GENERAL

Lochinvar CPM Boilers are certified for use on the following flue categories: 

Installation type Category Description
 

B23

 

Open flue

An appliance intended to be connected to a flue that evacuates the products of combustion to the outside of the room containing the appliance. The combustion air is drawn directly from the room.
C13 Closed Flue An appliance connected to either a concentric or twin-pipe flue system with a Horizontal flue terminal. Both the air inlet and flue exhaust must be in the same pressure zone.
C33 Closed Flue An appliance connected to either a concentric or twin-pipe flue system with a Vertical flue terminal. Both the air inlet and flue exhaust must be in the same pressure zone.
 

C43

 

Closed Flue

An appliance connected to a common air inlet and flue exhaust system, which is designed for more than one appliance. This common system has a single air inlet and flue exhaust and is part of the building not the appliance.
C53 Closed Flue An appliance connected to a twin-pipe flue system with a Horizontal or Vertical flue terminal. Both air inlet and flue exhaust may be in different pressure zones.
 

C63

 

Closed Flue

An appliance intended to be connected to a separately approved and marketed system for the supply of combustion air and discharge of combustion products (i.e. other than that supplied by the water heater manufacturer).
 

C83

 

Closed Flue

An appliance connected via one of its ducts to a single or common duct system. This duct system consists of a single natural draught duct (i.e. not incorporating a fan) that evacuates the products of combustion.

The appliance is connected via a second of its ducts to a terminal, which supplies air to the appliance from outside the building.

All installations should comply with the requirements of: 

  1.  For appliances up to 70kW net input- BS5440-1:2008- Flueing and ventilation for gas appliances of rated input not exceeding 70 kW net (1st, 2nd and 3rd family gases). Specification for installation of gas appliances to chimneys and for maintenance of chimneys.
  2.  Refer to drawing 1 and table 1 for details of terminal locations.
  3.  For appliances over 70kW net input- IGEM/UP/10 Edition 4 +A: 2016 – Installation of flued gas appliances in industrial and commercial premises, specific attention should be paid to the following sections.
  4.  Refer to drawing 1 and table 1 for details of terminal locations.
  5.  Horizontal terminations shall be located according to the minimum distances given in table 1, and subject to the risk assessment criteria shown in table 2.
  6.  Horizontal flue terminations (other than for fan dilution systems) must not be installed for any single appliance or group of appliances with a total nett input exceeding 333kW net heat input.
  7.  For any single appliance or group of appliances with a total net heat input exceeding 333 kW, the general requirements of IGEM/UP/10 Edition 4 +A: 2016 shall apply and approval must be sought from the Local Authority prior to commencement of the installation.
  8.  The Clean Air Act for installations exceeding 333kW nett input.Lochinvar CMP58 CPM Boiler Range Flue fig 1

TABLE 1 BOILER TERMINAL LOCATIONS

Location Description   CPM58 CPM77 CPM96 CPM116 CPM144 CPM175
A Directly below an opening, air brick, opening windows etc.# mm 300 2500 2500 2500 2500 2500
B Above an opening, air brick, opening windows etc. mm 300 631 760 896 1092 1294
C Horizontally to an opening, air brick, opening windows etc.# mm 300 631 760 896 1092 1294
D Below a gutter or sanitary pipework mm 75 200 200 200 200 200
E Below the eaves mm 200 200 200 200 200 200
F Below a balcony or car port roof mm 200 Not recommended see UP10 risk assessment
G From a vertical drain or soil pipe mm 144 150 150 150 150 150
H From an internal or external corner mm 300 1099 1513 1948 2573 3220
I Above ground, roof or balcony level mm 300 300 300 300 300 300
J From a surface facing the terminal mm 600 1100 1514 1948 2573 3220
K From a terminal facing the terminal mm 1200 2083 2429 2792 3314 3855
L From an opening in the car port (e.g. door, window) into the dwelling mm 1200 Not recommended see UP10 risk assessment
M Vertically from a terminal on the same wall mm 1500 2500 2500 2500 2500 2500
N Horizontally from a terminal on the same wall* mm 300 600 600 900 900 n/a**
P From a vertical structure on the roof mm 300 1500 1500 1500 1500 1500
Q Above intersection with the roof mm 150 311 359 409 481 556
  • distances shown ensure the boilers will operate without problems under most conditions, these distances can be reduced in certain circumstances contact Lochinvar Technical support for assistance if required.
  • multiple boiler installation of model CPM175 are covered by the clean air act and must comply with its requirements see UP10 figure 7 for full clarification

