Installation and Operation Instructions

Model: 14RESA, 20RESA, and 20RESB

Subject: PowerSync™ Automatic Paralleling Module (APM) Kit GM85144-KP1-QS and Circuit Breaker Kits GM86368-KP1-QS and GM86369-KP1-QS

Original Issue Date: 8/12

Introduction

This document describes the installation and operation of the PowerSync™ Automatic Paralleling Module (APM) and optional circuit breakers for single-phase residential generator sets. The APM allows the use of two Model 14RESA or two 20RESA/20RESB generator sets in a single-phase paralleling system to supply power to one building or site. The APM provides a common connection point for paralleling generators and permits individual control of the generator connections, allowing for synchronization, redundancy, and generator management.

Figure 1: PowerSync™ Automatic Paralleling Module (APM) - A rectangular enclosure with "KOHLER. Power Systems" branding.

Generator Set Combinations for Paralleling

Automatic Paralleling Requirements

The APM and associated equipment must be installed by a Kohler® trained and authorized distributor or dealer.

Circuit Breaker Kits

Circuit breaker kits are available for installation inside the APM enclosure if the APM is not installed within sight of the generator sets, as required by local codes. Figure 2 shows the kit numbers for different generator models.

Model Circuit Breaker Kit APM Kit
14RESAGM86368-KP1-QSGM85144-KP1-QS
20RESA / 20RESBGM86369-KP1-QS

Figure 2: Kit Numbers

Other Accessories

If OnCue® Plus is used, a unique activation code is required for each generator set. Two codes are provided with the APM kit.

Definitions

Term Definition
Automatic paralleling module (APM)The enclosure containing the contactors and optional circuit breakers. (See Figure 1)
Single-phase paralleling systemThe system including the APM, two generator sets, current transformers (CTs), transfer switch, load control module (LCM) or load shed kit, optional PIM, and optional OnCue® Plus. (See Figure 7)
Generator managementDetermines the number of generator sets needed for the load and controls stopping one set.
Load managementShedding and adding loads using the LCM or load shed kit.
Generator 1The generator set connected to the left-side contactor in the APM.
Generator 2The generator set connected to the right-side contactor in the APM.
Primary generatorThe generator set whose RDC2 controller is controlling the RBUS network.
Secondary generatorThe generator set whose RDC2 controller is monitoring but not controlling the RBUS network.
First-order generatorThe generator set that is not stopped by generator management.
Second-order generatorThe generator set that is turned off by generator management when not needed.
Runtime order selectionThe generator with the fewest operating hours is selected first. May cause generators 1 and 2 to alternate. (See Section 5.3.2)
Manual order selectionThe generator set last taken offline is always the second-order generator set. Runtime hours are ignored. (See Section 5.3.2)
Auto-OffPressing AUTO and OFF simultaneously on one set's RDC2 controller removes it from the bus. The other generator starts if offline. (See Section 5.3.2)
Auto-RunPressing AUTO and RUN simultaneously on either set places generator management in runtime hour selection mode. (See Section 5.3.2)
Auto-DiscoveryA required procedure after installation to confirm system component connectivity and communication. (See Section 4.4)

Figure 3: Definitions

Related Literature

The paralleling system includes the APM, two generator sets, and an RXT transfer switch. An LCM, load shed kit, or combined interface/load management board on the RXT is required if one generator set cannot support the maximum total load. Optional PIM and OnCue® Plus systems may also be used. Refer to documentation provided with these components for installation instructions. Related literature is listed in Figure 4.

Document Description Part Number
SiteTech™ Software Operation ManualTP-6701
OnCue® Plus Operation ManualTP-6928
Installation Manual, 14/20RESA/RESALTP-6803
Operation Manual, 14/20RESA/RESALTP-6804
Installation Manual, 20RESBTP-6925
Operation Manual, 20RESBTP-6926
Operation/Installation Manual, Model RXT Transfer SwitchTP-6807
Installation Instructions, Load Control Module (LCM)TT-1574
Installation Instructions, Programmable Interface Module (PIM)TT-1584
Installation Instructions, Load Shed KitTT-1609

Figure 4: Related Literature

Safety Precautions

Observe the following safety precautions while installing the kit.

WARNING: Accidental starting. Can cause severe injury or death.

Disconnect the battery cables before working on the generator set. Remove the negative (-) lead first when disconnecting the battery. Reconnect the negative (-) lead last when reconnecting the battery.

Disabling the generator set: Accidental starting can cause severe injury or death. Before working on the generator set or equipment connected to it, disable the generator set by:

  1. Pressing the generator set off/reset button to shut down the generator set.
  2. Disconnecting power to the battery charger, if equipped.
  3. Removing the battery cables, negative (-) lead first.
  4. Reconnecting the negative (-) lead last.

Follow these precautions to prevent the generator set from starting via the remote start/stop switch.

DANGER: Hazardous voltage. Will cause severe injury or death.

Disconnect all power sources before opening the enclosure.

Grounding electrical equipment: Hazardous voltage can cause severe injury or death. Electrocution is possible whenever electricity is present. Ensure compliance with all applicable codes and standards. Electrically ground the generator set, transfer switch, and related equipment and electrical circuits. Turn off the main circuit breakers of all power sources before servicing. Never contact electrical leads or appliances when standing in water or on wet ground, as these conditions increase the risk of electrocution.

Short circuits: Hazardous voltage/current can cause severe injury or death. Short circuits can cause bodily injury and/or equipment damage. Do not contact electrical connections with tools or jewelry while making adjustments or repairs. Remove all jewelry before servicing.

