Disclaimer
This installation manual provides specific information about the system to be installed, including mounting drawings and a ballast diagram calculated according to the applicable Eurocode, depending on the determined environmental factors. The environmental factors on which the ballast values are based must always be checked by the installer beforehand. In case of deviating situations, a project-specific calculation must be performed. For this, please contact Van der Valk Solar Systems.
All current building, safety, and construction-related regulations must be observed. The building in question will be additionally loaded as a result of the PV system. PV systems installed/mounted on roofs are exposed to wind and snow loads. Therefore, you are always responsible for obtaining and using a design calculation to determine whether the building can withstand the (additional) load at all times. Where necessary, you must make modifications. Van der Valk Solar Systems accepts no liability whatsoever if you have not received or have not correctly used such a required design calculation.
Mounting systems for PV panels placed on flat roofs with a maximum inclination of up to 5 degrees must be mechanically fastened to the roof or ballasted to ensure that the mounting system does not move or tip over in storms or gusts of wind. The required amount of ballast shown in the tables in this manual must be respected for safe placement and use of the mounting system. If the inclination of the roof surface is 5 degrees or more, the mounting system for PV panels must always be mechanically fastened to the roof structure.
The calculation does not take into account large obstacles in the immediate vicinity of the roof, such as tall buildings, cliffs, and mountains. Limitations also apply to the position of the solar energy mounting system on a roof. The solar panels must be installed at a certain distance from the roof edge: the center zone of the roof.
The standard warranty is 10 years. This warranty can be extended under certain conditions. The provided warranty is subject to the warranty conditions stated in the general terms and conditions of Van der Valk Solar Systems B.V. Our general terms and conditions always apply to all our products and can be found on our website: www.valksolarsystems.nl.
Van der Valk Solar Systems B.V. accepts no liability for any direct and/or indirect consequences of actions (or failure to act or omission thereof) resulting from the information in or non-compliance with the instructions in this installation manual. The use of the Installation Manual is always subject to Dutch law.
Van der Valk Solar Systems reserves the right to amend this document without further notice.
The ValkQuattro mounting system is a product of:
Van der Valk Solar Systems BV
Chamber of Commerce number: 27355116
www.valksolarsystems.com
Required Ballast | Netherlands
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: Built-up
- Roof covering: Bitumen
Ballast Foundations
Diagram of ballast foundations
Wind Map Netherlands
Map showing wind zones in the Netherlands with corresponding wind speeds (e.g., 29.5 m/s, 27 m/s, 24.5 m/s).
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(29.5 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
I (29.5 m/s) | 282.0 | 282.0 | X | X | X | kg | X | X | X | X | X | kg | |||||||||||||
II (27 m/s) | 31.5 | 31.5 | X | X | X | tegels | X | X | X | X | X | tegels | |||||||||||||
II (27 m/s) | 188.0 | 188.0 | 244.0 | X | X | kg | 252.0 | 252.0 | X | X | X | kg | |||||||||||||
III (24.5 m/s) | 21.0 | 21.0 | 27.5 | X | X | tegels | 28.0 | 28.0 | X | X | X | tegels | |||||||||||||
III (24.5 m/s) | 102.0 | 102.0 | 148.0 | 203.0 | 248.0 | kg | 152.0 | 152.0 | 206.0 | 270.0 | X | kg | |||||||||||||
IV (23 m/s) | 11.5 | 11.5 | 16.5 | 23.0 | 28.0 | tegels | 17.0 | 17.0 | 23.0 | 30.0 | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | Belgium
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: III (Villages, suburban areas, permanent forest)
- Roof covering: Bitumen
Ballast Foundations
Diagram of ballast foundations
Wind Map Belgium
Map showing wind zones in Belgium with corresponding wind speeds (e.g., 26.0 m/s, 25.0 m/s, 24.0 m/s, 23.0 m/s).
