Installation Procedure IP 832 FORWARD INSERT

The Lee Company
2 Pettipaug Road
Westbrook, CT 06498-0424 USA
860-399-6281

REVISION HISTORY

Revision Date Change
A 8/1/2022 Initial Release

Factory Installation Procedure

Installation Procedure, Lee Check Valve, 832 Series, Forward, Insert

1. Overview

This procedure is intended to provide process guidelines for proper installation of Lee Check Valve, 832 Series, Forward, Insert product. Section 2 provides an overview of the hole requirements. Section 3 contains the installation procedure. Section 4 contains a diagram of proper orientation and position of the product with respect to the installation hole and installation tool.

Compliance with this installation procedure will ensure optimal product performance. Please contact your local Lee Company Sales Representative for questions concerning installation of Lee Company products.

2. Installation Hole Requirements

The Lee Check Valve, 832 Series, Forward, Insert product is purposely designed to perform well under adverse conditions. Therefore, the installation hole specifications outlined in this section should be followed precisely to ensure proper function of the product's expansion sealing features. Installation forces and pressure ratings are based on installations into aluminum housings or manifolds.

Installation hole specifications as found on Lee Installation Drawing 1INST033385S (Appendix B) will ensure proper operation of the Lee Check Valve, 832 Series, Forward, Insert product. The hole should be clean, dry, and free of burrs. Surface finish should not exceed 1.6µm (Ra) with no longitudinal surface defects. Surface finish requirements must be given special attention. The expansion section of the Lee Check Valve, 832 Series, Forward, Insert product seals and retains the product in the hole. A smooth machined surface where the product interacts with the hole is needed to seal and retain the valve properly.

The Lee Company does not recommend the use of coatings or surface treatments in the area of the installation hole where the product is to be installed. These may reduce product retention.

3. Installation

Installation Overview

All Lee Check Valve, 832 Series, Forward, Insert products use a pin to expand a grooved section of the insert's body into the housing wall to affect a seal and retain the component. The pin, which has been pre-installed, is driven into the body. The insert is pre-lubricated for proper installation. Do not clean prior to installation.

Diagram: Installation Process

A diagram illustrates the installation process. It shows an 'Installation Tool' positioned above an 'Installation Hole' containing the 'Forward Valve' insert. A 'Pin' within the insert is visible. The diagram depicts the 'Installation Force' being applied by the tool to drive the pin. The numbered steps describe the sequence:

  1. When the installation tool is retracted, the pin should be flush to within 0.25 mm above flush of the insert body.
  2. The installation tool (P/N CCRT0900150S), aligned with the installation hole, approaches the hole and contacts the back of the pre-installed pin. The tool drives the pin into the Lee Check Valve, 832 Series, Forward, Insert product body with a force of 6,227 Newtons maximum. Using friction and penetration, the lands bite into the housing material.
  3. The Lee Check Valve, 832 Series, Forward, Insert product is inserted into the installation hole with the pin end up as shown.

3.1 Installation Equipment

The Lee Check Valve, 832 Series, Forward, Insert product has been designed to be installed using pneumatic, hydraulic, or electric servo-press equipment. An electric servo-press system is recommended for high volume production as it provides detailed feedback for better in-process controls of the installation process. The housing in which the component is to be installed should be held stationary on a solid surface. The Lee Check Valve, 832 Series, Forward, Insert product is expanded by the insertion of the pre-installed and lubricated expansion pin using an installation tool under load. Adjust the press stroke to eliminate excess over travel as this may damage the Lee Check Valve, 832 Series, Forward, Insert product. Adjust the press supply pressure to limit the maximum force to 6,672 Newtons.

Insertion should be done using Lee Installation Tool P/N CCRT0900150S (see Appendix C). The tool and installation hole need to be concentric within 0.03 mm as shown in Diagram of Factory Installation Appendix A. See Appendix D for further information about the recommended electric servo-press system from Promess, Inc.

3.2 Standard Factory Installation (see Appendix A)

  1. Firmly support the housing or manifold in which the valve is to be installed.
  2. Insert Lee Check Valve, 832 Series, Forward, Insert product into the installation hole, pin end up, until it is seated on the shoulder of the installation hole.
  3. The installation force should be 6,227 Newtons maximum using Lee Installation Tool P/N CCRT0900150S. The tool can approach the product at a rate of 20-35 mm/sec. The maximum speed of the tool during installation should be limited to 3 mm/sec.
  4. Inspect the Lee Check Valve, 832 Series, Forward, Insert product for proper installation by measuring the depth of the pin relative to the valve body. Installation is complete when the exposed ends (surfaces A and B) are flush to within 0.25mm above flush of each other as shown in Appendix A.
  5. Retract the tool and follow the same procedure for additional installations.

Factory Best Practices:

  1. Examine the condition of the Installation Tool at appropriate intervals and replace if damaged or chipped.
  2. Clean feed bowls once per day.
  3. Turn off vibratory feed bowl when the assembly station is idle, or if the feed rail is full of parts.
  4. Use the minimum vibration setting to advance valves in the feed bowl.
  5. If the check valve is blown into the assembly area from the feed rail, minimize the air pressure at which the check valve is blown into the assembly area to prevent possible damage.

