Quick Start Guide

32-Port 400G Data Center Spine Switch

AS9716-32D

Package Contents

1. 32-Port 400G Data Center Spine Switch AS9716-32D

2. Rack mounting kit—2 front-post brackets, 2 rear-post brackets, 20 screws, and 2 ear-locking screws

3. Power cord (included with AC PSUs only)

4. Console cable—RJ-45 to DE-9

5. Documentation—Quick Start Guide (this document) and Safety and Regulatory Information

Overview

1. Timing ports: 10 MHz, 1PPS, TOD

2. 32 x 400G QSFP-DD ports

3. Management ports: 1 x 1000BASE-T RJ-45, 2 x 10G SFP+, RJ-45 console, USB

4. Product label

5. 2 x AC PSUs

6. 6 x fan trays

7. 2 x grounding screws

System LEDs/Buttons

PS1/PS2: Green (OK), Amber (fault)

Diag: Green (OK), Amber (no OS or fault)

Fan: Green (OK), Amber (fault)

Loc: Flashing Amber (switch locator)

Reset Button

Port LEDs

QSFP-DD LEDs

400G: 1 LED Blue

200G Breakout: 1 LED White, 1-2 LEDs Green

100G Breakout: 1-4 LEDs Green

50G Breakout: 1 LED Cyan

SFP+ 10G Mgmt LEDs

Green (10G)

Amber (1G)

RJ-45 Mgmt LED

Green (link/activity)

FRU Replacement

PSU Replacement

1. Remove the power cord.

2. Press the release latch and remove the PSU.

3. Install replacement PSU with matching airflow direction.

Fan Tray Replacement

1. Pull the handle release latch.

2. Remove fan tray from the chassis.

3. Install replacement fan with matching airflow direction.

Airflow Reversal

1. F2B Airflow

Remove front-to-back (F2B) airflow fan trays (red handles) and PSUs (red release latches).

2. B2F Airflow

Install back-to-front (B2F) airflow fan trays (blue handles) and PSUs (blue release latches).

Installation

Warning: For a safe and reliable installation, use only the accessories and screws provided with the AS9716-32D. Use of other accessories and screws could result in damage to the unit. Any damages incurred by using unapproved accessories are not covered by the warranty.

Caution: The switch includes plug-in power supply (PSU) and fan tray modules that are installed into its chassis. Make sure all installed modules have a matching airflow direction (front-to-back or back-to-front).

Note: The switch has the Open Network Install Environment (ONIE) software installer preloaded on the switch, but no switch software image. Information about compatible switch software can be found at www.edge-core.com.

Note: The switch drawings in this document are for illustration only and may not match your particular switch model.

Caution: This device must be installed in a telecommunications room or a server room.

1 Mount the Switch

1. Attach the Brackets: Use the included screws to attach the front- and rear-post brackets.

2. Mount the Switch: Mount the switch in the rack and secure it with rack screws.

3. Lock the Rear-Post Brackets: Use the included screws to lock the position of the rear-post brackets.

2 Connect Power

AC Power

Install one or two AC PSUs and connect them to an AC power source.

Caution: Use a UL/IEC/EN 60950-1 certified power supply to connect to a DC converter.

Caution: All DC power connections should be performed by a qualified professional.

3 Make Network Connections

QSFP-DD Ports

Install transceivers and then connect fiber optic cabling to the transceiver ports. Alternatively, connect DAC or AOC cables directly to the QSFP-DD slots.

Connect Timing Ports

1PPS and 10 MHz Ports

Use coax cables to connect the 1-pulse-per-second (1PPS) and 10 MHz IN/OUT ports to other synchronized devices.

ToD Port

Use a shielded cable to connect the Time-of-Day (ToD) port to other devices that use ToD synchronization signals.

Make Management Connections

10/100/1000M RJ-45 Management Port

Connect Cat. 5e or better twisted-pair cable.

10G SFP+ Management Ports

Install transceivers and then connect fiber optic cabling to the transceiver ports.

RJ-45 Console Port

Connect the included console cable and then configure the serial connection: 115200 bps, 8 characters, no parity, one stop bit, 8 data bits, and no flow control.

Hardware Specifications

Switch Chassis

Size (WxDxH): 438.4 x 536 x 43.1 mm (17.26 x 21.1 x 1.7 in.)

