10'x14' WALL-MOUNTED GAZEBO
Model: LGCF1698
Dimensions and Blueprints
The gazebo has overall dimensions of approximately 10 feet by 14 feet (120 inches by 168 inches). Key measurements shown include:
- Pole dimensions: 2.56" (65mm) height, 5.12" (130mm) width.
- Bracket dimensions: 3.46" (88mm) height, 0.472" (12mm) width.
- Overall length: 162.69" (4132mm) or 156.38" (3972mm) depending on the view.
- Overall width: 113.21" (2875.5mm) or 117.13" (2975mm) or 162.8" (4135mm) depending on the view.
- Various beam lengths and heights are indicated in the detailed blueprints.
The blueprints illustrate the structural layout, including pole placement, beam connections, and roof support structure.
Front Pole Assembly
Step 4-1: Bracket Installation
Install Bracket #K1 and Bracket #K2 onto the front Pole #A2. Secure these brackets using five bolts #3.
Step 4-2: Part Installation
Install parts #I1 and #I2 onto Pole #A2. Secure them with four bolts #3. Note: The bolts should not be fully tightened at this stage.
Step 4-3: Pole to Base Connection
Install Pole #A2 onto the base #C2. Secure it using three bolts #3. Repeat these procedures to assemble Pole #A1.
Front Beam Assembly
Step 5: Beam Connector and Cover
Insert the Beam Connector #D3 into the front beam #D2 and secure it with four bolts #3. Insert the other end of Beam Connector #D3 into the front beam #D1 and secure it with another four bolts #3. Apply sealant to the joint between #D1 and #D2. Install the Joint Cover #D4 to the beams #D1 and #D2 by aligning the holes, securing it with two screws #11 and one bolt #9.
Step 6: Beam to Pole Connection
Attach the front beam #D2 to the front pole #A2 and secure it with two bolts #6. Secure Bracket #K1 to the front beam #D2 using two bolts #3. Use two bolts #3 to secure #I1 to the front beam #D2 (viewed from outside and inside). Repeat these procedures to assemble Pole #A1 with Front Beam #D1. Note: Do not fully tighten the bolts at this stage.
Rear Pole Assembly
Step 7-1: Pole Extension and Bracket
Insert the rear pole (upper) #B4 or #B3 into the rear pole (lower) #B2 or B1 and secure it with screws #12. Use bolts #3 to secure Bracket #C3 to the pole. This bracket is used for fixing the post against the wall. If not fixing to the wall, this step can be skipped. Assemble only two pieces for each post according to the actual installation situation.
Step 7-2: Base to Pole Connection
Use four bolts #3 to secure base #C1 to Pole #B1 and #B2.
Rear Beam Assembly
Step 8: Beam Connector and Securing
Insert the Beam Connector #K3 into the rear beam #E2 and secure it with four bolts #3. Insert the other side of Beam Connector #K3 into the rear beam #E1 and secure it with four bolts #3. Align the holes and use two bolts #3 to secure #K4 to the Rear Beam #E2 & E1. Secure the bottom of the rear beam with two bolts #3.
Step 9: Beam to Pole Connection
Attach the rear beam #E1 to the rear pole #B3 and secure it with four bolts #7. Attach the rear beam #E2 to the rear pole #B4 and secure it with four bolts #7.
Side Beam Assembly
Step 11: Beam Connector Installation
Insert the Beam Connector #K3 into the side beam #G1 and secure it with four bolts #3. Insert the other side of Beam Connector #K3 into the side beam #G2 and secure it with four bolts #3. Repeat these procedures to assemble #H1 with #H2.
Frame Assembly
Step 12: Connecting Frame Components
Use two bolts #3 to connect Corner Solidifying Bar #I2 with Side Beam #H1. Use four bolts #7 to connect Side Beam #H1 and #D2. Repeat these procedures to assemble #G1 and #D1. Use four bolts #7 to connect Side Beam #H2 and #E2. Repeat these procedures to assemble #E1 and #B3.
Centre Beam Assembly
Step 13: Centre Beam Connector and Bracket
Insert the Beam Connector #K3 into the center beam #F2 and secure it with four bolts #3. Insert the other side of Beam Connector #K3 into the center beam #F1 and secure it with four bolts #3. Secure it at the bottom with bolts #3 as shown. Combine the Bracket #K5 as shown and insert it into #F1 or #F2, securing it with two bolts #2 on each side.
Step 14: Centre Beam to Side Beam Connection
Assemble the middle beam #F1 or #F2 with the side beam #G1 or #G2 or #H1 or H2 using Bracket #K5, and secure them with four bolts #3. Note: Please do not fully tighten the bolts until all bolts have been screwed into place.
Roof Panel Assembly
Step 15: Preparation
Remove the protective film from the panels before installing the roofing panels.
Step 16: First Row Installation
Install in the order of Black Rubber #L2, Roof Panels #N, Rubber gaskets #L1, and bolts #4 as shown. Connect with the front beam #D1. Secure the bottom with Nuts #8. Apply sealant #14 to the first row of roof panels. Follow the steps of the first row to install the second and third rows of roof panels and fix them with bolts and nuts.
Step 17: Additional Panels
Repeat the above procedures to assemble the 18 Roof Panels #N. Apply silicon sealant to the connection points.
Step 18: More Panels
Repeat the above procedures to assemble the 3 Roof Panels #N.
Step 19: Final Roof Panel and Cover Installation
Place the rubber spacer #L2 between the beams and the roof panel #N and secure them using bolts #4 along with rubber gaskets #L1. Place Roof Cover #J1 & J2 on the higher side of the roof. Insert rubber spacer #L2 into the gap between the beam and the roof panels. Secure with bolt #4, rubber gaskets #L1, and nuts #8.
Side Roof Cover Assembly
This section details the installation of the side roof covers. Specific steps and part references would be detailed here, typically involving securing the covers to the main roof structure.
Installation of the Rear Drip Rail
This section provides dimensions related to wall mounting and drip rail installation.
- Dimensions shown: 2438mm, 660mm, 657.5mm, 90mm.
- Diagrams illustrate wall mounting points and drip rail placement.
Step 21: Wall Mounting Preparation
This step is for fixing the canopy to the wall and requires drilling holes into the wall. If wall fixation is not required, skip this step.
Step 22: Drip Rail Placement
The diagram shows the placement of the drip rail.
Step 23: Securing Posts and Beams to Wall
Insert part #13 into the wall through #C3 to secure rear posts to the wall. Insert part #13 into the wall through #K4 to secure #E1 & E2 to the wall. If wall fixation is not considered, this step can be skipped. This step requires the user to drill holes in the wall for fixation. Bracket #C3 is used to fix the post against the wall. Assemble only two pieces for each post according to the actual installation situation.
Base Assembly
Step 24: Base Component Connection
Insert part #AA into #BB and secure it with #15 and #16. Insert #BB into the base #CC.
Step 25: Support Tube Function
The support tube can strengthen the weight capacity of the metal roof. It is essentially needed in bad weather, especially snowstorms, to prevent the roof from collapsing under heavy snow. In daily life, it can be put away.
Support and Warranty
domi outdoor living thanks customers for their purchase and expresses belief in their products. A 12-month warranty and friendly, easy-to-reach after-sales service are provided.
For questions about the product and assembly, customers are encouraged to contact domi outdoor living.
Support Contact Information:
- After-sales contact email: service@domioutdoorliving.com
- Business cooperation contact email: marketing@domioutdoorliving.com