4 5 1. Preface 1.1 Overview This manual is an integral part of Sunways STS 3-6kW series single-phase inverters (hereinafter referred to as the inverter).

PDF User Manual - suntech-power.com.au


File Info : application/pdf, 18 Pages, 2.52MB

PDF preview unavailable. Download the PDF instead.

Sunways-STS3-6KTL-User-Manual
Grid-connected PV Inverter Single Phase Dual MPPT
User Manual
STS-3K/3.6K/4.2K/4.6K/5K/6KTL
Sunways Technologies Co., Ltd. 1

CONTENTS

1. Preface ........................................................................................................................5
1.1 Overview........................................................................................................5 1.2 Target Groups ................................................................................................5
2. Safety Instructions ................................................................................................5
2.1 Safety Notes ..................................................................................................5 2.2 Statement ......................................................................................................5 2.3 Important Safety Matters .............................................................................6 2.4 Symbols Explanation ....................................................................................7
3. Product Description .............................................................................................9
3.1 Basic Features ...............................................................................................9 3.2 Physical Layout ...........................................................................................10 3.3 Display Interface .........................................................................................12 3.4 Packing List..................................................................................................13
4. Installation..............................................................................................................13
4.1 Location .......................................................................................................13 4.2 Mounting .....................................................................................................15 4.3 Electrical Connection .................................................................................17 4.4 Monitoring Device Installation ...................................................................22 4.5 CT/RS485/DRED Connection ......................................................................23 4.6 System Layout of Units without Integrated DC Switch ............................26
5. Start and Stop .......................................................................................................27
5.1 Start the Inverter .........................................................................................27 5.2 Stop the Inverter .........................................................................................27
6. General Operation...............................................................................................28
6.1 Display Operation .......................................................................................28 6.2 Auto-Test......................................................................................................29 6.3 AC Output Boost for STS-5KTL Inverter.....................................................30 6.4 Power Quality Response Modes ................................................................30 6.5 Country Code (Safety Code) Setting..........................................................30 6.6 Online Monitoring APP ...............................................................................30
7. Troubleshooting...................................................................................................31
7.1 Error Message ..............................................................................................31 7.2 Maintenance................................................................................................32
8. Technical Parameters ........................................................................................33

2

3

Attention
The products, services or features purchased are subject to the commercial contracts and terms of Sunways technologies Co., Ltd. All or part of the products, services or features described in this document may not be within purchased. Unless otherwise agreed in the contract, the Company shall not make any express or implied declaration or guarantee of the contents of this document. Due to product version upgrades or other reasons, the contents of this document will be updated periodically. Unless otherwise agreed, this document serves only as a guide to use, and all statements, information and recommendations in this document do not constitute any express or implied guarantee.
Manufacturer: Sunways Technologies Co., Ltd. Address: No. 1, Second Road, Green Industrial Zone, Chongshou Town,
Cixi City, ZheJiang Province, PEOPLE'S REPUBLIC OF CHINA Website: www.sunways-tech.com Service Mail: service@sunways-tech.com Hotline: +86 400-9922-958
4

1. Preface
1.1 Overview
This manual is an integral part of Sunways STS 3-6kW series single-phase inverters (hereinafter referred to as the inverter). It mainly introduces the assembly, installation, electrical connection, maintenance and troubleshooting of the products. Before installing and using the inverter, please read this manual carefully, understand the safety information and be familiar with the functions and characteristics of the inverter.
1.2 Target Groups
This manual is applicable to the electrical installers with professional qualifications and end-users. If there are any problems in the installation process, please call Sunways service telephone at +86 400-9922-958 or email Sunways at service@sunways-tech.com for consultation.
2. Safety Instructions
2.1 Safety Notes
2.1.1 Before installation, please read this manual carefully and follow the instructions in this manual strictly. 2.1.2 Installers need to undergo professional training or obtain electrical related professional qualification certificates. 2.1.3 When installing, do not open the front cover of the inverter. Apart from performing work at the wiring terminal (as instructed in this manual), touching or changing components without authorization may cause injury to people, damage to inverters and annulment of the warranty. 2.1.4 All electrical installations must conform to local electrical safety standards. 2.1.5 If the inverter needs maintenance, please contact the local designated personnel for system installation and maintenance. 2.1.6 To use this grid-connected inverter for power generation needs the permission of the local power supply authority. 2.1.7 The temperature of some parts of the inverter may exceed 60° C during operation. To avoid being burnt do not touch the inverter during operation. Let it cool before touching it. 2.1.8 When exposed to sunlight, the PV array generates dangerous high DC voltage. Please operate according to our instructions, or it will result in danger to life.
2.2 Statement
Sunways Technologies Co., Ltd. has the right not to undertake quality assurance in any of the following circumstances:
5