4. Appendices

4.1 Appendix A: Diagram of Factory Installation

(Section View of Hole, Forward, Insert Product, and Installation Tool)

Diagram: Factory Installation Views

This appendix contains two diagrams illustrating the installation process. The top diagram, labeled 'During Installation', shows a cross-section of the installation hole, the forward valve insert, and the installation tool. It indicates that the 'Tool and Hole concentric to within 0.03 mm'. The bottom diagram, labeled 'Post Installation', shows the insert seated in the hole. It indicates that 'Installation is complete when the exposed ends (surfaces A and B) are flush to within 0.25 mm above' the reference plane.

4.2 Appendix B: Installation Hole Dimensions

Diagram: Installation Hole Dimensions

This diagram shows a cross-section of the required installation hole with dimensions in millimeters. Key dimensions include:

  • Diameter: 8.05 - 8.13 mm
  • Diameter: 10.50 - 11.00 mm
  • Angle: 118° ±2°
  • Depth: 6.27 ± 0.20 mm
  • Minimum depth: 4.50 mm
  • Minimum depth: 17.0 mm
  • Minimum depth: 3.0 mm

Requirements for the hole are reiterated: The hole should be clean, dry, and free of burrs. No longitudinal surface defects permitted. No coatings or surface treatments in the area of the installation hole where the product is to be installed. Refer to Lee Drawing No. 1INST033385S for complete specifications.

4.3 Appendix C: Installation Tool Dimensions

Diagram: Installation Tool Dimensions

This diagram shows the dimensions of the installation tool in inches. Key dimensions include:

  • Diameter: 0.496 - 0.499 inches
  • Length: 6.00 inches
  • Chamfer: 0.010 x 45°
  • Other features indicated at 2.10-1.90 and 0.312-0.314.

The tool is marked with the part number and revision. Refer to Lee Part No. CCRT0900150S for complete specifications.

4.4 Appendix D: Promess, Inc. Press Information

Contact Information:

Promess, Inc.
11429 Grand River Road
Brighton, MI 48116
Phone: (810) 229-9334
Web: www.promessinc.com

Press Information:

The EMAP 12kN/200mm – FEMP8/200MP press includes the following components:

  • Press with integrated load cell, motor mounting plate, and Motor
  • PreAmplifier (Connected to the Press Load Cell and Prox Switch)
  • MotionPRO Servo Amplifier
  • Motor Power Cable
  • Motor Encoder Cable
  • PreAmplifier Cable
  • MotionPRO software

Image: Promess Press

An image displays a Promess EMAP 12kN/200mm press.

Models: 832 Series Side Exit Check Valve, 832 Series, Side Exit Check Valve, Exit Check Valve, Check Valve, Valve

File Info : application/pdf, 7 Pages, 334.70KB

PDF preview unavailable. Download the PDF instead.

Installation-Procedure-1-832-Series-Forward-Insert

References

Microsoft Word for Microsoft 365

Related Documents

Preview Lee Company IP 558 Reverse Insert Unscreened Installation Procedure
Detailed installation procedure for the Lee Company IP 558 Reverse Insert Unscreened check valve, including hole requirements, equipment, standard installation steps, and appendices with diagrams and specifications.
Preview Lee Check Valve 558 Series Forward Insert Installation Procedure
This document outlines the factory installation procedure for the Lee Check Valve, 558 Series, Forward, Insert product, including hole requirements, installation steps, and best practices.
Preview Lee 558 Series Press-In Check Valve Installation Procedure
Detailed installation procedure for the Lee 558 Series Press-In Check Valve, covering hole requirements, installation steps, best practices, and dimensional specifications for forward and reverse flow applications.
Preview The Lee Company 2.5 mm Press-In Check Valve Installation Procedure for Reverse Flow
Detailed installation procedure for The Lee Company's 2.5 mm Press-In Check Valve, designed for reverse flow applications in plastic manifolds and fittings. Includes hole requirements, installation steps, and best practices.
Preview Lee Relief Valve 5.5mm Series Installation Procedure IP PCHR 5.5
Detailed installation procedure for the Lee Relief Valve, 5.5mm Series, Insert, Reverse product (Model IP PCHR 5.5). Includes hole requirements, equipment, standard installation steps, and dimensional diagrams for the valve, hole, and installation tool from The Lee Company.
Preview The Lee Company Technical Hydraulic Handbook - 12th Edition
Explore The Lee Company's 12th Edition Technical Hydraulic Handbook, featuring comprehensive engineering data on miniature fluid control components for aerospace, high-performance racing, oil and gas, and medical industries.
Preview The Lee Company Piezoelectric Disc Pump User Manual
Comprehensive user manual for The Lee Company's Piezoelectric Disc Pumps, detailing product features, safety precautions, installation procedures, system operation, available accessories, and conformity certificates. Covers BL/XP/LT, HP, and US series pumps.
Preview The Lee Company Variable Volume Pump Driver Quick Start Guide
A quick start guide for setting up and operating The Lee Company's Variable Volume Pump Driver, featuring the ADI Trinamic TMC5130 motion controller and MAX22200 solenoid drivers. Covers introduction to pumps and drivers, required materials, setup procedures, program interface details, and example scripts.