Stäubli MC4-Evo 2 Connector MA298 Assembly Instructions

Valid for: PV-KBT4-EVO 2A/... PV-KST4-EVO 2A/...

Safety Instructions

Importance of the Assembly Instructions

Failure to follow safety and assembly instructions can lead to life-threatening injuries from electric shock, electric arcs, fire, or system failure. Always adhere strictly to all instructions and use the product only as specified.

Intended Use

The connector electrically connects components within the DC circuits of a PV array. It may also be used in other low-voltage DC systems. For alternative uses, consult Stäubli for specific requirements.

Requirements for Personnel

Assembly, installation, and commissioning must be performed by a qualified electrician or an electrically instructed person.

Prerequisites for Installation and Assembly

  • Never use a damaged product.
  • Only use tools and materials approved by Stäubli.
  • Only assemble approved PV cables to the connector.

Safe Assembly and Mounting

Live parts can remain energized even after isolation. Install the product only when the PV module is de-energized.

Mating and Disconnecting

  • Always de-energize the PV system before mating or disconnecting connectors.
  • Never disconnect connectors under load.
  • Never connect Stäubli connectors with connectors from other manufacturers.
  • Never mate contaminated connectors.
  • A tool is required to open the locking-type connector.

Do NOT Modify or Repair Component

  • Mount connectors only once.
  • Do not modify connectors after assembly.
  • Replace defective connectors.

Notes on Installation

General Notes

  • Unmated connectors must be protected from environmental impact (moisture, dirt, dust) using sealing caps.
  • Do not mate contaminated connectors.
  • Connectors must not come into contact with chemicals.

Cable Routing and Wire Management

Cable management must allow a minimum of 20 mm of cable exiting the seal without bending or stress. Ensure the connector is not positioned at the lowest point of cabling where water can collect. Refer to cable manufacturer specifications for minimum bending radius.

[Diagram: Cable exit length illustration showing minimum 20mm clearance.]

Contaminated/Damaged Connectors

  • Prevent environmental contamination (soil, water, insects, dust).
  • Prevent surface contamination (stickers, paint, heat shrink tubing).
  • Do not allow the connector to be directly on the roofing surface.
  • Avoid installation in standing water.
  • Do not mount cable ties directly on the connector body.

Mechanical Stress

Ensure connectors are not subjected to permanent mechanical tensile load or vibration. Connectors must not be strained by cables and should be constrained from dynamic movement, isolated from mechanical load (e.g., from moving components of a PV-Tracker system).

Thermal Stress

Ensure the connector is not exposed to excessive thermal stress. Install for sufficient heat dissipation. Installation is not permitted in areas that restrict airflow (e.g., large bundles, split cable harnesses, other housings). Direct burial is not permitted.

Tools

The following tools are recommended for assembly:

Illustration Tool Name Description Order No. Notes
[Illustration of stripping pliers] Stripping Pliers PV-AZM... For conductor cross sections 1.5-2.5/4/6 mm² (14/12/10 AWG) and 4/6/10 mm² (12/10/8 AWG) PV-AZM-156 / PV-AZM-410 Operating instructions MA267 available at www.staubli.com/re-downloads.html
[Illustration of crimping pliers] Crimping Pliers PV-CZM... with Locator For crimping range 2.5/4/6 mm² (14/12/10 AWG) and 4/10/6 mm² (12/8/10 AWG) PV-CZM-61100 / PV-CZM-60100 with PV-LOC-MC4-EVO 2 (32.6084 / 32.6083) Operating instructions MA704 available at www.staubli.com/re-downloads.html
[Illustration of assembly/unlocking tool] Assembly and Unlocking Tool PV-MS-PLS or PV-MS 32.6058 (PV-MS-PLS) / 32.6024 (PV-MS set) Operating instructions MA270 available at www.staubli.com/re-downloads.html
[Illustration of torque tool set] Torque Tool Set PV-WZ-TORQUE-SET / Torque wrench 17 mm 32.0065 For precise tightening.
[Illustration of test plug] Test Plug PV-EVO-PST 32.6073 For assembly checks.
[Illustration of cable cutter] Cable Cutter PV-WZ-KS 32.6080 For cutting cables.

Storage

Store components at a constant temperature between -30 °C and +60 °C with relative humidity below 70%. Avoid exposure to moisture and contact with aggressive chemicals.

Cable Preparation

Use cables with class 5 and 6 strands, exclusively tinned copper cables. Do not use oxidized or bare conductors. Stäubli prohibits the use of PVC cables and non-tinned H07RN-F cables for safety reasons.

[Diagram: Cable preparation showing correct stripping length.]

