User Guide for RICE LAKE models including: 920i, iQUBE2, Junction Box 920i, Junction Box, iQUBE2 Junction Box 920i, iQUBE2 Junction Box, iQUBE2, Junction Box 920i

iQUBE2 Junction Box/920i Quick-Start Guide

wireless, ethernet, wifi, wlan, installation, help, manual, instructions, 108671, 108680, cw-90, cw-90x, 720i, 820i, iQUBE2, LaserLT

Rice Lake Weighing Systems

Download

Manuals | Rice Lake Weighing Systems

[PDF] iQUBE2 Junction Box/920i Quick-Start Guidewww.ricelake.com › media › a 119...


File Info : application/pdf, 6 Pages, 557.97KB

PDF preview unavailable. Download the PDF instead.

a 119611 iqube2 quickstart enus revb
iQUBE2® Junction Box/920i
Quick-Start Guide
This document will guide you through a typical iQUBE2 to 920i installation with the recommended settings. It assumes an 8-cell truck scale is being used with two iQUBE2 CPU boards.
NOTE: Load cells or simulators must be connected before following the instructions listed in this document. RS-422 and RS-485 are used interchangeably. TEDS is not supported.
Configuration using 920i
Establish a Connection 1. Connect the iQUBE2 and the 920i using an RS-422 connection.
NOTE: RS-422 is recommended over RS-232 due to the 115,200 baud rate of the iQUBE2, RS-232 has a maximum distance of 10 feet and RS-422 has a maximum distance of 1000 feet at this high baud rate. 2. The table below shows connections needed for RS-422 communications between a host 920i and the iQUBE2. Two-wire half duplex is available on Port 4 of the 920i.

920i Board J10 Connector (Port 4)

iQUBE2 J7 Connector

RS-422 Signal GND
RS-422 A RS-422 B

Pin Pin 11 54 65

RS-422 Signal GND1
RS-485 A RS-485 B

Table 1. 2-Wire RS-422 Connections for 920i Host

3. Ensure S2 dip switches on the iQUBE2 CPU board are set to 485 (1,2 both set to OFF). See Figure 1 for S2 dip switch location.

NOTE: If a change is made to switch position, cycle power on the iQUBE2 while SW1 is switched to CFG, as the switch position is only read on power-up. Once power has been re-applied, place the SW1 in the OFF position.

IO4 IO3 IO2 IO1 GND +5V

S1
1
+SIG ­SIG +EXC ­EXC +TD ­TD

CHANNEL 1

1 2
GND +V GND +V CFG OFF

4 3 2 1

6 5 4 3 2 1

1
J12
M/S PORT

1
J7
SERIAL PORT 1

1
J5
DIGITAL I/O

J6
POWER SUPPLY CONNECTOR
SW1
CONFIG SWITCH
J10

485 232
S2
HDPLX FDPLX
########

J14
TMS
J8 TDI TDO TCK GND +3.3

J3 J1

CHANNEL 3

RTS DTR RxD TxD GND1 GND
­TD +TD ­EXC +EXC ­SIG +SIG

COMMUNICATIONS PORT 2

+SIG ­SIG +EXC ­EXC +TD ­TD

CHANNEL 2

J2 J9

J4
HB1

CHANNEL 4

­TD +TD ­EXC +EXC ­SIG +SIG

Figure 1. iQUBE2 CPU Board

July 16, 2024

PN 119611 Rev B

iQUBE2® Junction Box/920i Quick-Start Guide

J7 Pin
1 2 3 4 5 6

RS-232 Signal

RS-485 2-Wire Signal

RS-485 4-Wire Signal

GND1 RxD -- -- TxD --

GND1 -- -- A/+ B/--

GND1 Rx+ RxTx+ Tx--

Table 2. J7 (Port 1) Pin Assignments

J12 Pin Primary iQUBE2 Secondary iQUBE2

1

iQA

2

iQB

3

GND2

4

GND2

iQA iQB GND2 GND2

Table 3. J12 (M/S Port) Pin Assignment

OFF

ON

1

RS-485

RS-232

2

2-Wire

4-Wire

Table 4. S2 Switch Settings

4. Change Port 4 to iQUBE2 and press Enter to save it.

5. Go back to the SERIAL menu and navigate to the CONFIG parameter under the SCALES menu.

6. Press the Change Type softkey until Available A/D's displays in the left column.

10/20/2017
AVAILABLE A/D's Port 4 - Scale 1

12:14PM
SCALES
CONFIG SCALES Scale 1 Scale 2 Scale 3 Scale 4 Scale 5

ASSOCIATED A/D's

Default Upload Connect Download Save and Exit
Figure 2. Scale Association Screen
7. Press left arrow key to highlight Port 4 - Scale 1. 8. Press the ADD softkey to add it to Associated A/D's in the right column. 9. Press the Done softkey. 10. Navigate to the SERIAL menu.