2.2.1 Damages caused by improper transportation. 2.2.2 Damages caused by incorrect storage, installation or use. 2.2.3 Damages caused by installation and use of equipment by non-professionals or untrained personnel. 2.2.4 Damages caused by failure to comply with the instructions and safety warnings in this document. 2.2.5 Damages of running in an environment that does not meet the requirements stated in this document. 2.2.6 Damages caused by operation beyond the parameters specified in applicable technical specifications. 2.2.7 Damages caused by unauthorized disassembly, alteration of products or modification of software codes. 2.2.8 Damages caused by abnormal natural environment (force majeure, such as lightning, earthquake, fire, storm, etc.). 2.2.9 Any damages caused by the process of installation and operation which don't follow the local standards and regulations. 2.2.10 Products beyond the warranty period.
2.3 Important Safety Matters
Table below shows the symbols that may appear in this document and their definition:

Symbol

Description

Danger

Dangerous situation, if not avoided, it could result in death or serious personal injury.

Warning

Potentially dangerous situation, if not avoided, may result in death or serious personal injury.

Caution Attention Note

Potentially dangerous situation, if not avoided, may result in moderate or minor personal injury.
The safety warning information about equipment or environment, to prevent equipment damage, data loss, equipment performance degradation or other unpredictable results.
Symbol highlights important information, best practices and tips, etc.

6

2.4 Symbols Explanation
This chapter mainly elaborates the symbols displayed on the inverter, nameplate and packing box. 2.4.1 Symbols on the Inverter

Symbol

Description

Inverter status indicator.

Inverter running indicator.

Grounding symbol, the inverter casing needs to be properly grounded.

2.4.2 Symbol on the Inverter nameplate Symbol

Description

The inverter cannot be disposed of with household waste.

Please read the instructions carefully before installation.
Do not touch any internal parts of the inverter until 5 min after being disconnected from the mains and PV input.
CE mark, the inverter complies with the requirements of the applicable CE guidelines.
TUV certification.

SAA certification. Danger. Risk of electric shock!

The surface is hot during operation and no touch is allowed.
Electric shock hazard, live parts, risk of electric shock, do not touch.
7

2.4.3 Symbol on the Packing box Symbol Handle with care.

Description

This side up.

Keep dry.

Stacked layers.

8

3. Product Description
3.1 Basic Features
3.1.1 Function The Sunways STS 3~6kW series inverter is a single-phase grid-connected PV inverter which used to efficiently convert the DC power generated by the PV string into AC power and feed it into the grid. 3.1.2 The STS 3~6kW series inverter includes 6 models which are listed below: STS-3KTL, STS-3.6KTL, STS-4.2KTL, STS-4.6KTL, STS-5KTL, STS-6KTL 3.1.3 Applicable grid type The applicable grid types for the Sunways STS 3~6kW series are TN-S, TN-C, TN-C-S and TT. When applied to the TT grid, the voltage of N to PE should be less than 30V. For more details please see Figure 3-1: 3.1.4 Storage conditions 1) Inverter must be stored in its original packaging. 2) The storage temperature and humidity should be in the range of -30 ° C and + 60 ° C, and less than 90%, respectively. 3) If a batch of inverters needs to be stored, the height of each pile should be no more than 6 levels.

STS Single Phase

STS Single Phase

STS Single Phase

STS Single Phase

Figure 3-1 Applicable grid types

9

3.2 Physical Layout
3.2.1 Inverter front view:

410mm

Logo

360mm

Display

3.2.2 Inverter side view:

Figure 3-2 Front view 120mm

360mm

Name Plate
Figure 3-3 Side view 10

3.2.3 Inverter bottom view:

120mm

DC Switch (Optional)

Back Rail

AC Output Terminal

DC Input Terminal

Com1 Port Com2 Port (Optional)

3.2.4 Inverter back view:

Figure 3-4 Bottom view

Back Rail

Vent Valve Figure 3-5 Inverter back view
11

3.3 Display Interface

3.4 Packing List
The package of the inverter includes the following accessories. Please check whether the accessories in the packing box are complete when receiving the goods. See Figure 3-7 for the packing list:

sunways

Figure 3-6 Display interface

Item Indicator Status

Description

Off

No input voltage detected or input voltage is too low.

Slow flashing Inverter powered on, waiting for the grid connection.

