PLEASE READ
Before Installing your GREE MULTIPRO
STOP IMPORTANT: Before You Continue...
Warranty
ONLY VALID IF SYSTEM IS INSTALLED BY A LICENSED HVAC CONTRACTOR.
Installation must comply with applicable local & national codes.
TOOLS REQUIRED
- R410A Flaring Tool
- Clamp-On Amp Meter
- Vacuum Pump
- Refrigerant Scale
- Micron Gauge
- Refrigerant Manifold & Gauges
- Nitrogen Regulator
- Wrenches (standard)
- Adjustable Torque Wrench
- Hex Keys (Allen Wrenches)
- Drill & Drill Bits
- Hole Saw
- Pipe Cutter
- Level
- Screw Drivers
- Safety Goggles
- Gloves
BEST PRACTICES
Verify Equipment
- ✔️ Ensure both IDU & ODU
- Model Numbers begin with GMV
Unit Placement
- ✔️ Follow clearance guidelines on indoor & outdoor units for proper airflow & servicing
- ✔️ Include space for drainage so condensate flows out of unit
- ✔️ Anchor both units properly to prevent vibration or malfunction
- ✔️ Be sure condensate drain tubing is pitched downward for proper drainage
Piping
- ✔️ Use only correct line set size as determined by either Basic Layout, system builder or selection software
- ✔️ Insulate both refrigerant lines from each other
- ✔️ For flare connections, use 45° flaring tool
- ✔️ Refer to GREE Multipro reference guide for Piping details.
Communication Wiring
- ✔️ All Control wiring is 18 AWG, 2 Conductor, Stranded
- Shielding is not required, but if used must tie together, following the daisy chain (parallel) configuration of the control wiring, and grounded only at the outdoor unit.
- ✔️ Resistor to be installed on the last indoor unit D1 & D2
Wiring
- ✔️ Wiring and breaker sizing must be in accordance with local codes
- ✔️ Outdoor and Indoor units are powered separately and are 208/230 vac
- ✔️ Must have a means to disconnect for all indoor and outdoor units
- ✔️ Multiple indoor units may share one breaker (Check local requirements)
- ✔️ Surge protector HIGHLY recommended
Charging
- ✔️ Test refrigerant lines for leaks by pressurizing with Nitrogen to 500 PSI.
- ✔️ While under pressure, use a leak detection solution to test for all leaks at all flare solder, compression fitting connections.
- ✔️ Use only approved evacuation hose & vacuum pump oil for proper evacuation and leak testing: Evacuate to less than 500 Microns and hold for 30 minutes.
- ✔️ If refrigerant is added, use an electronic scale and weigh in the precise amount that is determined by the basic layout or the selection software
- ✔️ Open all service valves (air handler) prior to energizing the system.
INSTALL SUPPORT
greecomfort.com/resources | www.youtube.com/@GREEComfort/videos