Making line or auxiliary connections: Hazardous voltage can cause severe injury or death. To prevent electrical shock, de-energize the normal power source before making any line or auxiliary connections.

Electrical backfeed to the utility: Hazardous backfeed voltage can cause severe injury or death. Install a transfer switch in standby power installations to prevent connection of standby and other sources of power. Electrical backfeed into a utility electrical system can cause severe injury or death to utility personnel working on power lines.

1 Installation Procedure

Read the entire installation procedure and compare the kit parts with the parts list at the end of this publication before beginning installation. Perform the steps in the order shown.

For generator sets, transfer switch, LCM or load shed kit, and other accessories, refer to the installation instructions provided with each component.

Refer to the block diagram in Figure 7 and the APM dimension drawings in Section 8 as needed during installation.

1.1 Install the generator sets and current transformers (CTs).

  1. Install the generator sets according to the instructions and diagrams in the generator set Installation Manual. Do not connect wiring to the transfer switch at this time.
  2. Identify the generator sets as generator 1 and generator 2. Use the provided decals to label them. Be careful to keep track of generator 1 and generator 2 during installation and connection.
  3. Install one current transformer (CT) (GM86609) inside each generator set enclosure, below the customer-connection terminal block in the air intake area.
    1. Load lead L1 from the generator should enter the CT on the side with the dot. (See Figure 5)
    2. Load lead L2 must pass through the CT in the opposite direction from L1. (See Figure 5)

    Do not operate the paralleling system without the CTs in place. CTs measure power on each generator to allow load sharing.

  4. Connect the CT harness to connector P3 on the RDC2 controller inside the generator set. (See Figure 6)

Figure 5: Load Lead Routing through Current Transformer (CT) - Shows L1 and L2 passing through a CT. The dot on the CT indicates the direction for L1. Emergency leads must cross through the CT in opposite directions.

Figure 6: Current Transformer and Adaptor Harness Connections to RDC2 - Diagrams illustrating connections to the RDC2 controller, including adaptor harness to P2 and CT connection to P3.

1.2 Install the automatic paralleling module (APM).

  1. To remove the enclosure's front panel, support it while removing screws. Pull the bottom out and down until the top clears the enclosure. Remove the inner panel to access APM components.
  2. Refer to Section 8 for recommended cable entrance areas. Cover internal components. Punch or drill cable entry openings in the APM enclosure.
  3. Use a vacuum cleaner to remove debris from the enclosure. Do not use compressed air, as it can lodge debris and damage components.
  4. Mount the enclosure to a wall or other rigid vertical structure using the provided mounting holes. Use shims to plumb the enclosure. Mounting holes have gaskets to seal out moisture. Use washers with screws to prevent gasket damage.

Figure 8: Adaptor/Protection Harness GM86610 (provided) - Diagram of the harness.

1.3 Install the circuit breaker kit, if required.

Circuit breaker kits may be required if the APM is not installed within sight of the generator sets. Ensure compliance with NEC and local codes. If kits are not used, proceed to Section 1.4.

  1. Install circuit breaker mounting bracket GM85151 onto the back wall of the APM enclosure:
    1. Remove 4 screws X-67-133 and 8 washers X-25-36 from the back wall. Save screws; discard washers. (See Figure 9)
    2. Align bracket mounting holes with enclosure holes.
    3. Secure the bracket with the removed screws.
  2. Mount two circuit breakers onto the bracket.
    • For 14RESA (70 amp breakers): Use 4 X-67-132 screws and 4 X-400-145 spacers per breaker, placing spacers between mounting tabs and bracket. (See Figure 10) Connect breakers to APM contactors using 4 leads LN-0607-0606. (See Figure 9 and Section 8 wiring diagram)
    • For 20RESA or 20RESB (100 amp breakers): Use 2 X-67-132 screws per breaker. (See Figure 11) Connect breakers to APM contactors using 4 leads LN-0407-0606. (See Figure 9 and Section 8 wiring diagram)
  3. Remove knockouts for circuit breakers in the inner cover of the enclosure. (See Figure 9 and Figure 12)
    • For 70 amp breakers (14RESA): Remove the larger portion on the left side of each knockout.
    • For 100 amp breakers (20RESA/20RESB): Remove both portions of each knockout.
  4. Attach the GENERATOR 1 and GENERATOR 2 decals above the circuit breakers as shown in Figure 9. (Decals are provided in the literature bag with the APM).
  5. Attach the Service Disconnect decals to the outside of the inner cover near the circuit breaker openings, correctly labeling them for Generator 1 and Generator 2. (See Figure 13 and Figure 9)
  6. Close the circuit breakers between the APM and the generator sets.

The inner door for the APM enclosure will be installed later.

Figure 9: Circuit Breaker Kit Installation Inside the APM Enclosure - Shows internal components, labels, and installation steps.

Figure 10: 70 Amp Circuit Breaker Mounting, 14RESA - Diagram showing mounting bracket, spacers, screws, and 70A circuit breaker.

Figure 11: 100 Amp Circuit Breaker Mounting, 20RESA and 20RESB - Diagram showing mounting bracket, screws, and 100A circuit breaker.

Figure 12: Circuit Breaker Knockouts - Diagrams illustrating knockout removal for different breaker sizes.

Figure 13: Decals provided with APM - Shows Generator 1, Generator 2, and Service Disconnect decals.