1

Power Indicator

Quick flashing Inverter detected grid power and entered self-test status.

On

Normal, grid-connected and power generated.

On

An alarm or fault is detected, specific fault information can be viewed from the display.

Off

The inverter is running normally.

2

Alarm Indicator

Slow flashing

The monitoring device is not connected to the router or is not connected to internet.

Quick flashing

The monitoring device is connected to the router or connected to internet but not connected to the server.

3

OLED Display

On

Display the inverter operating information.

Off

If the button pressed without any response, the screen is faulty or not well connected.

4

Button

Physical button

Switch OLED display information and set parameters by short press and long press.

12

Inverter × 1

Wall Bracket × 1

Expansion Bolt × 4 3Pin Terminal × 1

PV Terminal × 2

Monitoring Device × 1(Optional)

AC Terminal × 1

Ground Terminal × 1 6Pin Terminal × 1

User Manual

Quick Guide
Inspection Report

User Manual × 1 Quick Guide × 1 Inspection Report × 1

Figure 3-7 Packing list

Note



Export limitation & control version 2pcs; RS485 and DRED version 1pcs (This connector already pre-installed inside the inverter).

 DRED version only (This connector already pre-installed inside the inverter).

4. Installation
4.1 Location
The Sunways STS 3~6kW series inverter is designed with IP65 protection enclosure for indoor and outdoor installations. When selecting an inverter installation location, the following factors should be considered: 1) The wall on which the inverter is mounted must be able to withstand the weight of the inverter. 2) The inverter needs to be installed in a well-ventilated environment. 3) Do not expose the inverter directly to strong sunlight to prevent excessive temperature operation. The inverter should be installed in a place with shelter to prevent direct exposure to sunlight and rain. 4) Install the inverter at eye level for easy inspection of screen data and further maintenance. 5) The ambient temperature of the inverter installation location should be between -30 ° C and 60 ° C. 6) The surface temperature of the inverter may reach up to 75 ° C. To avoid risk of burns, do not touch the inverter while it's operating and inverter must be installed out of reaching of children. 4.1.1 Recommended installation location of the inverter, as shown in Figure 4-1:
13

Figure 4-1 Recommended installation location

Warning

Do not put flammable and explosive articles around the inverter.

4.1.2 The requirements for inverter installation spacing are shown in Figure 4-2:

500mm

500mm

300mm

300mm

300mm

500mm

500mm

Figure 4-2 Recommended installation spacing 4.1.3 The installation angle of the inverter is recommended as shown in Figure 4-3:

4.2 Mounting
4.2.1 Wall bracket installation Dimensions of wall bracket, see Figure 4-4:
220mm

10mm

110mm

110mm

16mm

150mm

104mm

Figure 4-4 Dimensions of wall bracket
1) Use the wall bracket as the template to mark the position of 4 holes on the wall. See Figure 4-5 for details:

Figure 4-3 Recommended installation angle 14

Figure 4-5 Marking hole position using installation bracket 15

2) Bracket assembly Prepare the two M5 screws and Z-shaped plate in the accessory bag, then fix the Z-shaped plate to the mounting bracket.

4.2.2 Mounting the inverter Lift up the inverter, hang the back rail on the fixed wall bracket carefully. Screws the inverter to the Z-shaped plate ( The lock is purchased separately). See Figure 4-8 for details:

Figure 4-6 Bracket assembly 3) Use an electrical driller with 10mm diameter bit to drill 4 holes in the wall with 80 mm depth.

Warning

Before drilling, make sure to avoid any buried water tube and electric wires in the wall.

4) Insert the expansion tubes into the holes and tighten them, then fix the bracket onto the wall with expansion screws by using a cross screwdriver, as shown in Figure 4-7:

Figure 4-7 Fixing the wall bracket 16

Figure 4-8 Mounting the inverter
4.3 Electrical Connection

Danger

A high voltage in the conductive part of the inverter may cause an electric shock. When installing the inverter, make sure that the AC and DC sides of the inverter are completely de-energized.

Warning

Do not ground the positive or negative pole of the PV string, otherwise it will cause serious damage to the inverter.

Warning

Static may cause damage to the electronic components of the inverter. Antistatic measures should be taken during installation and maintenance.

Do not use other brands or other types of terminals other than the terminals in
Attention the accessory package. Sunways has the right to refuse all damages caused by
the mixed-use of terminals.

Moisture and dust can damage the inverter, ensure the cable gland is securely
Attention tightened during installation. The warranty claim will be invalidated if the
inverter is damaged as a result of a poorly connected cable connector.

