- Model: OK Series Fixed 19 Rack Uprights
- Components: Fixed Upright, Fixing Bracket, Nuts, Hex Screws, Washers, Horizontal Rail, Cage Nuts
- Tools Required: 10mm extended socket, Driver or Screwdriver, Crescent wrench
Product Usage Instructions
STR-T (Horizontal Rail) Assembly:
- Insert four cage nuts into the square cutouts of the OKK Frame at the desired positions.
- Use a 10mm extended socket or Driver to secure the assembly.
Fixing Bracket Installation:
- Place two fixing brackets per horizontal rail.
Fixed Upright Installation:
- Position the fixed upright with the open channel facing inward, against the fixing brackets.
- Attach using one M6x16 hex screw, one M6 Nut, and washers as needed.
OK Series Fixed 19” Rack Uprights Guide
OK STRK BOM | ||
Item | Qty | Part Description |
1 | 2 | Fixed Upright (STRK) |
2 | 4 | Fixing Bracket |
3 | 4 | M6 Nut |
4 | 12 | M6x16 Hex Screw |
5 | 16 | M6 Washer |
OK STR-T BOM | ||
Item | Qty | Part Description |
6 | 2 | Horizontal Rail (STR-T) |
7 | 8 | Flanged Cage Nut |
8 | 8 | Cage Nut |
9 | 8 | M6 Washer |
10 | 8 | M6x16 Hex Screw |
STR-T (Horizontal Rail) Assembly
Tools Required: 10mm extended socket, Driver or Screwdriver.
- The top horizontal rail is wider than the bottom to fit the single mounting rail on the OKK Top Element (Figure 1).
- Orient the obround cutouts towards the enclosure front to mount correctly on the OKK Elements (narrow flange section towards front).
- Both rails are installed identically
- Insert four flanged cage nuts (Item 7) from the bottom into each horizontal rail (Figure 2).
- For 19” configurations, place the flanged cage nuts into the second square cutouts from each rail end.
- Insert four cage nuts (Item 8) into the square cutouts of the OKK Frame at the desired positions (Figures 3 & 6).
- Attach each rail to the frame using four M6x16 hex screws (Item 10) and M6 washers (Item 9). See Figure 3.
- Align with the previously installed frame cage nuts.
- Torque Specifications: 100 in-lbs per M6 screw.
STRK (Fixed Upright) Assembly
Tools Required: 10mm extended socket, Driver or Screwdriver, Crescent wrench
- For enclosures 600 mm wide, fixed uprights (Item 1) can be mounted directly to the OKK Frame – horizontal rails are not required.
Fixing Bracket Installation
- Place two fixing brackets (Item 2) per horizontal rail (Item 6).
- Ensure flanges face the enclosure walls.
- Secure each bracket to the rail using two M6x16 hex screws (Item 4) and M6 washers (Item 5). See Figure 4.
- Fasten into the previously installed flanged cage nuts (Item 7) on the horizontal rails.
- Torque Specifications: 70 in-lbs per M6 screw.
Fixed Upright Installation
- Position the fixed upright (Item 1) with the open channel facing inward, against the fixing brackets.
- Attach using one M6x16 hex screw (Item 4), one M6 Nut (Item 3), and two M6 washers (Item 5) per bracket.
- Insert the screw and one washer from the outside of the upright and bracket.
- Secure the nut and the second washer from the inside of the fixed upright. See Figure 5.
- Torque Specifications: 90 in-lbs per M6 screw.
FAQs
Q: What tools are required for assembly?
A: The assembly requires a 10mm extended socket, Driver or Screwdriver, and a Crescent wrench.
Q: How many cage nuts should be inserted for the Horizontal Rail Assembly?
A: Four cage nuts should be inserted into the square cutouts of the OKK Frame.