2

Visit our website www.RiceLake.com

11. Change the Port 4 PORTTYPE parameter to 422 (see Figure 3).

iQUBE2® Junction Box/920i Quick-Start Guide

SERIAL PORT 4 IQUBE2 CONFIG

COMMSEL PORTTYPE

232 422 485
Figure 3. PORTTYPE Parameter
12. Navigate to the CONFIG menu and press the Connect softkey (see Figure 4). The serial number will show (i.e., 123XX456*NONE* *NONE* *NONE*). If the serial number does not show, check wiring and dip switches.

10/20/2017
PORTTYPE

12:14PM

SERIAL

DISPLAY

PORT4 IQUBE2

UPDATE

CONFIG

PROGIN COMM SEL PORTTYPE

iQube2 Con guration
Default Upload Connect Download Save and Exit
Figure 4. CONFIG Menu
Add Secondary Boards to the System 1. Under CONFIG, navigate to the BOARDS parameter to select how many boards are being used in the system. 2. Press Enter. 3. Navigate back to BOARDS parameter and press the Auto Assign softkey. Green lights on the iQUBE2 CPU boards will start blinking on all cells.

10/20/2017
PORTTYPE DIGIO

12:14PM

SERIAL

DISPLAY UPDATE

PORT4 IQUBE2 CONFIG

COMM

BOARDS

PROGIN COMM SEL
CELLS

PORTTYPE SCALES

iQube Boards Number of iQube2 boards on port

Auto Assign

Manual Save and Assign Exit

Figure 5. BOARDS Parameter

© Rice Lake Weighing Systems  All Rights Reserved

3

iQUBE2® Junction Box/920i Quick-Start Guide
4. Press and release the setup button (S1) on secondary board #1. This makes cells 5-8 available to the system and registers its serial number with the primary board. The lights on the board will stop blinking.
5. Once the secondary unit has been assigned, press the setup button (S1) on the primary board. 6. You will see a screen showing the primary board serial number and any assigned secondary board serial numbers.

10/20/2017
Primary
Secondary
1) 2) 3)

12:14PM
0
65 __ __

123XX456
456XX789 ________ ________

Auto Assign Done

Edit

Figure 6. Primary and Secondary Boards Screen
7. Press the Done softkey.
Configure and Add Load Cells 1. Under CELLS, set the capacity and confirm the mV/V. 2. Ensure all the AVAILABLE Cells are assigned to the correct scale. See Figure 7 for the correct screen layout.

10/20/2017

12:14PM

CELLS SCALES SMPRAT

AVAILABLE Cells
CELL#15 CELL#6 CELL#7 CELL#8

SCALES Scale 1 Scale 2 Scale 3 Scale 4 Scale 5
A1 A3

ASSOCIATED Cells
CELL#1
CELL#2 CELL#3 CELL#4

A2 A4

Done
Figure 7. Cells 5-8 Added to Scale 1
NOTE: To turn off the warm up function, set the WARMUP parameter to 0. This allows the unit to skip the warm up period when cycling power. 3. Navigate back to the CONFIG parameter. 4. Click the Download button. 5. Select Configuration Only. 6. Download to the iQUBE2. 7. Press the Save and Exit softkey to complete the setup for the iQUBE2. The scale is ready for calibration. NOTE: Refer to the iQUBE2 Installation Manual (PN 106113) for calibration instructions.

4

Visit our website www.RiceLake.com

iQUBE2® Junction Box/920i Quick-Start Guide

GND2 GND2
iQB iQA

GND2 GND2
iQB iQA
GND2 GND2
iQB iQA GND2 GND2 iQB iQA GND2 GND2 iQB iQA

J12

1

3

CELLS 1 ­ 4

2

4

Primary iQUBE²

J12

J12

5

7

CELLS 5 ­ 8

6

8

J12

9

11

CELLS 9 ­ 12

10

12

Secondary iQUBE² #1

Secondary iQUBE² #2

Figure 8. Primary-to-Secondary Communications Wiring

J12

13

15

CELLS 13 ­ 16

14

16

Secondary iQUBE² #3

© Rice Lake Weighing Systems  All Rights Reserved

5

© Rice Lake Weighing Systems Content subject to change without notice. 230 W. Coleman St. · Rice Lake, WI 54868 · USA USA: 800-472-6703 · International: +1-715-234-9171

July 16, 2024

www.ricelake.com

PN 119611 Rev B