1.4 Install the Model RXT transfer switch.

Only one transfer switch can be used.

  1. Install the ATS according to the installation instructions and dimension drawings in the transfer switch Installation Manual.
  2. Do not connect the emergency source wiring or the RBUS connections until instructed later in this procedure.

1.5 Install the LCM or load shed kit and optional PIM, if used.

One PIM and one LCM or load shed kit can be used. Multiple PIMs, LCMs, or load shed kits cannot be connected.

  1. Follow the installation instructions provided with the PIM and LCM or load shed kit(s).

Connect sufficient non-critical loads to the LCM or load shed kit so that one generator set can support the remaining load, if necessary.

Do not install the CT provided with the LCM or load shed kit. The generator controllers have built-in metering with the locally mounted CT installed in Section 1.1.

2 Connections

After physical installation, make the electrical connections described in this section.

  1. Press the OFF buttons on both generator set controllers.
  2. Turn off the AC power supplying the battery charger on both generator sets.
  3. Disconnect the generator set engine starting battery(ies), negative (-) lead first.

Route communication cables in separate conduit from power cables and voltage sensing leads.

Refer to the block diagram (Figure 7) and wiring diagrams (Section 8) when making connections. Be careful to connect Generator 1 and Generator 2 as instructed.

2.1 Voltage Sensing

  1. Connect voltage sensing leads from both adaptor harnesses (installed in step 5) to terminal block TB1 in the APM. (See Figure 9 and Figure 14)
    1. Connect voltage sensing lead V9 (RDC2 P2-8) from Generator 1 to TB1-1, labeled V9A, in the APM enclosure.
    2. Connect voltage sensing lead V9 (RDC2 P2-8) from Generator 2 to TB1-2, labeled V9B, in the APM enclosure.

Figure 14: Voltage Sensing Connections - Diagram showing connections from Generator 1 and Generator 2 to TB1-1 (V9A) and TB1-2 (V9B) respectively.

2.2 RBUS Communication Connections

RBUS communication wiring to the APM must connect directly to the generator sets (See Figure 7). Other accessories (PIM, LCM, load shed kit) connect after the APM.

Measure cable length from the furthest generator set to the last RBUS device and compare to Figure 15. Maximum cable length depends on the number of optional modules (APM, RXT, PIM, LCM, load shed kit).

For RBUS connections A and B to APM, RXT, LCM, and/or PIM, use 20 AWG shielded, twisted-pair cable (Belden #9402 or #8762 recommended). For outdoor/buried installations, use outdoor-rated Belden #1075A or equivalent.

For PWR and COM connections from TB1 to RXT, PIM, and/or LCM, use the second pair in a two-pair cable for short runs, or 12-14 AWG cable for longer runs (See Figure 15).

All communication cables must be routed through conduit, separate from power cables.

  1. Connect RBUS communication cables (A, B, PWR, and COM terminals). (See Figure 16)
    1. Connect RBUS from Generator 1 RDC2 controller to APM diode board terminal P21 (GEN 1).
    2. Connect RBUS from Generator 2 RDC2 controller to APM diode board terminal P20 (GEN 2).
    3. Connect P10 on the APM PIB circuit board to the RXT interface board. (See Figure 16)
    4. If PIM and/or LCM are used, connect communication cables from the RXT to the accessory modules per their instructions.
    5. Connect communication cable shields as shown in Figure 16, leaving one end disconnected.
Maximum length per run, meters (ft.)
Cable (TB1-PWR and COM) 1 Module 2 Modules 3 Modules 4 Modules
Belden #9402 or equivalent 20AWG for indoor installations46 (150)15 (50)5 (17)Do not use 20AWG for PWR and COM
Belden #1075A or equivalent 20AWG for outdoor installations or buried cables46 (150)15 (50)5 (17)Do not use 20AWG for PWR and COM
14 AWG *137 (450)137 (450)107 (350)107 (350)
12 AWG *137 (450)137 (450)137 (450)137 (450)

* Use 12 or 14 AWG cable for PWR and COM connections only. For RBUS connections A and B, use shielded, twisted pair communication cable specified above.

Figure 15: Maximum Communication Cable Lengths for Connection of RBUS Modules to the APM

Figure 16: Communication (RBUS) Connection Details - Diagrams showing connections between APM PIB, Diode Board, RXT, PIM, and LCM/load shed kit.

2.3 AC Voltage Output Connections

  1. Connect generator set AC output leads to the APM contactors or to the circuit breakers (if installed per Section 1.3). Connect generator 1 to contactor 1 and generator 2 to contactor 2 in the APM. (See Figure 17 or Figure 33 wiring diagram) If optional circuit breakers are used, connect to them instead of the APM contactors.
    1. Connect L1 from generator 1 to 1L1 at APM contactor 1. Connect L2 from generator 1 to 3L2 on APM contactor 1.
    2. Connect L1 from generator 2 to 1L1 at APM contactor 2. Connect L2 from generator 2 to 3L2 on APM contactor 2.

    L1 and L2 polarity is important. Reversing these leads is a common cause of auto-discovery failure.

  2. Connect the GEN LOAD A, GEN LOAD B, and NEUTRAL lugs in the APM to the emergency source lugs on the RXT transfer switch. (See Figure 33 wiring diagram)

Figure 17: Generator Output Connections to APM Contactors (optional circuit breakers not shown) - Diagram showing connections from Generator 1 and Generator 2 to Contactor 1 and Contactor 2 respectively, including L1 and L2 terminals.