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(23 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
23 m/s | 18.0 | 58.0 | 94.0 | 136.0 | 170.0 | kg | 49.0 | 101.0 | 143.0 | 192.0 | 231.0 | kg | |||||||||||||
24 m/s | 2.0 | 6.5 | 10.5 | 15.5 | 19.0 | tegels | 5.5 | 11.5 | 16.0 | 21.5 | 26.0 | tegels | |||||||||||||
24 m/s | 38.0 | 88.0 | 126.0 | 172.0 | 209.0 | kg | 78.0 | 135.0 | 180.0 | 234.0 | 277.0 | kg | |||||||||||||
25 m/s | 4.5 | 10.0 | 14.0 | 19.5 | 23.5 | tegels | 9.0 | 15.0 | 20.0 | 26.0 | 31.0 | tegels | |||||||||||||
25 m/s | 65.0 | 118.0 | 160.0 | 210.0 | 250.0 | kg | 109.0 | 171.0 | 220.0 | 278.0 | X | kg | |||||||||||||
26 m/s | 7.5 | 13.5 | 18.0 | 23.5 | 28.0 | tegels | 12.5 | 19.0 | 24.5 | 31.0 | X | tegels | |||||||||||||
26 m/s | 92.0 | 150.0 | 195.0 | 249.0 | X | kg | 141.0 | 208.0 | 261.0 | X | X | kg | |||||||||||||
27 m/s | 10.5 | 17.0 | 22.0 | 28.0 | X | tegels | 16.0 | 23.5 | 29.0 | X | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | Germany
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: IV (city)
- Altitude above sea level: 350 m
- Excluding North German lowlands
- Roof covering: Bitumen
Ballast Foundations
Diagram of ballast foundations
Wind Map Germany
Map showing wind zones in Germany with corresponding wind speeds (e.g., 22.5 m/s, 25 m/s, 27.5 m/s, 30 m/s).
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(22.5 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
1 (22.5 m/s) | 22.0 | 22.0 | 22.0 | 22.0 | 22.0 | kg | 54.0 | 54.0 | 54.0 | 54.0 | 54.0 | kg | |||||||||||||
1 (22.5 m/s) | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | tegels | 6.0 | 6.0 | 6.0 | 6.0 | 6.0 | tegels | |||||||||||||
2 (25 m/s) | 86.0 | 86.0 | 86.0 | 86.0 | 86.0 | kg | 133.0 | 133.0 | 133.0 | 133.0 | 133.0 | kg | |||||||||||||
2 (25 m/s) | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | tegels | 15.0 | 15.0 | 15.0 | 15.0 | 15.0 | tegels | |||||||||||||
3 (27.5 m/s) | 161.0 | 161.0 | 161.0 | 161.0 | 161.0 | kg | 220.0 | 220.0 | 220.0 | 220.0 | 220.0 | kg | |||||||||||||
3 (27.5 m/s) | 18.0 | 18.0 | 18.0 | 18.0 | 18.0 | tegels | 24.5 | 24.5 | 24.5 | 24.5 | 24.5 | tegels | |||||||||||||
4 (30 m/s) | 242.0 | 242.0 | 242.0 | 242.0 | 242.0 | kg | 316.0 | 316.0 | 316.0 | 316.0 | 316.0 | kg | |||||||||||||
4 (30 m/s) | 27.0 | 27.0 | 27.0 | 27.0 | 27.0 | tegels | X | X | X | X | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | United Kingdom
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Built-up
- Terrain category
- Altitude above sea level: 50 m
- Distance to coast: 5 km
- Distance to city limits: 5 km
- Roof covering: Bitumen
Ballast Foundations
Diagram of ballast foundations
Wind Map United Kingdom
Map showing wind zones in the UK with corresponding wind speeds and regions.