Weight: 11.06 kg (24.38 lb), with 2 PSUs and 6 fans installed

Temperature: Operating: 0° C to 45° C (32°F to 113° F), Storage: -40° C to 70° C (-40°F to 158° F)

Humidity: Operating: 5% to 95% (non-condensing)

Power Consumption: 1300 Watts maximum

AC PSU

Input Power Rating: 100-120 VAC, 50-60 Hz, 12 A max. 200-240 VAC, 50-60 Hz, 7.5 A max. 190-310 VDC, 8-5 A

Regulatory Compliances

Emissions: EN 55032:2015+AC:2016, Class A, EN 61000-3-2:2014, Class A, EN 61000-3-3:2013, FCC Class A, VCCI Class A, CCC GB 9254-2008, Class A

Immunity: EN 55035:2017, EN 55024:2010+A1:2015, IEC 61000-4-2/3/4/5/6/8/11

Safety: UL (CSA 22.2 No 62368-1 & UL62368-1), CB (IEC/EN60950-1 & IEC/EN 62368-1), CCC GB4943.1-2011

Models: AS9716-32D, AS9716-32D 400G Data Center Spine Switch, 400G Data Center Spine Switch, Data Center Spine Switch, Spine Switch

PDF preview unavailable. Download the PDF instead.

AS9716-32D Quick Start Guide - AS9716-32D QSG-R02 EN-SC 0327 cairo 1.17.4 (https://cairographics.org) Mozilla Firefox

Related Documents

Preview Edgecore AS5916-54XKS/AS5916-54XL Quick Start Guide
Quick start guide for the Edgecore AS5916-54XKS and AS5916-54XL 54-Port 10G/100G Datacenter Ethernet Switch, covering unpacking, installation, grounding, power connection, verification, and initial boot.
Preview Edgecore EAP105 Wi-Fi 7 Access Point Quick Start Guide
This document provides a quick start guide for the Edgecore EAP105 Wi-Fi 7 Access Point, detailing package contents, overview of features, installation procedures for various mounting options, network cable connections, system LED indicators, web user interface setup, QR code onboarding, and essential safety and regulatory information.
Preview Edgecore MLTG-360 Terragraph Distribution Node User Manual
Comprehensive user manual for the Edgecore MLTG-360 Terragraph Distribution Node, detailing its features, configuration, operation modes, topology management, and system settings for high-speed wireless networking.
Preview Edgecore AS7326-56X 25G Ethernet Switch: Safety and Regulatory Information
Safety and regulatory compliance documentation for the Edgecore AS7326-56X 25G Ethernet Switch. Covers FCC, CE, UKCA, KC, TEC, VCCI, ANATEL certifications, laser and power safety guidelines, power cord specifications for various regions, and RoHS hazardous substance information.
Preview Edgecore EAP104/EAP104 Lite TIP OpenWiFi Wi-Fi 6 Access Point Datasheet
Datasheet for the Edgecore EAP104 and EAP104 Lite, enterprise-grade Wi-Fi 6 indoor wall-plate access points. Features include dual-band Wi-Fi 6, MU-MIMO, multiple LAN ports, BLE/Zigbee support (EAP104), and PoE Out (EAP104). Includes detailed specifications, performance data, and ordering information.
Preview Edgecore ECS2100 Series Gigabit Web-Smart Pro Switches Safety and Regulatory Information
This document provides safety and regulatory information for the Edgecore ECS2100 Series Gigabit Web-Smart Pro Switches, including FCC, CE, VCCI, and PSE compliance, as well as important warnings and cautionary messages for installation and operation.
Preview Edgecore CSR440 Cell Site Router Datasheet
Datasheet for the Edgecore CSR440 Cell Site Router (AS7535-28XB), an open disaggregated cell site gateway platform with 1/10/25Gbps, 50/100Gbps, and 100/400Gbps interfaces, featuring a temperature-hardened design and Intel Xeon processor.
Preview Edgecore EAP112/EAP112-L/EAP112-H Wi-Fi 6 IoT Gateway Quick Start Guide
A comprehensive quick start guide for the Edgecore EAP112, EAP112-L, and EAP112-H Wi-Fi 6 IoT Gateways, covering package contents, device overview, installation, connection, configuration, and safety information.