Guideline for Connector Configuration

Note: If the chosen cable diameter falls between two limits, use the smaller sealing. Seals are color-coded: Maroon (DI), Yellow (DX), Grey (DII).

Connector Configuration Tables

Table 1: TÜV Rheinland Certification

Conductor Cross Section (mm²) AWG Outer Cable Diameter A (mm) Reference Dimension b (mm) Usable Seals PV Cable Type (TÜV / TÜV+UL)
1.5 - 2.5 14 ~ 4.0 4.7 - 6.4 DI (Maroon) PV-K...T4-EVO 2A/2.5I / PV-K...T4-EVO 2A/2.5X
4 - 6 12/10 ~ 5.8 5.9 - 7.3 DX (Yellow) PV-K...T4-EVO 2A/6I / PV-K...T4-EVO 2A/6X
10 8 ~ 6.5 6.4 - 8.4 DII (Grey) PV-K...T4-EVO 2A/10I / PV-K...T4-EVO 2A/10X

Table 2: UL Certification

Cable Type Conductor Cross Section (mm²) AWG (Stranding) Outer Cable Diameter A (mm) Reference Dimension b (mm) Usable Seals PV Cable Type (UL)
TYLZ (USE-2) up to DC 600 V 2.5 14 (19-49) 4.93 - 6.5 5.58 - 6.5 DI (Maroon) PV-K...T4-EVO 2A/2.5II
ZKLA (PV-wire) up to DC 1000 V 4 12 (19-65) 5.76 - 7.45 6.5 - 8.5 DX (Yellow) PV-K...T4-EVO 2A/6II
ZKLA (PV-wire) up to DC 2000 V 6 10 (19-105) 6.5 - 8.5 6.5 - 8.5 DII (Grey) PV-K...T4-EVO 2A/10II
10 8 (19-168)

Attention: Do not assemble with single jacket cross-linked polyethylene (XLPE) cable, as it does not meet UL 6703 strain relief requirements.

Note for Canada: Installation must comply with CSA C22.1-2021. Use conductors rated for 75°C or higher. Suitable only for Class B and C stranded copper conductors (NFPA NEC 70).

Crimping Procedure

Stripping the Cable (ill. 8): Strip cable insulation 6.0 mm to 7.5 mm. Do not cut individual strands.

Crimping (ill. 9, 10, 11):

  1. Open clamp (K) and insert contact into the appropriate section. Turn crimping flaps upwards. Release clamp (K) to lock the contact.
  2. Ensure the contact is correctly seated and held by the clamp.
  3. Verify crimping flaps are aligned. Gently press pliers until flaps are properly located in the crimping die.
  4. Insert stripped lead end until strands touch the locator.
  5. Completely close the crimping pliers, then open them and remove the crimped cable assembly.

[Diagrams illustrating stripping and crimping steps.]

Assembly Check

Visual Crimp Check (ill. 12): Confirm all strands are captured, the crimp sleeve is not deformed, and the crimp is symmetrical with a visible 'brush' of conductor strands.

Contact Engagement (ill. 13): Insert crimped contact into the insulator until it clicks. Gently pull the cable to verify correct engagement.

Test Pin Check (ill. 14): Insert the test pin. If assembly is correct, the white mark on the test pin should remain visible.

Cable Gland Tightening (ill. 15): Pre-tighten the cable gland using PV-MS-PLS, then tighten with the torque set (PV-WZ-TORQUE-SET), supporting the insulator with PV-MS-PLS.

Conductor Cross Section (mm²) AWG Tightening Torque (Nm)
2.5 14 4.5
4.0 12 4.0
6.0 10 3.5
10.0 8 4.0

Notes: Recommended ambient temperature for assembly is -15 °C to 35 °C. Torque values should be adapted to specific PV cables. Stäubli recommends using a calibrated torque wrench, as required by NFPA NEC 2017.

Mating and Disconnecting

Mating (ill. 16): Connect the connectors until a 'click' is heard. Verify engagement by lightly pulling (max 20 N). Attention: Do not fully engage connectors, as this can permanently damage the locking clips. Always verify correct assembly.

Disconnecting (ill. 17): Use PV-MS-PLS/2 or PV-MS to disconnect.

Note: Protect unmated connectors from contamination with Stäubli sealing caps. Warning: Do not bottom out the capnut.