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(22 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
22 m/s | 106.0 | 183.0 | 213.0 | X | X | kg | 157.0 | 246.0 | 282.0 | X | X | kg | |||||||||||||
22 m/s | 12.0 | 20.5 | 24.0 | X | X | tegels | 17.5 | 27.5 | 31.5 | X | X | tegels | |||||||||||||
23 m/s | 141.0 | 225.0 | 258.0 | X | X | kg | 198.0 | X | X | X | X | kg | |||||||||||||
23 m/s | 16.0 | 25.0 | 29.0 | X | X | tegels | 22.0 | X | X | X | X | tegels | |||||||||||||
24 m/s | 178.0 | 269.0 | X | X | X | kg | 240.0 | X | X | X | X | kg | |||||||||||||
24 m/s | 20.0 | 30.0 | X | X | X | tegels | 27.0 | X | X | X | X | tegels | |||||||||||||
25 m/s | 216.0 | X | X | X | X | kg | 285.0 | X | X | X | X | kg | |||||||||||||
25 m/s | 24.0 | X | X | X | X | tegels | 32.0 | X | X | X | X | tegels | |||||||||||||
26 m/s | 256.0 | X | X | X | X | kg | X | X | X | X | X | kg | |||||||||||||
26 m/s | 28.5 | X | X | X | X | tegels | X | X | X | X | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | Ireland
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: Built-up
- Altitude above sea level: 50 m
- Distance to coast: 5 km
- Distance to city limits: 5 km
- Roof covering: Bitumen
Ballast Foundations
Diagram of ballast foundations
Wind Map Ireland
Map showing wind zones in Ireland with corresponding wind speeds (e.g., 28.0 m/s, 27.0 m/s, 26.0 m/s, 25.0 m/s).
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(25 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
25 m/s | 216.0 | X | X | X | X | kg | 285.0 | X | X | X | X | kg | |||||||||||||
25 m/s | 24.0 | X | X | X | X | tegels | 32.0 | X | X | X | X | tegels | |||||||||||||
26 m/s | 256.0 | X | X | X | X | kg | X | X | X | X | X | kg | |||||||||||||
26 m/s | 29.5 | X | X | X | X | tegels | X | X | X | X | X | tegels | |||||||||||||
27 m/s | X | X | X | X | X | kg | X | X | X | X | X | kg | |||||||||||||
27 m/s | X | X | X | X | X | tegels | X | X | X | X | X | tegels | |||||||||||||
28 m/s | X | X | X | X | X | kg | X | X | X | X | X | kg | |||||||||||||
28 m/s | X | X | X | X | X | tegels | X | X | X | X | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | Norway
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: III (Villages, suburban areas, permanent forest)
- Altitude above sea level: 175 m
- Roof covering: Bitumen
Ballast Foundations
Diagram of ballast foundations
Wind Map Norway
Map showing wind zones in Norway. For determining the wind region, see the following page.
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(22 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
22 m/s | 71.0 | 71.0 | 88.0 | 129.0 | 162.0 | kg | 116.0 | 116.0 | 135.0 | 183.0 | 222.0 | kg | |||||||||||||
22 m/s | 8.0 | 8.0 | 10.0 | 14.5 | 18.0 | tegels | 13.0 | 13.0 | 15.0 | 20.5 | 25.0 | tegels | |||||||||||||
25 m/s | 171.0 | 171.0 | 192.0 | 245.0 | 288.0 | kg | 233.0 | 233.0 | 257.0 | X | X | kg | |||||||||||||
25 m/s | 19.0 | 19.0 | 21.5 | 27.5 | 32.0 | tegels | 26.0 | 26.0 | 29.0 | X | X | tegels | |||||||||||||
27 m/s | 244.0 | 244.0 | 269.0 | X | X | kg | X | X | X | X | X | kg | |||||||||||||
27 m/s | 27.5 | 27.5 | 30.0 | X | X | tegels | X | X | X | X | X | tegels | |||||||||||||
29 m/s | X | X | X | X | X | kg | X | X | X | X | X | kg | |||||||||||||
29 m/s | X | X | X | X | X | tegels | X | X | X | X | X | tegels | |||||||||||||
31 m/s | X | X | X | X | X | kg | X | X | X | X | X | kg | |||||||||||||
31 m/s | X | X | X | X | X | tegels | X | X | X | X | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | Sweden
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: III (Villages, suburban areas, permanent forest)
- Altitude above sea level: 175 m
- Roof covering: Bitumen
Ballast Foundations
Diagram of ballast foundations
Wind Map Sweden
Map showing wind zones in Sweden with corresponding wind speeds.
