Engineering Recommendation G100 Declaration

Internal Disclosure

SolaX Power Network Technology (Zhejiang) Co., Ltd. hereby confirms that X3-Hybrid Series inverter (the model shown as below) complies with the power meter (&CTs) recommended by SOLAX, Engineering Recommendation G100 Issue 1 2016, Technical Guidance for Customer Export Limiting Schemes, when installed in accordance with this Engineering G100 Declaration. (note: only Support EASTRON SDM630M power meter)

This Declaration should be read in conjunction with the inverter user manuals and meter quick installation guide.

Supported Models:

1. Introduction

Engineering Recommendation G100: Technical Guidance for Customer Export Limiting Schemes, published by the ENA, “defines the technical design requirements for Export Limitation Schemes which limit the net site export to below an agreed maximum and are installed on the Customer's side of the Connection Point”.

This document describes how a SOLAX X3-Hybrid Series inverter installation performs relative to key G100 requirements.

2. Description of Operation

G100 Requirement:

A description of the scheme, its settings, and a single line diagram should be permanently displayed on site.

SOLAX X3-Hybrid Series inverter can be set the export limiting power on the inverter LCD display based on customer or local rules requirements. SOLAX named this function “export control” on LCD display and it can be set from 0-300000W. This function means customer should install a meter (power monitoring unit) to monitor energy exported to or imported from the grid.

Note: Please see section 7 of specific LCD display operation.

System Operational States:

After setting the export limit power, the system switches between 3 operational states:

A fundamental principle of this operation is that energy stored in the battery is only released to run loads within the building - at no time is the system attempting to export battery energy to the grid. This control is achieved by:

Meter (Power Monitoring Unit)

3. System schematic

An X3-Hybrid Series inverter installation is shown as below:

X3-Hybrid: controls the AC output power according to the data from meter.

SOLAX Meter: Collects power data and feeds this data to the Inverter.

Diagram Description: A schematic shows the DNO supply connected through a fuse and main switch to a SOLAX Meter. The SOLAX Meter is then connected to an MCB, which feeds the Homeload. The SOLAX Meter also connects to an X3-Hybrid Inverter. The X3-Hybrid Inverter has connections for Battery and PV- PV+. The inverter and meter are also connected via a communication cable.

4. Component interconnection | Fail-safe operation

G100 requirement:

Where discrete units are used they should preferably be interconnected using metallic or fibre optic cables. Alternatively the units may be interconnected using secure radio links but where this is the case these links should be licensed (by OFCOM) and have a planned availability of 99.9% or higher.

Irrespective of the media used for interconnecting between the discrete units, if the communication path fails the generation output should be reduced to a nominal value stipulated by the DNO within a set response time to prevent the Agreed Export Capacity from being exceeded.

As shown in the diagram below, communication between all parts of the system can be wired.

Diagram Description: Two boxes are shown, one labeled "X3-Hybrid Inverter" and the other "SOLAX Meter". Arrows indicate a wired connection between them.

Unplugging or otherwise interrupting any of these wired connections, results in the system turning off. The system reaction speed under these conditions is less than 5s.

System fail-safe tests

No. Test System response Time Pass?
1. Unplug comms cable between Inverter and Meter Loss of meter data detected. System switches off. <5s Yes

See Annex A for test results

5. Response time

G100 requirement

The ELS must detect an excursion and reduce the export to the Agreed Export Capacity or less within 5 seconds.

Under normal operating conditions, X3-Hybrid Series response time is less than 5s.

Under loss of communications, or loss of power to Meter, response time is less than 5s.

6. Password protection

G100 requirement:

Once installed and commissioned, the scheme settings should not be capable of being readily altered by the Customer and should only be changed with the written agreement of the DNO.

All X3-Hybrid Series inverter export limit settings are password protected.

7. LCD display operation

Customer should set “export control” function on the LCD display. “Export Control” setting can be found according to path below.

Path: Menu ➔ Settings ➔ Advanced ➔ On-grid ➔ Export Control

Diagram Description: A flow chart shows the navigation path on the inverter's LCD: Menu -> Settings -> Advanced -> On-grid -> Export Control. A "Password needed" prompt is indicated before reaching "Export Control".

This value can be set from 0-300000W.

For example, if it is set 0W, it means no power can be exported to the grid; If it is set 4000W, it means the power exported to the grid can not exceed 4000W.

Example Setting:

Export Control

User value: 4000W

Mr Guo Huawei

R&D technical director

Date: 2019-01-26

SolaX Power Network Technology (Zhejiang) Co., Ltd.

No.288 Shizhu Road, Tonglu Economic Development Zone, Tonglu City, Zhejiang Province, China.

PDF preview unavailable. Download the PDF instead.

X3-Hybrid-UK-G100 Declaration 20190126 Adobe PDF Library 10.0

Related Documents

Preview Solax X3 Hybrid G4 Inverter: Datasheet and Specifications
Comprehensive datasheet for the Solax X3 Hybrid G4 series of three-phase hybrid inverters for home use, detailing features, performance, and technical specifications for models ranging from 5.0kW to 15.0kW.
Preview SolaX X3-Hybrid G4 User Manual: Installation, Operation, and Maintenance
Comprehensive user manual for the SolaX X3-Hybrid G4 series inverter, covering models from 5 kW to 15 kW. This guide details transportation, storage, installation, electrical connection, commissioning, maintenance, and troubleshooting.
Preview Solax X3-Retro Fit 8kW-10kW Quick Installation Guide
This guide provides step-by-step instructions for the installation of the Solax X3-Retro Fit 8kW-10kW solar inverter. It covers essential procedures including mounting, AC and EPS connections, battery integration, meter setup, firmware updates, and initial system configuration for optimal performance.
Preview SolaX X3-HYB-G4 PRO Installationshandbuch: Leitfaden für Hybrid-Wechselrichter
Entdecken Sie das Installationshandbuch für den SolaX X3-HYB-G4 PRO Hybrid-Wechselrichter. Detaillierte Anleitungen zur sicheren Installation, Verdrahtung und Konfiguration von 4 kW bis 15 kW Solaranlagen.
Preview SOLAX X3-Hybrid G4 Pika-asennusopas: Asennusohjeet
Kattava pika-asennusopas SOLAX X3-Hybrid G4 -sarjan aurinkoinverttereille (5.0 kW – 15.0 kW). Opas sisältää pakkausluettelon, työkalujen valmistelun, asennusvaiheet, liitäntäohjeet (PV, akku, verkko, EPS), tietoliikenneyhteydet, maadoituksen, valvontatoiminnot, käynnistyksen ja laiteohjelmiston päivityksen.
Preview Solax X3-MIC G2 Series Quick Installation Guide | 3 kW - 15 kW Solar Inverter Setup
Quick installation guide for Solax X3-MIC G2 Series solar inverters (3 kW-15 kW). Covers essential steps for inverter installation, PV and AC connections, earth grounding, WiFi setup, and firmware upgrades via USB.
Preview SolaX X1-Hybrid 3KW-5KW Quick Installation Guide
A comprehensive guide for installing the SolaX X1-Hybrid 3KW-5KW solar inverter, detailing mounting, electrical connections (PV, AC, EPS, Battery), startup procedures, firmware updates, and monitoring setup.
Preview SolaX X1-Hybrid User Manual: 3.0kW - 5.0kW
Comprehensive user manual for the SolaX X1-Hybrid inverter, covering installation, operation, safety, technical specifications, and troubleshooting for models 3.0kW to 5.0kW.