2.4 Ethernet Connection for OnCue Plus

  1. If OnCue® Plus is used, connect both RDC2 controllers to the Internet via the Ethernet modem or router on site. Refer to the generator set Installation Manual for Ethernet cable location.

3 Prepare the equipment for operation.

3.1 Secure the APM enclosure and reconnect power to the generator sets.

  1. The APM's NEMA 3R enclosure has a locking tab. Turn it out while the enclosure is open so the door can be locked with a padlock.
  2. Install the inner door on the APM enclosure.
  3. Install the APM enclosure door and lock it with a customer-supplied padlock.
  4. Reconnect the generator set engine starting batteries, negative (-) lead last.
  5. Reconnect utility power to the generator sets.

3.2 Load firmware onto each generator set controller.

A personal computer (laptop) with Kohler SiteTech™ software is required for system installation and setup. SiteTech™ software is available to Kohler-authorized distributors and dealers.

Use a personal computer and Kohler SiteTech™ software to load RDC2 paralleling firmware version 105.4 or higher. Download from TechTools and save on the laptop. Refer to TP-6701, SiteTech Software Operation Manual, for instructions. Load the firmware onto both generator sets' RDC2 controllers.

Standard RDC2 controller firmware cannot be used on paralleled generator sets. Paralleling firmware is required.

Choose one generator set as the primary device. It will control other RBUS devices (RXT, PIM, LCM). The other set is secondary.

  1. Save the paralleling firmware file to your computer (e.g., RDC2_###_#.bin).
  2. Connect the laptop PC to the primary generator set's RDC2 controller via USB. Open SiteTech program.
  3. Load the paralleling firmware onto the generator set's RDC2 controller. (See TP-6701 for instructions)
  4. Repeat steps 2 and 3 for the secondary generator set.
  5. Check the firmware version on each controller to verify version 105.4 or higher is loaded. (See generator set operation manual for instructions)
  6. If OnCue Plus will be used, refer to the OnCue Plus Operation manual to set the password on each RDC2 controller.

3.3 Set the time, date, and exercise schedule on the primary generator set.

  1. The RDC2 display will prompt you to set the primary generator set. After firmware update, "RBUS Primary?" will appear.
    1. Use up/down arrows to select TRUE for the chosen primary generator set.
    2. Select RBUS Primary? FALSE on the other generator set.
  2. Follow the generator set installation manual to set time, date, and exercise on the primary generator set only. The primary set communicates these to the secondary set.
  3. Proceed to Section 4, Setup and Commissioning.

4 Setup and Commissioning

The following procedures are required for setup and commissioning of the paralleling system.

A personal computer (laptop) with Kohler SiteTech™ software version 3.5 or higher is required for system setup. SiteTech™ software is available to Kohler-authorized distributors and dealers.

4.1 Verify communication connections.

Check Network Information and Remote Devices menus on the RDC2 controller, or use Kohler SiteTech to check RBUS Devices group parameters.

  1. Verify the primary controller recognizes the secondary controller as a "Kohler Power Generation Device."
  2. Check that the serial number of the Kohler Power Generation Device seen in the primary controller matches the secondary controller's serial number. The secondary controller will not see the primary controller as an RBUS device.

The controller serial number can be found in the RDC2 controller's Genset Information menu.

4.2 Set up the LCM or load shed kit.

  1. Check that the primary controller sees the LCM or load shed kit as an RBUS device. Check Network Information and Remote Devices menus on the RDC2 controller, or use Kohler SiteTech to check RBUS Devices group parameters.
  2. Use SiteTech software connected to the primary controller to set the following parameters on the LCM:
    1. Set Genset Maximum Percent Capacity on the LCM or load shed kit higher than the APM Automatic Stop Minimum Percent setting. (See Figure 21 for APM settings)
    2. Set Generator Overload Percent on the LCM or load shed kit at least 20% higher than the APM Automatic Stop Minimum Percent Load setting.

See instruction sheets TT-1574 for LCM or TT-1609 for load shed kit, if necessary.

4.3 Set up the PIM, if equipped.

If the system does not include a programmable interface module (PIM), proceed to Section 4.4.

  1. If an optional PIM is connected, check that the primary controller sees it as an RBUS device. Check Network Information and Remote Devices menus on the RDC2 controller, or use Kohler SiteTech to check RBUS Devices group parameters.
  2. Use SiteTech software connected to the primary controller to set up PIM inputs and outputs. See TT-1584 (provided with PIM) for default settings. See TP-6701, SiteTech Software Operation manual, for instructions to change settings.
  3. Set PIM settings on the secondary controller to match the primary controller's PIM settings. Although the secondary controller only reads system status, matching PIM configuration ensures primary status can be switched between controllers.

4.4 Perform the auto-discovery procedure.

This procedure is REQUIRED.

  1. Close circuit breakers on both generator sets and in the APM (if equipped with optional kit).
  2. Press OFF on generator set 2. Press RUN to start generator set 1.
  3. After generator 1 starts, the controller cycles relays in the APM to recognize the output driving the contactor that connects the generator to the paralleling bus. Contactor status may display the wrong generator until auto-discovery is complete.
  4. Verify the connection LED on the APM lights up, indicating the generator set is connected. It will turn on, off, on again, and remain on if the correct output is detected. The controller remembers which contactor is associated with the generator after successful connection.
  5. Press OFF to stop generator set 1. Press RUN to start generator set 2. Repeat steps 3 and 4 for the other generator to verify relay cycling.