4.3.1 Inverter PV string connection

4.3.1.1 The following must be considered when making electrical connections to the inverter:

1) Disconnect the AC breaker switch on the grid side.

2) The DC switch of the inverter must be turned to the "OFF" position.

3) For best practice, ensure PV modules of the same model and specifications are connected in

each string.

17

4) Make sure the maximum output voltage of each PV string does not exceed 600V. 4.3.1.2 DC connector assembly procedure 1) Select the appropriate photovoltaic cable:

Cable type General photovoltaic cable

Traverse area (mm²)

Range (mm²)

Recommended value (mm²)

2.5-4.0

4.0

2) Peel off the DC cable insulation sleeve for 7 mm, as shown in Figure 4-9:

Wire Traverse area 2.5-4mm2

7mm

Figure 4-9 3) Disassemble the connector in the accessory bag, as shown in Figure 4-10:
+
-
Figure 4-10 4) Insert the DC cable through the DC connector nut into the metal terminal and press the terminal with a professional crimping plier (pull back the cable with some power to check if the terminal is well connected to the cable), as shown in Figure 4-11:
Crimping Plier

Figure 4-11 18

5) Insert the positive and negative cables into the corresponding positive and negative connectors, pull back the DC cable to ensure that the terminal is tightly attached in the connector. 6) Use an open-end wrench to screw the nut to the end to ensure that the terminal is well sealed, as shown in Figure 4-12:
Open-end Wrench

Figure 4-12

Warning

1.Before assembling the DC connector, make sure that the cable polarity is correct.
2.Use a multimeter to measure the voltage of the DC input string, verify the polarity of the DC input cable, and ensure that each string voltage is within 600V.

7) Insert the positive and negative connectors into the inverter DC input terminals respectively, a click sound should be heard if the terminals are well connected, as shown in Figure 4-13:

Figure 4-13 8) Seal the unused PV terminals with the terminal caps.

4.3.2 Connection of AC output

The Sunways STS 3~6kW series single phase inverter operates with grid voltage and frequency

of 220/230V and 50/60Hz, respectively.

This inverter includes an integrated residual current device (RCD) .

If an external residual current device (RCD) is used, a device of type (A/AC etc) should be used,

with a tripping current of 300mA or higher.

19

The recommended cable and AC switch for the Sunways STS 3~6kW series single phase inverter are shown in the following table:

Model Cable

STS-3KTL STS-3.6KTL STS-4.2KTL STS-4.6KTL STS-5KTL

4mm2

4mm2

4mm2

4mm2

6mm2

STS-6KTL 6mm2

Breaker

20A

25A

32A

32A

40A

40A

Warning

An AC breaker must be connected on the AC side of the inverter. Any loads cannot be connected to the inverter without the AC breaker.

4.3.2.1 AC connector connection steps 1) Take the AC connector out of the accessory bag and disassemble it, as shown in Figure 4-14:

Allen Key
Figure 4-16 4) According to the arrow direction push the threaded sleeve to make it connected with the AC terminal head and then rotate the cable gland clockwise to lock it, as shown in figure 4-17:

Cable Gland

Threaded Sleeve

AC Terminal Head

Figure 4-14
2) According to the table above, select an appropriate cable, peel the insulation sleeve of AC cable off for 50mm, and peel off the end of L /PE / N wires for 8mm, as shown in Figure 4-15:

Wire Diameter:10-14mm

Stri p Length:8mm

50mm
Figure 4-15 3) Insert the stripped end of each three wire into the appropriate hole of the terminal head (yellow green wire to PE port, red or brown wire to L port, and blue or black wire to the N port). Please try to pull out the cable to make sure it is well connected. As shown in Figure 4-16: 20

Figure 4-17
5) Connect the AC connector to the inverter AC terminal, and the slight click shows that the connection is in the place. As shown in figure 4-18:

Figure 4-18 Connect the AC connector

21

4.3.3 External ground connection

Danger

Do not connect the N-wire as a protective ground wire to the inverter casing. Otherwise, it may cause electric shock.

Good grounding is good for resisting surge voltage shock and improving EMI
performance. Inverters must be well-grounded.
Attention For a system with only one inverter, the PE cable needs to be grounded.
For a multi-inverter system, all inverters PE wires need to be connected to the same grounding copper bar to ensure equipotential bonding.