Technical Data

Parameter Specification
Type Designation PV-KST4-EVO 2A/xy; PV-KBT4-EVO 2A/xy
Connector System Ø 4 mm
Rated Voltage (IEC) CC 1500 V
Rated Voltage (UL) CC 1500 V
Rated Current (IEC) 39 A (2.5 mm²), 45 A (4.0 mm²), 53 A (6.0 mm²), 69 A (10.0 mm²)
Rated Current (UL) 30 A (14 AWG), 39 A (12 AWG), 50 A (10 AWG), 70 A (8 AWG)
Rated Impulse Voltage 16 kV
Ambient Temperature Range -40 °C to +85 °C
Transportation/Storage Temperature Range -30 °C to +60 °C
Transportation/Storage Relative Humidity < 70%
Upper Limiting Temperature 115 °C (IEC)
Degree of Protection, Mated IP65/IP68 (1 m, 168 h)
Degree of Protection, Unmated IP2X
Overvoltage Category III
Contact Resistance of Plug Connectors < 0.2 mΩ
Locking System Locking Type
Safety Class (IEC) II
Contact System MULTILAM
Type of Termination Crimping
Number of Mating Cycles 100
Contact Material Copper, tin plated
Insulation Material PA
Flame Class UL94-V0
Ammonia Resistance Certified (TÜV Rheinland acc. to 2 PfG 1911/04.2016)
TÜV Rheinland Certification Acc. to IEC 62852:2014+Amd.1:2020
UL/CSA Certification Certified acc. to UL6703 and CSA C22.2 No. 182.5 (cULus Listed and UL Recognized)
JET Certification 1625-C4304-336
Max. Altitude for Operation 5000 m
Temperature Level (IEC TS 63126) Level 2

Notes on Certifications:

  • Connectors evaluated with ZKLA (PV-wire) or TYLZ (USE-2) cable types. Refer to Table 2 for cross-sections.
  • Connector compliance with UL6703 requires assembly as specified in these instructions.
  • PV connectors are certified cULus Listed, even if the UL Recognized Component Mark (UR) is molded on the housing.

Notes

Manufacturer: Stäubli Electrical Connectors AG, Stockbrunnenrain 8, 4123 Allschwil/Switzerland. Tel: +41 61 306 55 55, Fax: +41 61 306 55 56, Email: ec.ch@staubli.com, Website: www.staubli.com/electrical.

Models: MA298, MC4 Evo 2 Connector, MC4 Evo 2 Connector, 2 Connector, Connector

File Info : application/pdf, 12 Pages, 1.77MB

PDF preview unavailable. Download the PDF instead.

v1

References

Adobe PDF Library 17.0

Related Documents

Preview Stäubli MC4-Evo 2 Connector Assembly Instructions (MA298)
Comprehensive assembly instructions for the Stäubli MC4-Evo 2 connector (MA298). This guide covers essential safety precautions, required tools, cable preparation, crimping procedures, mating and disconnecting steps, and detailed technical specifications for photovoltaic applications.
Preview Stäubli MC4-Evo 2 Connector MA273 Assembly and Safety Instructions
Comprehensive guide for assembling and safely using Stäubli MC4-Evo 2 connectors (MA273), including technical data, tools, and best practices for photovoltaic systems.
Preview Stäubli MC4-Evo 2 Panel Receptacle MA299 Assembly Instructions
Comprehensive assembly instructions for the Stäubli MC4-Evo 2 panel receptacle (MA299), covering safety, tools, preparation, installation, mating, and technical data for photovoltaic systems.
Preview Stäubli MC4-Evo Ready Connector MA293 Assembly Instructions
Comprehensive assembly instructions for Stäubli MC4-Evo Ready connectors (MA293), covering safety, tools, cable preparation, assembly, mating, disconnecting, and technical data for PV-KST4-EVO READY and PV-KBT4-EVO READY.
Preview Stäubli MC4-Evo 2 Branch Connector MA292: Assembly and Technical Data
Comprehensive assembly instructions and technical specifications for the Stäubli MC4-Evo 2 MA292 branch connector, including safety guidelines, installation notes, and product data for PV systems.
Preview Stäubli MC4-Evo 2 Panel Receptacle Assembly Instructions (MA713)
Detailed assembly instructions for Stäubli MC4-Evo 2 panel receptacles (PV-ADB4-EVO 2A/..., PV-ADS4-EVO 2A/...), covering safety, tools, cable preparation, crimping, installation, and checks.
Preview Stäubli MC4-Evo Ready Connector MA293 Assembly Instructions
Comprehensive assembly instructions for the Stäubli MC4-Evo Ready MA293 connector. This guide covers essential safety precautions, required tools, detailed cable preparation steps, connector assembly, fastening, mating, and disconnecting procedures, along with technical specifications for photovoltaic applications.
Preview Stäubli MC4-Evo 2 MA299 Panel Receptacle Assembly Instructions
This document provides comprehensive assembly and installation instructions for the Stäubli MC4-Evo 2 MA299 panel receptacle. It covers safety guidelines, required tools, cable preparation, crimping procedures, connector installation, assembly checks, mating and disconnecting, notes on installation, and detailed technical specifications for photovoltaic applications.