Troubleshooting Auto-Discovery

If the connection LED on the APM fails to illuminate or relays do not cycle, check the following:

  • Check wiring between the generator and APM, paying special attention to L1 and L2 connections.
  • Check connection of the sensing wire to V9 on the generator wiring harness. (See Figure 14)
  • Verify generator 1 is connected to contactor 1 and generator 2 to contactor 2 in the APM.

If relays continue to cycle after ATS indicates availability, check wiring to both generator sets, especially from V9A and V9B on APM transformers to V9 terminals on generator controllers. This connection is necessary for auto-discovery of output contacts.

If correct output is detected (on, off, on, remain on), but output continues to cycle, verify L1 and L2 connections are correct from generator to APM and consistent throughout the APM. Ensure APM wiring has not been modified, as bus sensing must be accurate.

In SiteTech™, observe Generator Voltage L2-L3 parameter. It should match generator voltage L1-L2 when the contactor is closed, and read 0 volts when open. If L2-L3 reads over 200 volts when both contactors are open, reverse L1 and L2 connections between that generator and the APM.

4.5 Verify synchronization and calibration.

  1. Start generator 1 by pressing RUN on the RDC2 controller.
  2. When the generator reaches rated voltage and frequency, verify the corresponding contactor in the APM closes.
  3. Verify the Generator Rotation Actual parameter (in SiteTech Generator Metering) reads between -300 and 300 (-30° and 30° phase angle across the closed contactor). If outside this range, Generator 1's RDC2 controller is not sensing bus direction accurately.
  4. Calibrate voltage metering on Generator 1.
  5. Calibrate bus metering (Generator Voltage L2-L3). Always calibrate bus voltage with the generator running and paralleling contactor closed.
    1. Bus metering should match calibrated generator metering. It is normal for bus voltage to vary more than generator voltage. Match average bus voltage reading to generator voltage.
    2. Increase Genset Calibration Factor Voltage L2-L3 to increase measured bus voltage.
    3. Decrease Genset Calibration Factor Voltage L2-L3 to decrease measured bus voltage.
  6. Stop generator 1 and repeat steps above for generator 2.
  7. After synchronization checking, stop both generators and place them in Auto. (Note: generators will start if utility is not present on the ATS).

4.6 Verify current metering.

  1. Ensure both generator sets are in AUTO mode.
  2. Open the utility source breaker to the ATS to simulate utility power loss. A loaded exercise can also be used.
  3. Verify generators start, synchronize, and close both contactors. This enables controllers to verify metering. Engines may appear slightly unstable during verification.
  4. Once complete, the ATS will transfer. Metering is now verified. Metering verification only needs to be performed once. Subsequent utility losses will result in more timely ATS transfers.
  5. Close the utility source circuit breaker or wait for loaded exercise to end. Verify ATS transfers to utility and both generator sets shut down.
  6. Verify both generator sets are in AUTO mode after commissioning is complete.

Troubleshooting Current Metering

If a generator shuts down with "No Current Shutdown" displayed, verify AC output wires cross through the CT in opposite directions (See Figure 5) and the CT is connected to the generator controller at P3. Correct and retry the current metering test from Section 4.6, step 1.

The message "ErraticSig Shutdown Current Metering" indicates unstable current readings. Otherwise, the controller has successfully determined CT connection direction when the ATS transfers.

4.7 Final adjustments.

At this point, the paralleling system can provide power to ATS-connected loads. Further adjustment of gains and windows for optimal performance can be done if desired.

See Section 5.3.2, Order Selection Method, for instructions on manually setting generator set order of operation or selecting the runtime hours method, which balances operation times based on hours on each set. Runtime hours method is the default.

5 Operation

5.1 Synchronization and Paralleling

The RDC2 controllers on Generator 1 and Generator 2 manage synchronizing and paralleling. Each controller adjusts to synchronize with the other and share real/reactive load once both are online. The process starts after the generator reaches rated voltage and frequency and consists of 3 steps:

  1. First-on determination
  2. Synchronizing
  3. Paralleling

These steps are described in the following sections.

5.1.1 First-On Determination

Generators exchange information over the RBUS network. When one runs at rated voltage and frequency, it alerts the other and closes the paralleling contactor in the APM, connecting it to the bus.

Either generator can be the first to close to the bus, depending on which starts and reaches rated voltage and frequency first.

5.1.2 Synchronizing

Once a generator connects to the paralleling bus (becomes the running generator), the other (incoming generator) sees bus voltage and synchronizes to it. If no bus voltage is detected, a BusDeadLive warning is issued.

Synchronizing adjusts the incoming generator's engine speed until dips and swells in its voltage waveform align with those of the running generator. When waveforms align, generators are synchronized. Figure 18 shows typical voltage waveforms when not synchronized.

Synchronizing also verifies bus voltage is not appreciably different from generator voltage. If significantly different, the controller adjusts generator voltage to match. This is why bus voltage must be calibrated (Section 4.5).

When synchronized, the incoming generator's paralleling contactor also closes.

Figure 18: Voltage Wave Forms, Not Synchronized - A graph showing generator voltage and bus voltage waveforms over time, illustrating misalignment.

5.1.3 Paralleling

After both contactors close, controllers ensure voltage regulators target the same voltage (nearly identical if calibrated) and throttles are in the same position.

Voltage regulator target voltage differences are measured as reactive power. Positive reactive power (generated VARs) means a generator's voltage regulator is higher; negative (absorbed VARs) means it's lower. Controllers adjust target voltages to match reactive power. The sum of reactive power from both generators equals the load's demand (typically low unless a large motor starts).

