Growatt DRMS & RRCR Function

As a green source of energy, PV station installation grows massive in the past several decades worldwide. But due to the unstable PV production and the limitation grid infrastructure, the stability and security of the grid are becoming more and more important. To ensure this, the grid operator has required a remote-control function by PV inverter. This white paper will introduce the local control requirement in Australia and Europe area, and corresponding solution of Growatt's inverter.

DRMS requirement in Australia and New Zealand

With the focus on global warming and the goal of carbon neutrality, photovoltaic (PV) as a green energy source has been installed in large numbers over the past few decades. However, due to the weather, photovoltaic power generation is not stable during the day. Sometimes there are production peaks, but at the same time the power consumption is low. The grid infrastructure cannot withstand such large fluctuations due to equipment limitations. Therefore, grid stability and security are becoming increasingly important. For this reason, grid operators require PV inverters with remote control capabilities.

As of October 9, 2016, all grids connect inverters installed in Australia have to meet the full requirements of AS4777.2:2015. A key requirement of AS4777.2:2015 is Demand Response Mode (DRM) which enables the inverter to respond to signals sent to it remotely.

"The inverter shall support the demand response mode DRM 0 of Table 5. The inverter should support the other demand response modes of Table 5."

So, while support for all demand response modes is not currently mandatory, all inverters are required to support demand mode DRM 0 (which disconnects the inverter when the signal is received).

Mode Requirement
DRM 0 Operate the disconnection device
DRM 1 Do not consume power
DRM 2 Do not consume at more than 50% of rated power
DRM 3 Do not consume at more than 75% of rated power and source reactive power if capable
DRM 4 Increase power consumption (subject to constraints from other active DRMs)
DRM 5 Do not generate power
DRM 6 Do not generate at more than 50% of rated power
DRM 7 Do not generate at more than 75% of rated power and sink reactive power if capable.
DRM 8 Increase power generation (subject to constraints from other active DRMs)

Table 1: Table 5 from AS/NZS 4777.2:2015

EES System connection

Auxiliary DRED test circuit

DRED

DRM 1/5

DRM 2/6

DRM 3/7

DRM 4/8

REF GEN/0

COM LOAD/0

Picture 1: Appendix F from AS/NZS 4755.3:2016

RRCR requirement in Europe

In EU, similar functionality is mandatory. The COMMISSION REGULATION (EU) 2016/631 of 14 April 2016 has required the remotely control by grid operator to improved grid stability and controllability:

The power-generating module shall be equipped with a logic interface (input port) to cease active power output within five seconds following an instruction being received at the input port. The relevant system operator shall have the right to specify requirements for equipment to make this facility operable remotely.

The concrete control logic will be defined by counties individually. For example, Germany has required a four set points for power control level: 0%-30%-60%-100%, which is also used in CZ and Swiss.

The signal from grid operator is received and transferred by a specific receiver.

Picture 2: DRED controller used in Australia and New Zealand

Picture 3: Ripple control receiver used in Europe

Growatt's solution for DRMS and RRCR

Growatt has realized this function in the inverter through the communication port. The communication port receives the control signal from receiver which controlled by local grid operator. These signals trigger the inverter to change the mode of operation, potentially turning it off, on, or ramping the output up or down.

There are 2 kinds of communication ports for DRMS/RRCR by Growatt's inverters, one is the PIN communication port by Growatt -X/ -X2/ -XH inverters. The other one is RJ45 port, which is on Growatt MIC-X/ SPH / WIT / MAX 50-80K series. Please find the corresponding port in following table:

Picture 4: Growatt inverter communication ports

We take MOD-XH series and SPH series as examples for the following introduction.

Picture 5: Communication port of MOD-XH and SPH BH UP

The definition of inverter communication port is easily found on the user manual. For example, the definition of each PIN of MOD-XH series inverter and the RJ45 definition on SPH series as the list:

PIN Definition Function PIN Definition Function
No. CAN METER DRMS DRMS 485-1/485-2 485-3 PIN Function
1 +12V DRM1/5 RS485B RS485B 1 RS485B
2 COM Dry contact: the power supply should not be greater than 2W DRM2/6 GND GND 2 GND
3 RS485A1 DRM3/7 3 DRY-
4 CANH DRM4/8 4
5 CANL RS485A RS485A 5 REF
6 RS485B3 COM 6 GND
7 RS485A2 7
8 RS485B2 8 WAKEUP
9 WP+ DRM1/5 Relay contact 1 input
10 WP- DRM2/6 Relay contact 2 input
11 DRM3/7 Relay contact 3 input
12 DRM4/8 Relay contact 4 input
13 REF/GEN GND
14
15

RJ45 wiring color code:

PIN 1 2 3 4 5 6 7 8
Color White/ orange Orange White/ Blue Blue White/ Brown Brown

Picture 6: Definition of communication port of MOD-XH and SPH BH UP

Note: Different inverter has different PIN definition, please refer to the individual user manual.

