iPE P670-4 Installation Manual
[Remote Controller System]
System Components Overview:
- 1. Red Cable: Connects to Key on Switch
- 2. Brown Cable: Connects to GND
- 3. Yellow Cable: Connects to TPS Voltage Signal (0-5V)
- 4. Electronic Valve
A visual diagram shows the layout of the remote controller system components, including the electronic valves, control unit, and wiring harness.
Installation Steps:
Step 1: Wiring Connections
Locate the fuse box under the glove compartment at the passenger's seat.
Connect the red power cord to the fuse slot labeled "10" (the second-to-last slot).
Hang the GND connection above the fuse box.
Identify the yellow/black cable lines from the electronic power control on the right-hand side of the accelerator pedal. Connect the yellow/black cables to this control.
A series of images illustrate the fuse box and the connection points for the red power cord and GND. Another set of images shows the accelerator pedal area and the connection of the yellow/black cables to the electronic power control, including a close-up of the TPS connector.
Step 2: Solenoid Valve Installation
Open the engine bay. Locate the solenoid valve on the right-hand side of the engine.
Disconnect the "IN" and "OUT" cable lines from the stock solenoid valve.
Connect the stock "IN" and "OUT" solenoid valve together with the provided cable lines. Images show the solenoid valve in the engine bay before and after the connection, with a red circle highlighting the solenoid valve and its connections.