Throttle position variations are measured as real power. Opening a throttle increases power output. Controllers adjust engine speed (via governor) to match real power. The sum of real power from both generators equals the load provided, used for generator management and load control calculations.

5.2 Primary and Secondary Controllers

Generator set controllers are designated primary and secondary.

The RBUS primary controller initiates all RBUS communication.

  • The primary controller operates all RBUS modules (RXT, PIM, LCM).
  • The primary controller reads status from all RBUS modules.
  • If the primary controller loses power, RBUS communication for the paralleling system is lost.

The RBUS secondary controller responds to requests from the primary controller.

  • The secondary controller monitors RBUS activity but cannot control RBUS devices.
  • The secondary controller receives generator management information from the primary controller.
  • The secondary controller can only change the state of the secondary generator's contactor if the primary controller requests it to close.

Primary and secondary controller designations change if AUTO-OFF is pressed on the primary controller. (See Section 5.3.2)

5.3 Generator Management

The paralleling system performs generator management as follows:

  • If one generator fails to start, the other remains online and supplies loads it can support. The LCM or load shed kit sheds loads exceeding the generator set's capacity.
  • After both generators connect to the load, one will disconnect and shut down if not needed for 5 minutes. If an LCM or load shed kit is connected, the generator stops 5 minutes after all loads are added. Minimum stop time is 5 minutes without load management, 11 minutes with it.
  • Generator management logic alternates generator set operation to equalize run times.
  • Operating order changes if generator set run times differ by more than 24 hours.
  • Generator management logic is solved in the primary controller. Configuration is verified in the secondary controller upon connection; a message warns of differences.
  • The primary controller can overwrite configurations in attached devices. Changing a setting on the primary controller changes it on both.

5.3.1 Generator Management Operation

If a single generator is overloaded, the LCM (if equipped) sheds load until the other generator comes online.

Generator Management requires the following before stopping a generator:

  • An ATS start signal is present, a loaded exercise is active, or an unloaded full-speed exercise is active.
  • Both generators are online.
  • All load control priorities have been added (unless no Load Control Module exists on the RBUS network).
  • The system has been stable (no changes in the above conditions) for 5 minutes.

5.4 Generator Set Maintenance

To perform maintenance or service on generator sets, remove one generator set from the system at a time using this procedure:

  1. On the generator set to be serviced, press AUTO and OFF buttons on the RDC2 controller simultaneously for about 1 second.
  2. Wait for the generator set to shut down. Turn off non-critical appliances to reduce load, if necessary.
  3. Press OFF to shut down the generator set, if necessary.
  4. Disconnect utility power to the generator set.
  5. Disconnect the generator set battery, negative (-) lead first.
  6. Follow instructions in the generator set manual for service.
  7. Reconnect the generator set battery, negative (-) lead last.
  8. Reconnect utility power to the generator set.
  9. Press AUTO and RUN buttons on the RDC2 controller simultaneously to return the system to runtime hours mode, if desired.

5.5 Faults

Fault messages displayed on the RDC2 controller are shown in Figure 22 and Figure 23.

To clear warnings in Figure 22, press AUTO or OFF.

  • Press AUTO to clear the fault without shutting down the generator set.
  • Pressing OFF clears the fault AND stops the generator set.

LossOfComAPM Fault

A possible cause is the primary controller being powered down. If powered off without using the AUTO-OFF sequence (Section 5.3.2), the paralleling system will not function. To restore function, go to the secondary controller's Communications menu, RBUS network. Set RBUS primary to True on the secondary controller. When the former primary controller powers up again, set RBUS Primary? to False.

Fault Text Description When Active Warning Delay Display Cleared On
Voltage L1-L2 High WarningOver VoltageParalleled10Press AUTO or OFF *
Voltage L1-L2 Low WarningUnder VoltageParalleled10Press AUTO or OFF *
Frequency High WarningOver FrequencyParalleled10Press AUTO or OFF *
Frequency Low WarningUnder FrequencyParalleled10Press AUTO or OFF *
Current A High WarningOver CurrentParalleled10Press AUTO or OFF *
Reactive Power Low WarningLoss of FieldParalleled10Press AUTO or OFF *
Real Power High WarningOver PowerParalleled10Press AUTO or OFF *
Real Power Low WarningReverse PowerParalleled10Press AUTO or OFF *

* Pressing OFF will stop the generator set.

Figure 22: Warning Messages (protective relay disconnect)

