive installation instructions for the HÖRMANN BFT3 casting frame, detailing safety precautions, required tools, assembly steps, and final checks for proper integration with loading bridges.
Preview HÖRMANN HTL3 Loading Ramp: Installation, Use, and Maintenance Manual
Comprehensive guide for the HÖRMANN HTL3 loading ramp, covering installation procedures, safe usage instructions, maintenance schedules, troubleshooting tips, and technical specifications. Includes safety warnings and compliance information.
Preview Hormann HTL3 Dock Leveler: Installation, Operation, and Maintenance Manual
Comprehensive guide for the Hormann HTL3 dock leveler, covering installation, operation, maintenance, safety, and troubleshooting. Includes technical specifications and compliance information.
Preview HORMANN HTL2 ISO Dock Leveller: Fitting, Operation, and Maintenance Manual
This manual provides comprehensive instructions for the fitting, operation, and maintenance of the HORMANN HTL2 ISO dock leveller. It covers essential safety guidelines, technical specifications, and troubleshooting for industrial loading bay environments.
Preview Hormann AWB Automatic Wheel-Blocking System: Fitting, Operation & Maintenance Instructions
Comprehensive guide for the Hormann AWB Automatic Wheel-Blocking System, covering installation, operation, maintenance, safety, and technical specifications for industrial loading bays. Includes detailed diagrams and troubleshooting.
Preview Hormann AWB Automatic Wheel Blocking System - Installation, Operation, and Maintenance Manual
Comprehensive guide for the Hormann AWB automatic wheel blocking system, covering installation, operation, maintenance, safety, and technical specifications.
Preview HÖRMANN HTL2 ISO Lastbrygga: Bruksanvisning för Montering, Drift och Underhåll
En komplett guide för HÖRMANN HTL2 ISO lastbrygga, som täcker installation, säker användning och underhållsprocedurer för optimal prestanda och säkerhet.
Preview Hormann IBS Instructions for Adjustment and Operation
This document provides detailed instructions for the adjustment and operation of the Hörmann IBS (Intermediate Stop) system, designed for Hörmann telescopic lip dock levellers with control 560 T/V. It covers safety, description, electrical connection, adjustment procedures, operational progress, maintenance, and troubleshooting.