Rabalux SHAUN LED Downlight Installation Guide
Installation for Rabalux Art. 3167 / 3168 / 3169 / 3170
Step 1: Power Off. Ensure the power is turned OFF. A hand is shown turning a switch to the 'OFF' position on a terminal block.
Step 2: Prepare Ceiling Opening. The diagram shows a cut-out in a ceiling. Text indicates required dimensions for different wattages: 5W: D75x75-90x90 mm, 12W: D120x120-140x140 mm, 18W: D145x145-165x165 mm, 24W: D195x195-215x215 mm.
Step 3: Connect Driver. Connect the driver to the AC 220V power supply. The diagram shows the driver connected to a terminal block and the main power.
Step 4: Insert Downlight. Make the spring clips vertical. The diagram shows a downlight with its spring clips being positioned upright, with arrows indicating upward movement, ready for insertion into the ceiling hole.
Step 5: Secure Downlight. Hold the spring clips horizontal and push the downlight into position. The diagram shows the downlight being inserted into the ceiling, with labels 'spring clip' and 'ceiling'.
Step 6: Power On. Turn the power ON. A hand is shown turning a switch to the 'ON' position on the terminal block, indicating the installation is complete.
Installation for Rabalux Art. 3174 / 3175 / 3176
Step 1: Power Off. Ensure the power is turned OFF. A hand is shown turning a switch to the 'OFF' position on a terminal block.
Step 2: Fix Frame. Fix the surface-mounted frame. The diagram shows a frame being attached to a 'ceiling&wall' surface using screws in a 'screw-hole'.
Step 3: Connect Driver. Connect the driver to the AC 220V power supply. The diagram shows the driver connected to a terminal block and the main power.
Step 4: Align and Install. Align the rectangular hole of the downlight with the buckle of the frame, and install upwards. The diagram shows the downlight's 'rectagle hole' aligning with a 'buckle' on the frame, with arrows indicating upward installation.
Step 5: Installation Complete. The diagram shows the completed installation of the downlight, flush with the ceiling.
Step 6: Power On. Turn the power ON. A hand is shown turning a switch to the 'ON' position on the terminal block, indicating the installation is complete.