Quick Installation Guide
X3-FORTH 40kW-150kW

Mounting the inverter on the wall

- Use the bracket as a template for marking the position of holes with a level and marker.

- Drill the four holes with a 13 drill. - Depth: at least 65 mm.

- Hammer the M10x80 expansion bolt
into four holes. - Screw in the nut firmly with socket wrench.

Expansion bolt Bracket Nut
*Note: Screws used for installation on the wall are not in the accessory box. Please prepare them in advance.

- Lift up the inverter. - Two methods are available
by four installers or lifting ring

-Hang it onto the bracket.

- Fix it on the wall bracket with M8 bolts. (Torque: 7.0-8.5 N·m)

Inverter x1

Packing list

Bracketx1

M10xL40 Bolt combination x4

Communication connector x1

Mounting the inverter on the stand

- Use a bracket as a template for marking the position of the holes with a level and marker.

- Drill the four holes with a 12 drill.

- Screw in the M10x40 bolt into holes. - Tighten it firmly with corresponding
socket wrench.

Bracket M10x40 bolt

M8Boltx2

Positive DC connectorx24 Negative DC connectors x24

Positive DC pin contact x24 Negative DC pin contact x24

Allen key x1

Documents

Wi-Fi dongle (Optional)

*For the optional accessories, please be subject to the actual delivery. *Note: The allen key in the accessory box is used to remove the screws on the front cover of the inverter. Keep it in a safe place.

I

Grounding connection

- Select 35-70 mm² ground conductor and OT copper terminal

- Pull the heat-shrink tubing over grounding cable - Insert the stripped section into OT terminal. - And crimp with crimping tool

- Strip the insulation end of cable

with proper length

A=B+(2~3mm)

C=A+2 cm

Heat-shrink tubing B

- Pull the heat-shrink tubing onto crimped section of OT terminal - The tubing must be at below stripped cable section - Use hot-air blower to shrink it so that they are
in firm contact with OT terminal

- Connect the grounding cable to grounding point on the inverter
- Tighten it with torque 7.0-8.5 N·m

I

PV connection

- Disassemble the DC connector

- Strip the PV cable insulation 6 mm

Positive DC connector
Negative DC connector Positive DC PV pin contact

Positive pin contact Positive terminal Fastening head Negative pin contact Negative terminal Fastening head

Cable size: 4-6mm2 Positive terminal

Negative DC PV pin contact

Clamp pin

(Torque: 3-4 N·m)

- Connect the PV cable to the corresponding PV port

PV2

PV4

PV6

PV8

M

M

M

M

P

P

P

P

P

P

P

P

T

T

T

T

1

2

3

4

PV1

PV3

PV5

PV7

ON OFF

PV10

PV12

PV14

PV16

M

M

M

M

P

P

P

P

P

P

P

P

T

T

T

T

DC SWITCH 1

5

6

7

8

PV9

PV11

PV13

PV15

ON OFF

PV18

PV20

PV22

PV24

M

P

P

T

DC SWITCH 2

9

M

M

M

P

P

P

P

P

P

T

T

T

10

11

12

PV17

PV19

PV21

PV23

ON USB
OFF
DC SWITCH 3
COM

++

PV 2

PV 4

-

-

Negative terminal Tighten the fastening head

- Lift up the inverter. - Two methods are available
by four installers or lifting right

- Hang it onto the bracket.

- Fix it on the stand with M8 bolts. (Torque: 7.0-8.5 N·m)

Grid connection

- Select the appropriate OT terminal and 70~240 mm² copper cable

- Use wire stripper to strip the insulation layer of the AC cable end.

- The stripped insulation layer shall be 2-3mm longer than "D" part of OT terminal as shown below.

A

40 kW-70 kW / 80 kW-125 kW inverter B

L1 L2 L3 N
PE D+(2~3) mm

L1 / L2 / L3 / N

A260 mm B150 mm

a45 mm D 12.5b15 mm

136 kW-150 kW inverter

A

L1
L2
L3
D+(2~3) mm

L1 / L2 / L3 / N

PE

B

A260 mm a45 mm D

B150 mm 12.5b15 mm

*Note: The "Delta Grid" in "Setting"-"Grid Protection"- "FunctionChoose" is set as "Enable" in default. In this condition, the Neutral wire is not required to be connected. Please set "Delta Grid" to "Disable" before connecting the Neutral wire for 40 kW-70 kW / 80 kW-125 kW inverter.

- Pull the heat-shrink tubing over AC cable. - Insert the stripped section into OT terminal and crimp with crimping tool. - Pull the heat-shrink tubing over the crimped section of OT terminal. - Use hot air blower to shrink it so that they are in firm contact with OT terminal.