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(22 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
22 m/s | 0.0 | 8.0 | 28.0 | 63.0 | 92.0 | kg | 1.0 | 32.0 | 66.0 | 107.0 | 140.0 | kg | |||||||||||||
22 m/s | 0.0 | 1.0 | 3.5 | 7.0 | 10.5 | tegels | 0.5 | 4.0 | 7.5 | 12.0 | 16.0 | tegels | |||||||||||||
23 m/s | 0.0 | 25.0 | 56.0 | 94.0 | 125.0 | kg | 18.0 | 61.0 | 98.0 | 143.0 | 179.0 | kg | |||||||||||||
23 m/s | 0.0 | 3.0 | 6.5 | 10.5 | 14.0 | tegels | 2.0 | 7.0 | 11.0 | 16.0 | 20.0 | tegels | |||||||||||||
24 m/s | 13.0 | 50.0 | 85.0 | 127.0 | 160.0 | kg | 39.0 | 91.0 | 132.0 | 181.0 | 220.0 | kg | |||||||||||||
24 m/s | 1.5 | 6.0 | 9.5 | 14.5 | 18.0 | tegels | 4.5 | 10.5 | 15.0 | 20.5 | 24.5 | tegels | |||||||||||||
25 m/s | 29.0 | 77.0 | 115.0 | 160.0 | 197.0 | kg | 66.0 | 123.0 | 167.0 | 220.0 | 263.0 | kg | |||||||||||||
25 m/s | 3.5 | 9.0 | 13.0 | 18.0 | 22.0 | tegels | 7.5 | 14.0 | 19.0 | 24.5 | 29.5 | tegels | |||||||||||||
26 m/s | 53.0 | 105.0 | 147.0 | 196.0 | 235.0 | kg | 95.0 | 156.0 | 204.0 | 261.0 | X | kg | |||||||||||||
26 m/s | 6.0 | 12.0 | 16.5 | 22.0 | 26.5 | tegels | 11.0 | 17.5 | 23.0 | 29.0 | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | Finland
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: III (Villages, suburban areas, permanent forest)
- Roof covering: Bitumen
Ballast Foundations
Diagram of ballast foundations
Wind Map Finland
Map showing wind zones in Finland.
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(21 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
21 m/s | 18.0 | 57.0 | 92.0 | 134.0 | 167.0 | kg | 58.0 | 100.0 | 141.0 | 189.0 | 228.0 | kg | |||||||||||||
21 m/s | 2.0 | 6.5 | 10.5 | 15.0 | 19.0 | tegels | 6.5 | 11.5 | 16.0 | 21.0 | 25.5 | tegels | |||||||||||||
22 m/s | 40.0 | 89.0 | 128.0 | 173.0 | 210.0 | kg | 80.0 | 137.0 | 182.0 | 235.0 | 278.0 | kg | |||||||||||||
22 m/s | 4.5 | 10.0 | 14.5 | 19.5 | 23.5 | tegels | 10.0 | 15.5 | 20.5 | 26.5 | 31.0 | tegels | |||||||||||||
26 m/s | 163.0 | 232.0 | 285.0 | X | X | kg | 224.0 | X | X | X | X | kg | |||||||||||||
26 m/s | 18.5 | 26.0 | 32.0 | X | X | tegels | 25.0 | X | X | X | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | Poland
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: III (Villages, suburban areas, permanent forest)
- Altitude above sea level: 250 m
- Roof covering: Bitumen
Ballast Foundations
Diagram of ballast foundations
Wind Map Poland
Map showing wind zones in Poland.
