Hunter Golf Irrigation
Pilot® Control Network Commissioning Checklist
This form must be completed and returned to Hunter Industries Inc. by an authorized service provider or Hunter Field Service Manager for the activation of the Hunter Service Network plan. Answer all items that are applicable with a description or an "X.”
Once Complete
RETURN TO:
Hunter Industries
ATTN: Hunter Golf HSN
1840 La Costa Meadows Drive
San Marcos, CA 92078
OR
EMAIL TO:
golf@hunter.global
Golf Course Information
Golf Course Contact
Installation Contractor
Commissioning
System Type (Add number of controllers)
Additional Equipment Installed
Communication Type
Licensed Frequencies
Operator Training Complete
Field Interface Grounded (if applicable)
TeamViewer
Additional Checklist
UFHA Radio Report
ATTENTION: When UHFA modules are used in controllers, prioritize signal quality over RSSI, as it more accurately reflects communication reliability. If you experience communication issues, try adding more antennas or using multiple frequencies with MultiTalk™ Technology.
Controller Number | Date Checked | Quality Value | RSSI Value |
---|---|---|---|
Controller Grounding Report
ATTENTION: If grounding is required due to lightning activity in the area, all controllers must be grounded and tested using a ground-ohm meter. Ground resistance should be 10 ohms or less. If this requirement is not met, additional ground rods or plates must be installed.
Controller Number | Date Checked | Plate (P) or Rod (R) | Resistance Value |
---|---|---|---|
PILOT-SG Grounding Report
ATTENTION: If grounding is required due to lightning activity, all PILOT-SGs must be grounded and tested using a ground-ohm meter. Ground resistance should measure 10 ohms or less. If this requirement is not met, additional rods or plates must be installed. At least 10% of PILOT-SGs should be tested to verify compliance.
PILOT-SG Location | Date Checked | Plate (P) or Rod (R) | Resistance Value |
---|---|---|---|
Pilot Integrated Hub Current/Diagnostics Report
ATTENTION: Two-Way Modules draw approximately 1 mA each. Output Modules should remain within specified mA tolerances to ensure proper functionality.
Controller | Output Module | mA Reading | Total Wire Paths | mA per Path | Total TWMs |
---|---|---|---|---|---|
Controller 1 | 1 | ||||
2 | |||||
3 | |||||
4 | |||||
Controller 2 | 1 | ||||
2 | |||||
3 | |||||
4 | |||||
Controller 3 | 1 | ||||
2 | |||||
3 | |||||
4 | |||||
Controller 4 | 1 | ||||
2 | |||||
3 | |||||
4 |