40 kW-70 kW / 80 kW-125 kW inverter

136 kW-150 kW inverter

-Un-install the screws on the cover to open the cover of the wiring box. -Use utility knife to cut out the pagoda type protection ring in accordance with the whole cable size, -Put the AC cable through the pagoda protection ring, and connect it to the AC terminals L1, L2, L3 and N in turn, and tighten it with torque wrench (with the torque of 25-30 N·m). -Re-install the cover of wiring box with the torque of 5~7 N·m.

40 kW-70 kW / 80 kW-125 kW inverter

136 kW / 150 kW inverter

L1 L2 L3 N PE

L1 L2 L3 N PE

Separate PE cable

Multi-corecable

L1 L2 L3 PE

L1 L2 L3 PE

Separate PE cable

Multi-corecable

Communication connection

- Select 0.5~0.75 mm² twisted-pair and strip the 20-pin communication insulation

- Insert the insulated cord end terminal into the cable end

20-25 mm

(ENY0512 nylon terminal for 0.5mm²/22 AWG conductor;

ENY7512 nylon terminal for 0.75 mm²/20 AWG conductor)

- Clamp with terminals press clamp

12-14 mm

- Disassemble the communication terminal - Set the nut, claw, seal body, seal ring and body on the cable

Body,

Seal ring, Seal body,

Claw,

nut

V

PV connection

- Insert the tube type terminal into the housing according to the label
- Push the terminal-inserted housing into the body; you will hear "Click" , if it is correctly inserted
- Please check the following table for more details about corresponding Pin definition
Click!

Quick

Housing

Monitoring connection
Monitoring Cloud is an application that can communicate with the inverter via Wi-Fi/LAN/4G. It can realize alarm query, parameter configuration, daily maintenance and other functions. This is a convenient maintenance platform.
Plug Dongle into "USB" port at the bottom of the inverter. After the DC side or AC side is powered on, the APP and inverter can be connected. Please refer to the corresponding manual for details.

PV2

PV4

PV6

PV8

M

M

M

M

P

P

P

P

P

P

P

P

T

T

T

T

1

2

3

4

PV1

PV3

PV5

PV7

ON OFF

PV10

PV12

PV14

PV16

M

M

M

M

P

P

P

P

P

P

P

P

T

T

T

T

DC SWITCH 1

5

6

7

8

PV9

PV11

PV13

PV15

ON OFF

PV18

PV20

PV22

PV24

M

P

P

T

DC SWITCH 2

9

M

M

M

P

P

P

P

P

P

T

T

T

10

11

12

PV17

PV19

PV21

PV23

ON USB
OFF
DC SWITCH 3
COM

DC SWITCH 3

Ø Wi-Fi connection
WiFi dongle connects to a local network within 50 m of the installation to enable access to the Monitoring Cloud platform.

Monitoring Cloud
Router
Ø LAN connection If Wi-Fi isn't suitable, the LAN dongle enables users to connect to the network via an ethernet cable. Ethernet allows for a much more stable connection with less interference.

Communication connection

Port

Pin

1

2

3

RS-485-1

4

5

6

7 RS-485-2
8

9

10

11

12

13
DRM 14

15

16

21 DI
22

29 DO
30

- Push the seal body into seal ring, then push the claw Clockwise tighten the nut with torque 8+/-2 N·m - Keep the buttons on both sides pressed and then connect it to the communication port on the inverter. You will hear "Click" if it is correctly connected

Definition RS485A IN+ RS485B INRS485 IN-GND RS485A OUT+ RS485B OUTRS485OUT-GND RS485A METER RS485B METER
V+5V COM_GND DRM1/5 DRM2/6 DRM3/7 DRM4/8 RG/0 CL/0 Digital IN+ Digital INDigital OUT+ Digital OUT-

Remark Inverter RS485 networking or connectthedatacollector
ConnecttheRS485 meter or other devices
Reserved for DRM
Inputdigitalsignal Outputdigitalsignal

Monitoring connection
Ø 4G connection 4G dongle allows you to use a 4G connection to monitor your system without the option of connecting to a local network. (This product is not available in the UK)

Ø Basic setting Basic settings can set the time, date and language.

Ø Advanced setting
Advanced settings can set "Satety", "System Switch", "PVConnection", "Active Power Control", "Export Control", "Reactive Power Control", "Grid Voltage Parameters" "Grid Frequency Parameters", "Grid Through Parameters", "Check Parameters", "Reset", "Communication Parameters" and "New Password".