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(1) | kg | tegels | kg | tegels | |||||||||||||||||||||
1 | 76.0 | 107.0 | 133.0 | 164.0 | 190.0 | kg | 122.0 | 158.0 | 188.0 | 225.0 | 255.0 | kg | |||||||||||||
1 | 8.5 | 12.0 | 15.0 | 18.5 | 21.5 | tegels | 14.0 | 18.0 | 21.0 | 25.0 | 28.5 | tegels | |||||||||||||
2 | 213.0 | 257.0 | X | X | X | kg | 282.0 | X | X | X | X | kg | |||||||||||||
2 | 24.0 | 29.0 | X | X | X | tegels | 31.5 | X | X | X | X | tegels | |||||||||||||
3 | 76.0 | 107.0 | 133.0 | 164.0 | 190.0 | kg | 122.0 | 158.0 | 188.0 | 225.0 | 255.0 | kg | |||||||||||||
3 | 8.5 | 12.0 | 15.0 | 18.5 | 21.5 | tegels | 14.0 | 18.0 | 21.0 | 25.0 | 28.5 | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | Spain
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: III (Villages, suburban areas, permanent forest)
- Altitude above sea level: < 1000 m
- Roof covering: Concrete
Ballast Foundations
Diagram of ballast foundations
Wind Map Spain
Map showing wind zones in Spain with corresponding wind speeds (Wind zone A: 26, Wind zone B: 27, Wind zone C: 29).
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(26 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
26 m/s | 177.0 | 208.0 | 258.0 | 319.0 | 368.0 | kg | 240.0 | 275.0 | X | X | X | kg | |||||||||||||
26 m/s | 20.0 | 23.5 | 29.0 | X | X | tegels | 27.0 | 31.0 | X | X | X | tegels | |||||||||||||
27 m/s | 212.0 | 245.0 | X | X | X | kg | 281.0 | X | X | X | X | kg | |||||||||||||
27 m/s | 24.0 | 27.5 | X | X | X | tegels | 31.5 | X | X | X | X | tegels | |||||||||||||
29 m/s | 287.0 | X | X | X | X | kg | X | X | X | X | X | kg | |||||||||||||
29 m/s | 32.0 | X | X | X | X | tegels | X | X | X | X | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Required Ballast | Portugal
General
The ValkQuattro® mounting system must be ballasted using tiles, which must be placed on the indicated ballast foundations. You can easily calculate the required ballast in three steps:
- Determine the wind region on the wind map.
- Select the wind region and building height in the table.
- You can now read the number of tiles/kg.
Note 1: The number of tiles must be evenly distributed over the mass blocks on the indicated ballast foundations.
Note 2: A maximum of 32 tiles can be placed as extra ballast (288 kg).
Environmental Factors
- Position: Center zone of the roof
- Terrain category: III (Villages, suburban areas, permanent forest)
- Altitude above sea level: < 1000 m
- Roof covering: Concrete
Ballast Foundations
Diagram of ballast foundations
Wind Map Portugal
Map showing wind zones in Portugal (Wind zone A: 27, Wind zone B: 30).
Panel: maximum dimensions 1800x1100 mm (21 kg)
Building height | 0-5 meter | 5-7 meter | 7-9 meter | 9-12 meter | 12-15 meter | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(26 m/s) | kg | tegels | kg | tegels | |||||||||||||||||||||
26 m/s | 212.0 | 245.0 | X | X | X | kg | 240.0 | 275.0 | X | X | X | kg | |||||||||||||
26 m/s | 24.0 | 27.5 | X | X | X | tegels | 27.0 | 31.0 | X | X | X | tegels | |||||||||||||
27 m/s | X | X | X | X | X | kg | 281.0 | X | X | X | X | kg | |||||||||||||
27 m/s | X | X | X | X | X | tegels | 31.5 | X | X | X | X | tegels |
* X = The required ballast is higher than can fit under the system. The system must be mechanically fastened to the roof. Contact Van der Valk Solar Systems.