Fault Text Description Possible Causes
CfgModelNumThe two generators intended for paralleling have different model numbers.Incorrect configuration of one generator. Different generator types. Paralleled sets must be the same kW model (e.g., two 14RESAs, two 20RESAs, or one 20RESA and one 20RESB).
LossOfComm2Primary controller lost communication with secondary controller. (Secondary detected, then communication lost.)RBUS disconnected, secondary controller battery disconnected, firmware update in secondary controller, or intermittent RBUS connections.
CfgSysVoltSystem voltage of the two generators intended for paralleling is not the same. Generators will not start.One generator incorrectly configured. Intermittent RBUS network wiring connections.
LossOfComAPMAutomatic Paralleling Module stopped communicating on RBUS. (APM detected on RBUS but no longer communicating.)APM unplugged. Primary controller powered down. Check battery connections. Intermittent RBUS network wiring connections.
SyncFailureGenerator attempting to synchronize for over 2 minutes without success.Generator is hunting (fuel system). Advanced speed control settings need adjustment. Load changing frequently.
MeteringOkGenerator verified metering is correct and direction is consistent with expected power direction.Status message indicates CT is correctly connected to the generator.
NoCurrentGenerator applied load (using other generator) and observed no current on power sensing inputs.CT not connected to the controller. Output leads from generator do not go through CT in correct direction (See Figure 5).
ErraticSigPower metering signal inconsistent with system configuration. Reversing power direction does not resolve.Bad wiring to CT. Too much tension on wires from CT to controller.
ChkngMeterGenerator paralleled to other generator, verifying metering connection and direction.Status message appears first time generators are paralleled.
MeterUnknownGenerator does not know if metering is connected or its orientation. Generators cannot share load accurately until known.System commissioning and startup not yet complete. (See Section 4)
ConNotDetermAPM connection auto-discovery not complete. Generator does not know which contactor is connected.Generators not yet started in RUN with other generator in OFF. (See Section 4.4, perform auto-discovery procedure)
ConCheckingPerforming APM connection auto-discovery.Generator started in RUN, other generator in OFF.
ConCheckFailFailure to Auto-Discover APM connections.Wires 9A and 9B crossed between generators. Wires 9A or 9B not connected.
ContactorOkSuccessful auto-discovery of APM connections.Auto-discovery activated by placing other generator in OFF and this generator in RUN.
Fault Text Description Possible Causes
LossOfFieldGenerator absorbed >25% reactive power (magnetic excitation current) for 20 seconds.Generator voltage on this generator not calibrated correctly. Generator voltage on other generator not calibrated correctly. Bus voltage on this generator not calibrated correctly. Bus voltage on the other generator not calibrated correctly.
BusDeadLiveBus measured dead when one generator should be supplying voltage (closed contactor).Bus metering V9A and V9B connections to V9 of paralleling protection harness connected incorrectly.
BusLiveDeadBus measured live when no generators are connected (both contactors open).Bus metering V9A and V9B connections to V9 of paralleling protection harness connected incorrectly.

Figure 23: Other Events

5.6 Status Indicators

The APM has an LED panel indicating system status. (See Figure 24 and Figure 25)

A Model RXT transfer switch is required for power connection status indication. (See Figure 25)

Figure 24: Status Indicators - Diagram showing LED indicator locations on the APM panel.

LED Indicator LED Color OFF LED State Flashing ON
Utility power available *GreenNot available--Utility power available
Utility power connected *GreenNot connected--Utility power connected
Power to home *GreenNo power to the home--Home has power
GEN1 statusRedNot runningGenset faultGenerator is running
GEN1 contactor closedRedGEN1 contactor openSynchingGEN1 contactor closed, providing power to the home
GEN2 statusRedNot runningGenset faultGenerator is running
GEN2 contactor closedRedGEN2 contactor openSynchingGEN2 contactor closed, providing power to the home
Generator set voltage availableRedGenerator set voltage not available--Generator set voltage available
Generator set(s) connected *RedGenerator power not connected to the home--Generator power connected to the home

* Model RXT transfer switch is required for operation of these LEDs.

Figure 25: LED Operation/Status Indication

6 OnCue Plus Generator Management System

The APM kit includes two OnCue® activation codes to connect both generator sets to the OnCue Plus server. Follow instructions in the OnCue Plus Operation manual to connect both sets to OnCue.

The OnCue Plus Status view shows two generator sets. (See Figure 27) The secondary generator set can monitor RBUS devices (like optional PIM) but cannot control them.

Primary and secondary generator sets can be changed using RBUS settings on RDC2 controllers or SiteTech™ software (changing Modbus Master parameter). SiteTech version 3.5 or higher is required. The AUTO-OFF procedure (Section 5.3.2) can also change primary/secondary designations.

Generator set states shown in Figure 26 are unique to a paralleling system and displayed in the power chain view (Figure 27).

Generator Set State Description
SynchronizingThe generator is actively trying to match frequency, voltage, and phase with the paralleling bus.
Generator Management OffGenerator stopped by management as it is not presently needed. It is available and will start if needed again.
UnloadingGenerator is actively trying to transfer load from itself to the other generator.
ProtectiveRelayTrippedContactorContactor forced open to protect a generator or customer's load.

Figure 26: Generator Set States Related to Paralleling

Figure 27: OnCue Plus Status View with Paralleled Generator Sets - Screenshot showing the OnCue Plus interface with two generators displayed.

7 Additional Troubleshooting

If the paralleling system does not operate as expected, check the items in the following tables. Section 4 also includes troubleshooting tips for initial setup problems.

Breaker will not close in RUN.

Check whether the other generator set is connected to the paralleling bus.

  • NO: Auto-discovery is not complete. Initiate auto-discovery. Generator must be running in RUN mode (not AUTO). Other generator must be stopped with controller in OFF mode (press OFF button).
  • YES: Other breaker is closed. Stop the other generator set.

Check whether the generator sees bus voltage (L2-L3 in SiteTech) above 25% of rated voltage.

  • NO: Bus sensing is not connected or is connected incorrectly. Check wiring between both generators and the Automatic Paralleling Module.
  • YES: (Proceed to next check)

Figure 28: Troubleshooting: Breaker Will Not Close - Flowchart for diagnosing breaker closure issues.

SiteTech indicates that both engines are under load, but the ATS has not transferred.