Ground terminal connection steps: 1) The external grounding terminal is located in the lower right side of the inverter. 2) Fix the grounding terminal to the PE wire with a proper tool and lock the grounding terminal to the grounding hole in the lower right side of the inverter, as shown in Figure 4-19. 3) The cross-setional area of the external grounding cable is 4mm².

Figure 4-19 Grounding terminal connection
4.4 Monitoring Device Installation
Sunways STS 3~6kW series single phase inverter supports WiFi, GPRS, LAN and RS485 communication. Plug the WiFi, LAN or GPRS module into the COM1 port in the bottom of inverter (as shown in Figure 4-20). A slight "click" sound during the installation represents that the assembly is in place.
22

Figure 4-20 Monitoring device installation

Note

1.The GPRS and LAN version module does not need to be configured.
2.The WiFi version module needs to be configured to the router for the first installation. If the router name or password are changed, the WiFi dongle will need to be reconfigured. For details, please refer to the [QUICK INSTALLATION GUIDE] which is attached to the accessory bag.

Attention

Do not touch the waterproof plug in the card slot except for replacing the SIM card. In that case, please make sure the card slot is completely sealed by the weatherproof plug after replacing the SIM card. Any damages caused by improper waterproof plug placement, will void warranty.

4.5 CT/RS485/DRED Connection
4.5.1 Terminals definition Inverter communication ports are located at the behind of the CT/DRED plate at the bottom and include CT port, RS485 port (used for Datalogger connection), and DRED port, as shown in Figure 4-21

Note

Port 1 CT Port

Port 2 RS485 Ports

Port 3 DRED Port

23

Port 1
1 2 3

Port 2
1 2 3

1 2 Port 3 3 4 5 6

Note

Figure 4-21
1.This port is available on export limitation & control, RS485 and DRED versions of the inverter only. 2.The Pin connector in inverter Port1 and Port2 may vary from 2Pin to 3pin according to the shipment version.

Different versions of the inverter have different terminals, which are defined as follows:

Port

Function

Port 1

1.Only Export limitation & control version with this port.
2.Connect external CT to activate the Export Limitation&control function of Sunways STS series inverter.
3.The color of CT is only identified by Sunways.

Port 2

1.Export limitation & control/RS485/DRED version with this port.
2.In case of multiple inverters, all the inverters can be daisy-chained via RS485 cables.

NO.

Definition

1

Connect S1 cable (Black CT) or white black cable (Blue CT)

2

Connect S2 cable (Black CT) or black cable (Blue CT)

3

NULL

1

RS485 A

2

RS485 B

3

PE/NULL

1 1.Only DRED version with this port.

2.DRED means demand response enable device. The AS/NZS 4777.2:2015 requires inverters to

2

support demand response mode (DRM). This

function is for inveters that comply with AS/

3

Port 3 NZS4777.2:2015 standard.

3.Sunways inverter is fully compliant with

4

all DRM. The 6pin connector is used for DRM

connection.

5

4.Support DRM command: DRM0, DRM5, DRM6,

DRM7, DRM8. 6

COM/DRMO REFGEN DRM4/8 DRM3/7 DRM2/6 DRM1/5

24

4.5.2 RS485 Communication STS series single-phase inverter supports multiple inverters daisy-chain connection to a data logger via RS485 communication. Multiple inverters connection diagram as shown in Figure 4-22

Data logger
LAN/WiFi /GPRS

STS 3~6KTL

STS 3~6KTL

series inverter series inverter

STS 3~6KTL series inverter

...

RS485

RS485

RS485

Router

Internet

Internet

Sunways server

Figure 4-22

The maximum distance between the inverter at the end of the daisy chain and the Data logger should be within 1000m.

Attention

It is recommended to use the RS485 communication cable with a crosssectional area of 0.75-1.5mm² and an outer diameter of 5mm-10mm. RS485 cable requirements: Shielded twisted-pair cable or shielded twisted Ethernet cable.

4.5.3 Export limitation & control or power limit solution Export limitation & control or power limit solution, wiring instructions and configuration, please contact Sunways after-sales at service@sunways-tech.com. 4.5.4 Wiring Steps: 1) Remove the CT/DRED plate in the bottom of the inverter with a cross screwdriver. 2) Put the cable through the connector and connect to the terminal in the following order: screw cap, sealing ring, insulator, metal plate, nut and 3/6pin connector, as shown in Figure 4-23: 3) Insert the cable to the port in the 3/6pin connector and fasten with a screwdriver. 4) Insert the 3/6pin connector into the 3/6pin connecter inside the inverter, and screw the CT/ DRED plate back with a cross screwdriver, as shown in Figure 4-24:

25

Insulator ring Nut

213 Port 1
231 Port 2 135246 Port 3

Screw cap

Metal plate

Sealing ring

3/6pin connector

Figure 4-23

20-25mm
6mm 20-25mm
6mm

Figure 4-24
4.6 System Layout of Units without Integrated DC Switch
Local standards or codes may require that PV systems are fitted with an external DC switch on the DC side. The DC switch must be able to safely disconnect the open-circuit voltage of the PV array plus a safety reserve of 20%. Install a DC switch to each PV string to isolate the DC side of the inverter. We recommend the following electrical connection, as shown in Figure 4-25:
26

DC Switch -+

Inverter
DC INPUT AC OUTPUT
+-

Grid AC Breaker

To grounding electrode

PE L N PE

Figure 4-25
5. Start and Stop
5.1 Start the Inverter
When starting the inverter, follow these steps: 1) Turn on the AC breaker first (close the AC circuit breaker). 2) Turn on the DC switch in the bottom. If the PV string voltage higher than the inverter start-up voltage, the inverter will start. 3) When both AC and DC power supply are normal, the inverter is ready to start. The inverter will initiate checking its internal parameters and grid parameters, if it is within the range, the green light on the left side of the screen begins to flash, and the "Waiting" message will be displayed on the OLED display. 4) After self-checking completed, the inverter will start generating electricity, the green light will remain on, and the OLED display will display real-time power information.
5.2 Stop the Inverter
When turning off the inverter, please follow the steps below: 1) Turn off the AC breaker first. 2) Wait 30 seconds and then turn the DC switch to the "OFF" position. At this time, there is remaining power in the inverter capacitor. Wait for 5 minutes until the inverter is completely de-energized before conducting any work on the inverter. 3) Disconnect the AC and DC cables.

27

6. General Operation
6.1 Display Operation
When the inverter is turned on, the following interfaces will be displayed on the OLED display, and the OLED display allows the user to check various operation information and to modify the settings of the inverter. Please refer to the following display operation flow for details:

Waiting

Main Window

Checking

Normal

Fault Info

Firmware Updating

PV Voltage PV Current

Grid Voltage Grid Current
Grid Freq

E-Day

E-Total

H-Total

Not WiFi

Modbus Addr

WIFI Reload

WIFI Reset

RSSI

Model Name

General Settings

Advanvced Settings

Fault Info

System Info

Setting

Setting

Setting

Time Set

Language Set

Error Message

SN/FM Version

Setting

Setting

OverLoad (AU)

ReConnect

CT Ratio

Power Factor

Feed in Grid

Export Limit

Safety Set

Setting

Setting

Setting

Setting

Setting

Setting

Setting

Short press(1s), switch window
Long press(3s), enter the lower Menu 28

Tip: Please wait for 10 seconds and the inverter will automatically save your settings or modifications.

6.2 Auto-Test
This function is disabled by default, and will be only functional in the safety code of Italy. Short press the button several times until "Auto Test CEI 0-21" displays on the screen, press and hold the button 3 seconds to activate "Auto Test". After the auto test is finished, short press the button several times until the screen displays "Auto Test Record", and hold the button 3 seconds to check the test results. The auto test type will be chosen from "Remote" and "Local" before starting the auto test. "Remote" is set as 1 by default, which only can be modified to "0" by sending an external command and "Local" is set to 0 by default, which can be modified to 1 through operating the button on the inverter. According to the requirements of the standard, the test has been divided into three modes: 1) "Remote" set as 1, "Local" set as 0, then the test order is 59.S159.S227.S181>.S281<.S2; 2) "Remote" set as 1, "Local" set as 1, then the test order is 59.S159.S227.S181>.S181<.S1; 3) "Remote" set as 0, "Local" set as 1, then the test order is 59.S159.S227.S181>.S281<.S2. Connect the AC cable, auto test will start after the inverter connected to the grid, see the operation steps below:

Short press(1s), switch window
Long press(3s), enter the lower Menu

Setting

Password 1111

Main Windows

General Settings

Remote Cmd 1

Local Cmd 0

Auto Test CEI 0-21

If Tested
Test Record

Wait

Wait

IPS Item Testing

Test Pass/Fail

IPS Item xxxxx

Wait

Select Items

Wait

Wait

IPS Item

IPS Item

Verify Ok

Password

Test All

Test Null

1111

Test Result Display

The auto test will start when the correct test item is selected, and the test result will be displayed on the screen when it finished. If the test was successful , it will display "Test Pass", otherwise will display "Test Fail". After each item tested, the inverter will reconnect to the grid and automatically start the next test according to the requirements of CEI 0-21.
29

6.3 AC Output Boost for STS-5KTL Inverter
The maxium output power of the residencial single-phase solar system is 5kVA in most of the states in Australia. Check the local DNSPs or authorities if they allow AC output more than 5kVA.