* If you use tiles with different dimensions and therefore a different weight, you must adjust the number of tiles to achieve the correct weight.
Recommended Installation Tools
Diagrams of tools: Cordless drill, Socket 13, Torx bit T-30, Measuring tape, Wrench 13.
Required Materials
List of required materials with part numbers and installation page references: Roof carrier profile 2000mm, Coupling set, Concrete mass block, Rubber tile carrier, SS bolt M8x65, SS washer M8 125A, Threaded rod M8x220, SS flange nut M8, A-frame connector, Alu. support, Hammerheadbolt M8x20, Alu. profile 2400mm, Alu. profile 1175mm, Alu. profile coupling, Alu. hinge 50mm, SS bolt M8x20, SS bolt M8x80, Ballast tile, End clamp, Panel clamp, Cable clamp.
General Dimensions
Diagram showing dimensions of the solar panel array, including panel length, panel thickness, and overall dimensions of the mounting structure.
Step 1: Placing Mass Blocks
ValkHint!
1) Place the mass blocks on the right locations before mounting the roof carriers.
Diagram showing the placement of mass blocks on rubber tile carriers.
Detail A showing the correct placement and torque (15 Nm) for securing components.
Diagram indicating the 2nd to last hole, 8th hole from end roof carrier, 16th hole from end roof carrier, and 3rd hole, all with a torque of 15 Nm.
Step 2: Mounting Connector Pieces
Diagram showing the mounting of connector pieces to the roof carriers.
Detail A showing the connection with a torque of 15 Nm.
Diagram illustrating the correct orientation of a bolt head using a groove for alignment, with a checkmark for correct and a cross for incorrect.
Step 3: Mounting Push Rods
Diagram showing the mounting of push rods to the roof carriers to connect two rows.
Detail A showing the connection of diagonal rods in opposite directions (crossed).
Detail B showing the connection with a torque of 15 Nm.
Diagram illustrating the correct orientation of a bolt head using a groove for alignment, with a checkmark for correct and a cross for incorrect.
Step 4: Creating Aluminium Profiles
Detail A.1 showing the assembly of aluminium profiles, with a 2400mm profile in the middle and 1175mm profiles on each end, secured with a torque of 15 Nm.
ValkHint!
Create the aluminium profile with the connector pieces/couplings first. Then mount the profile to the roof carrier.
Detail A.2 showing the connection of profiles with an M8x80 bolt and a torque of 15 Nm.
Step 5: Mounting Diagonal Push Rods
Diagram showing the front view of the structure with diagonal push rods mounted in opposite directions (crossed).
Detail A showing the mounting of push rods between the aluminium profile and the roof carrier with a torque of 15 Nm.
Step 6: Placing Ballast Tiles
Diagram showing the assembly with ballast tiles.
Diagrams illustrating the placement of 2, 4, 6, and 8 extra tiles.
For the required number of tiles, check the ballast tables in the front of this manual.
Step 7: Installing End Clamps
Diagrams showing Step 1 to Step 5 for installing end clamps.
Step 1: Take the end clamp out of its slot for easier assembly.
Step 2: Diagram showing the end clamp being placed.
Step 3: The end clamp can only be turned clockwise, so make sure the end clamp is placed the right way.
Step 4: Shows the panel height and the end clamp placement.
Step 5: Shows the end clamp being secured with a torque of 8 Nm.
Put the end clamp in the right slot to continue the assembly.
Step 8: Final Panel Clamping
Detail A showing the final panel clamping with a torque of 8 Nm.
Attention!! Do not forget to install the end clamps above the fourth panel! (same assembly as other end clamps, page 07.)
Step 9: Mounting Cable Clamps
Diagrams showing the mounting of cable clamps on the panel.