Connection between inverter and signal receiver:

1. Connection with PIN communication port

Find the correct PINs according to the PIN definition list. Then connect the wires from DRED or RRCR device to the corresponding PIN ports.

For Australia and New Zealand:

Picture 7: Connection of DRED with PIN communication port

For Europe:

Picture 8: Connection of RRCR with PIN communication port

Caution: Excessive voltage can damage the inverter! External voltage of DRM port doesn't over +5V.

2. Connection with RJ45 communication port

Prepare a RJ 45 LAN cable and remove one end. Then connect the concrete PINs based on the following picture.

For Australia and New Zealand:

Picture 9: Connection of DRED with PIN communication port

For Europe:

PIN 1 2 3 4 5 6 7 8
Pin DRM5 DRM6 DRM7 DRM8 Ref/Gen COM/DRM0 standby
Description DRMs Power Control
0% 30% 60% 100%

Picture 10: Connection of RRCR with RJ45 communication port

Caution: Excessive voltage can damage the inverter! External voltage of DRM port doesn't over +5V.

How to enable and disable RRCR function

The RRCR function can be enabled and disabled through Growatt online installer platform Growatt OSS and local configuration APP ShineTools.

Picture 11: Setting on ShineTools (local) and OSS platform (remote)

Please confirm that the inverter and Shine Tools are the latest FW version.

Priority of energy management functions

Additionally, there is other 2 different energy management requirements beside DRMS/RRCR control used in inverter operation:

  1. Export limitation: limitation of electrical power amount exported (sent back) to the grid. This value is mostly aligned with grid distributor.
  2. VPP function: Virtual Power Plant, which is usually used for grid balancing and frequency regulation, peak shaving or centralized control......

In some scenarios, some or all these energy managements may exist in one system at the same time. In this case, Growatt inverter will ensure the DRMS/RRCR control and export limitation function as the highest priority. The inverter will perform the lower value of DRMS/RRCR demand and export limitation firstly, and then if there is VPP control, the output power can only be adjusted within that limitation.

Models: DRMS PV Inverter, DRMS PV, Inverter

PDF preview unavailable. Download the PDF instead.

Growatt DRMS RRCR Function EN 202409 WPS 文字

Related Documents

Preview Growatt Hybrid Inverter Conformity Certificate - MOD Series
Certificate of Conformity for Growatt MOD 3000TL3-XH to MOD 10KTL3-XH hybrid inverters, confirming compliance with UNE 217001:2020-10 and Spanish low voltage regulations.
Preview Growatt SPH TL3 BH-UP Series Installation and Operation Manual
Comprehensive guide for installing and operating the Growatt SPH TL3 BH-UP Series hybrid solar inverters and energy storage systems. Covers safety, product description, installation, commissioning, operation, maintenance, and specifications.
Preview Growatt SPH TL3 BH-UP Series Installation and Operation Manual
This manual provides detailed product information and installation instructions for the Growatt SPH TL3 BH-UP Series hybrid inverters. It covers safety precautions, product descriptions, installation procedures, commissioning, operation modes, troubleshooting, and technical specifications.
Preview Growatt Hybrid Inverter Installation Guide
This guide provides detailed instructions for installing Growatt hybrid inverters, including models like MIN-XH and MOD-XH, along with ARK battery systems and compatible meters. It covers essential wiring, connections, and troubleshooting steps for a successful setup.
Preview Growatt Energy Storage Configuration Checklist
A comprehensive checklist detailing the configuration and compatibility of Growatt's energy storage systems, including ARK LV, ARK HV, AXE LV, ML33RTA, GBLI 6532, ARK XH, and APX HV series with various inverters and battery modules.
Preview Intertek Unit Certificate for Growatt SPH and SPA Series Hybrid Inverters
This document contains the Intertek Unit Certificate for the Growatt SPH and SPA series of hybrid inverters, detailing their compliance with network and system protection standards, including VDE-AR-N 4105:2018-11 and DIN VDE V 0124-100.
Preview Growatt MID 11-30KTL3-XH User Manual: Installation, Operation, and Maintenance Guide
Comprehensive user manual for the Growatt MID 11-30KTL3-XH series of hybrid solar inverters. Covers installation, electrical connections, commissioning, operation, maintenance, and troubleshooting for photovoltaic (PV) plant operating personnel and qualified electricians.
Preview Growatt SPH10000TL-HU-US Hybrid Inverter: Installation & Operation Manual
Comprehensive user manual for the Growatt SPH10000TL-HU-US Grid-Hybrid Inverter. Covers detailed wiring diagrams, parallel connection configurations, breaker recommendations, and step-by-step guidance on using the ShineTools mobile app for system monitoring and commissioning.