Note

1. Advanced settings can only be changed by qualified professionals with relevant certifications.
2. Check requirements with local NSP before activating 10% AC output boost.
3. Only STS - 5KTL has the option to enable/disable the 10% AC output boost.
4. The default password to access the advanced settings is 1111, applicable to all on-grid inverters.

Please follow this flow chart to enable 10% AC output boost: Main Windows

Short press(1s), switch window
Long press(3s), enter the lower Menu

Advanced Settings

Password 1111

Verified OK

OverLoad(AU) ON

Setting OK

PV Voltage PV Current

Export Limit OFF

6.4 Power Quality Response Modes
6.4.1 Power derating for voltage variation (Volt-Watt mode) This mode can be enabled via the configuration software. Please contact Sunways Technical Support at service@sunways-tech.com for more information. 6.4.2 Reactive power regulation for voltage variation (Volt-VAr mode) This mode can be enabled via the configuration software. Please contact Sunways Technical Support at service@sunways-tech.com for more information.
6.5 Country Code (Safety Code) Setting
Please set "Country code (Safety code)" under the menu "Safety Set" in "Advanced Settings".
6.6 Online Monitoring APP
Customers can check their inverters real-time power, warnings and status through the App"SunwaysHome"anytime anywhere.

30

7. Troubleshooting

7.1 Error Message
Sunways STS 3~6kW series single phase inverter is designed in accordance with grid operation standards, and conform to the requirements of safety and EMC. The inverter had passed a series of rigorous tests to ensure it runs sustainably and reliably before shipment. When a fault occurs, the corresponding error message will be shown on the OLED display, and in this case, the inverter might stop feeding into grid. The fault messages and their corresponding troubleshooting methods are listed below:

Error Message

Troubleshooting

No Display Mains Lost
Grid Voltage Fault
Grid Frequency Fault ISO Over Limitation GFCI Fault PV Over Voltage Inverter Over Temperature

1. Check whether cables are all firmly connected and DC switch is on. 2. Check whether the input voltage meets the working voltage.
1. Check whether the mains supply is lost. 2. Check whether the AC breaker and terminals are well connected.
1. Check whether the safety regulation setting is correct. 2. Check the voltage of the grid. If the grid voltage exceeds the allowed range of inverter protection parameters, please contact the local grid company to resolve. 3. Check whether the impendence of the AC cable is too high. Replace with a thicker AC cable if that is the case.
1. Check whether the safety regulation settings are correct. 2. Check the frequency of the grid. If the grid frequency exceeds the allowed range of inverter protection parameters, please contact the local grid company to resolve.
1. Check whether the PV panels, cables, and connectors are broken or water leaked. 2. Check whether there is a reliable inverter grounding line.
1. The ground current is too high. 2. Check whether the PV cable has a short circuit to ground.
1. Input voltage is too high. 2. Reduce the number of PV panels to make sure the open-circuit voltage of each string is lower than the inverter max allowed input voltage.
1. Check whether the inverter is directly exposed to the sunlight. 2. Reduce ambient temperature.

DCI Fault

Bus Voltage Fault

SCI Fault

SPI Fault E2 Fault GFCI Device Fault

1. Restart the inverter, wait a moment for inverter recovery. 2. If the fault occurs repeatedly, please contact Sunways.

AC Transducer Fault

Relay Check Fail

Flash Fault

31

7.2 Maintenance

Danger

Risk of inverter damage or personal injury due to incorrect service!
Always keep in mind that the inverter is powered by dual sources: PV strings and utility grid.
Before any service work, observe the following procedure. 1. Disconnect the AC circuit breaker and then set the DC load-break switch of the inverter to OFF; 2. Wait at least 5 minutes for inner capacitors to discharge completely; 3. Verify that there is no voltage or current before pulling any connector.

Caution

Keep non-qualified persons away! A temporary warning sign or barrier must be posted to keep non-qualified persons away while performing electrical connection and service work.

Attention

Restart the inverter only after removing the fault that impairs safety performance.
Never arbitrarily replace any internal components.
For any maintenance support, please contact Sunways. Otherwise, Sunways shall not be held liable for any damage caused.