Transfer ATS and start each generator individually. Does the metering read positive power with load on the generator?

  • NO: The metering on this generator is backwards. Select a different model number for the generator, then re-select the correct model number. This will clear the CT direction flag and allow generators to re-determine CT direction.
  • YES: The metering on this generator is correct. Start the other generator and allow it to close to the bus, then stop this generator. Check that the other generator is reading positive power.
    • NO: The metering on the other generator is backwards. Select a different model number for the other generator, then re-select the correct model number. This will clear the CT direction flag and allow the generators to re-determine CT direction.
    • YES: Both generators are metering accurately; the load indicated in SiteTech must be due to electrical noise. Continue to commission the system.

Figure 29: Troubleshooting: ATS Has Not Transferred - Flowchart for diagnosing ATS transfer issues.

Auto-discovery does not complete.

Check whether the Automatic Paralleling Module indicates that the generator is closed to the bus.

  • NO: The wait for auto-discovery can be as long as 30 seconds. After 30 seconds expires, try to close the contactor manually (jump L1 to the C wire on the coil). Check if it closes. If it closes, the device may have auto-discovered to a different contactor. Set the engine model number select to a different model and then set it back. This will clear any auto-discover information stored in the controller.
  • YES: (Proceed to next check)

Is the generator circuit breaker tripped?

  • YES: Reset the generator circuit breaker.
  • NO: (Proceed to next check)

Is the APM circuit breaker tripped?

  • YES: Reset the circuit breaker in the APM.
  • NO: (Proceed to next check)

Check for bad connections between the generator and APM. Pay special attention to the Neutral connection.

  • NO: Correct the connections.
  • YES: (Proceed to next check)

Check that the APM is recognized on RBUS. Connection status of each module can be found on the front panel of the controller.

  • YES: Check the RBUS connections and follow RBUS troubleshooting procedures if the module is not visible in the list.
  • NO: The controller thinks that the bus is live (will not close to a live bus in auto-discovery mode). Check wiring between the generator and the APM. Pay special attention to the V9 lead connection, as this is the bus sensing.

Check if the generator controller is seeing bus voltage (look at L2-L3 voltage in SiteTech).

  • YES: (Proceed to next check)
  • NO: The other generator is not in OFF. Press the OFF button on the other generator. Then start this generator in run mode.

The controller has a fault or warning.

  • YES: Clear fault to retry. See Fault listing for additional information on which faults inhibit breaker closure.
  • NO: (Proceed to next check)

Controller is not running paralleling code.

  • YES: Load paralleling firmware RDC2_APM_###.#.bin onto both generator set controllers and cycle power when complete.

Figure 30: Troubleshooting: Auto-discovery - Flowchart for diagnosing auto-discovery failures.

8 Diagrams and Drawings

The paralleling system dimension drawing, wiring diagram, and schematic diagram are shown on the following pages. Also refer to Figure 7, Block Diagram, on page 5.

Diagram or Drawing Drawing Number Page
APM Dimension DrawingADV-8518Sheet 1: 30
Sheet 2: 31
Wiring DiagramGM85757Sheet 1: 32
Sheet 2: 33
Schematic DiagramGM85758Sheet 1: 34
Sheet 2: 35

PDF preview unavailable. Download the PDF instead.

kohler-powersync-automatic-paralleling-module-installation-manual-2155861044.1870577 Acrobat Distiller 10.0.1 (Windows)

Related Documents

Preview Kohler Load Control Module (LCM) and Load Shed Kit for Generators
Detailed specifications, features, and operation for Kohler's Load Control Module (LCM) and Load Shed Kit, designed for residential and light commercial generator systems to manage power loads efficiently and prevent generator overload.
Preview Kohler OnCue Plus Generator Management System: Features, Connectivity & Control
Explore the Kohler OnCue Plus system for remote monitoring and management of Kohler residential and light commercial generators. Learn about its features, applicable models, system requirements, and connectivity options for seamless generator control.
Preview Kohler Load Shed Kit for RXT/RDT Automatic Transfer Switches - Technical Specifications
Explore the Kohler Load Shed Kit, an essential accessory for RXT and RDT automatic transfer switches. This document details its features, applicable models, operational capabilities, specifications, and installation guidance for efficient power management and generator protection.
Preview Kohler OnCue Plus Generator Management System
Learn about the Kohler OnCue Plus system, a remote monitoring application for Kohler Residential and Light Commercial generators. Discover its features, applicable models, and system requirements for seamless generator management.
Preview Kohler Power Systems Sizing Chart for Residential Generator Sets
A guide to help estimate essential wattage requirements for appliances during emergency utility outages, aiding in the selection of the appropriate Kohler residential generator set. Includes appliance wattage calculations and a transfer switch selection chart.
Preview Kohler RXT Automatic Transfer Switch: Operation and Installation Manual
Comprehensive guide for the Kohler RXT Automatic Transfer Switch, covering operation, installation, safety precautions, and maintenance for reliable backup power systems. Learn about model features, setup, and service.
Preview Kohler RXT Automatic Transfer Switch: Operation and Installation Manual
Comprehensive guide for the Kohler RXT Automatic Transfer Switch, covering installation, operation, safety precautions, and maintenance for reliable standby power systems.
Preview Kohler APM603 Gaseous-Fueled Generator Sets Operation Manual
Comprehensive operation manual for Kohler Gaseous-Fueled Generator Sets equipped with the APM603 controller, detailing safety, operation, setup, monitoring, paralleling, and troubleshooting procedures.