Note

Servicing of the device in accordance with the manual should never be undertaken in the absence of proper tools, test equipment or the latest revision of the manual which has been clearly and thoroughly understood.

Items

Methods

Period

System clean

Check the temperature and dust of the inverter.

Clean the inverter enclosure if necessary. Check if the air inlet and outlet are normal.

Six months to a year (it depends on the dust contents in air.)

Clean the air inlet and outlet if necessary.

32

8. Technical Parameters

Model Start-up Voltage (V)

STS -3KTL
120

STS -3.6KTL
120

STS

STS

-4.2KTL -4.6KTL-

120

120

STS -5KTL
120

STS -6KTL
120

Max. DC Input Voltage (V)

600

600

600

600

600

600

Rated DC Input Voltage (V)

360

360

360

360

360

360

MPPT Voltage Range (V)

100~550 100~550 100~550 100~550 100~550 100~550

DC Input

Full power MPPT voltage range (V) 130~500

No. of MPP Trackers

2

150~500 2

180~500 2

190~500 2

210~500 2

250~500 2

No. of DC Inputs per MPPT

1/1

1/1

1/1

1/1

1/1

1/1

Max. Input Current (A)

12.5/12.5 12.5/12.5 12.5/12.5 12.5/12.5 12.5/12.5 12.5/12.5

Max. Short-circuit Current (A)

15

15

15

15

15

15

backfeed current to the array (A)

0

0

0

0

0

0

Rated Output Power (W) Max. Output Power (W)

3000 3300

3600 3960 

4200 4600

4600 4600

5000 5500 

6000 6600

AC Output Rated Apparent Power(VA) 3000

Max. Apparent Power (VA)

3300

3600 3960 

4200 4600

4600 4600

5000 5500 

6000 6600

Rated Output Voltage (V)

220/230 220/230 220/230 220/230 220/230 220/230

Rated AC Frequency (Hz)

50/60

50/60

50/60

50/60

50/60

50/60

AC Output

AC Output Rated Current (A) Max. Output Current (A)

13

15.7

18.3

20

21.7

26.1

15

18 

21

21

25 

28.7

The Measured Inrush Current (A)

13.5A@44µs

31.5A@55µs

Max. output fault current (A)

50

50

50

50

50

50

Max. output overcurrent protection (A)

50

50

50

50

50

50

Power Factor

0.8 leading ...0.8 lagging

Max. total harmonic distortion

< 3% @Rated Output Power

DCI

< 0.5%In

Note

 : STS-4.6KTL is available for countries using the regulation of VDE4105 only.

 : 3680 for G98

 : 16 for G98

 : 5000 for Belgium

 : 21.7 for Belgium
33

Model Max. Efficiency

STS -3KTL
98.1%

STS -3.6KTL
98.1%

STS

STS

-4.2KTL -4.6KTL-

98.1%

98.1%

STS -5KTL
98.1%

STS -6KTL
98.1%

Efficiency European Efficiency

97.5%

97.5%

97.5%

97.5%

97.5%

97.5%

MPPT Efficiency

99.9%

99.9%

99.9%

99.9%

99.9%

99.9%

DC Reverse Polarity Protection

Integrated

Insulation Resistance Protection

Integrated

DC Switch

Integrated

Surge Protection

Integrated (Type II AC/DC)

Protection Over-temperature Protection

Integrated

Residual Current Protection

Integrated

Islanding Protection

Frequency shift, Integrated

AC Short-circuit Protection

Integrated

AC Over-voltage Protection

Integrated

Dimensions (mm)

410W*360H*120D

Weight (kg)

13

Protection Degree

IP65

Self-consumption at Night (W)

< 1

Topology

Transformerless

Operating Temperature Range (° C)

-30~60

General Data

Relative Humidity(%) Operating Altitude (m)

0~100 3000

Cooling

Natural Convection

Noise Level (dB)

< 25

Display

OLED & LED

Communication Compliance

RS485/WiFi/GPRS/LAN (Optional)
NB/T32004IEC62109IEC62116VDE4105VDE0126UTE C15-712-1 AS4777C10/11CEI 0-21RD1699NBR16149IEC61727IEC60068
IEC61683EN50549EN61000

34

Address: No. 1, Second Road, Green Industrial Zone, Chongshou Town, Cixi City, ZheJiang Province, PEOPLE'S REPUBLIC OF CHINA
Website: www.sunways-tech.com Service Mail: service@sunways-tech.com Hotline: +86 400-9922-958
35

S11-00032-00



References

Adobe PDF Library 15.0 Adobe InDesign CC 14.0 (Windows)