TABLE 2 RISK ASSESMENT
The table below is an excerpt from IGEMUP10 and should be used in conjunction with that document

Further to the requirements in IGEM/UP/10 Edition 4 +A: 2016 Section 8 under clause 8.7.3.3 and Figure 7 the following risk assessment gives guidance for the positioning of horizontal flues. This form should be completed before work commences and undertaken by a person who is competent to undertake the risk assessment.

Type C appliances with net heat input exceeding 70 kW and not exceeding 333 kW low level flue discharge risk assessment (including net heat input for groups of appliances)
No. Regarding the flue position No Yes
 

1

Is the proposed flue termination within the distance in Figure K of a road, path, track, thoroughfare, walkway, property boundary or area, which is used for general

public access other than for maintenance purposes?

 

No

 

Yes

2 Is the proposed flue termination within the distance in Figure K to a playground, school, yard, seating area, or area where there may be a public gathering No Yes
3 If the proposed flue termination enclosed on more than two sides then does it comply with the requirements of Figure 11B? No Yes
 

4

Is the proposed flue termination within the distance in Figure K of a surface or building element that may be affected by corrosion or deterioration from plume

condensate?

 

No

 

Yes

5 Is the proposed flue position in an area where vehicles could be parked within distances from Figure 12 Line G to the flue? No Yes
6 Are there shrubs or trees within minimum distances shown on Figure K of the proposed terminal position? No Yes
7 Is the proposed flue termination within a light well? No Yes
 

8

Are the products of combustion from the proposed flue position likely to build up under unfavourable atmospheric conditions, due to poor cross flow of air caused by enclosures or adjacent structures and/or likely to cause nuisance?  

No

 

Yes

9 Is the flue termination position likely to cause a nuisance to adjoining properties? No Yes
Building Regulations part J
10 Is the proposed flue termination less than 300 mm from the boundary of the property, as measured from the side of the terminal to the boundary? No Yes
Regarding the Clean Air Act
11 Is the total output of the individual, or group of flue terminals (if within 5U (see A3.7)), greater than 333 kW net heat input? No Yes
General
12 Are there any other considerations that are required for this risk assessment, see separate sheet. No Yes
13 Comments:    
                   
If all answers are Blue then the flue position should be suitable
If any answer is Orange then the flue position is unsuitable, consider revising the position or type of flue outlet or contact the local Environmental Health officer for assistance and/or approval

BOILER FLUE INFORMATION

Model Number   CPM58 CPM77 CPM96 CPM116 CPM144 CPM175
FLUE DATA TYPE B23
Nominal flue diameter mm 80 100 130
Maximum flue gas temp °C 95
Flue gas temperature °C 85-95
Flue draught requirements mbar -0.03 to -0.1
Available pressure for the flue system Pa 200
Maximum flue gas volume g/s 5.59 to 28.9 6.52 to 38.6 7.69 to 47.9 11.6 to 57.7 15.2 to 71.7 20.1 to 86.2
FLUE DATA TYPE C13 & C33
Nominal flue diameter mm 80/125 100/150
Maximum flue gas temp °C 95
FLUE DATA TYPE C43 & C53
Nominal flue diameter mm 80 100 130
Maximum flue gas temp °C 95

CONCENTRIC FLUE SYSTEMS

CPMH001 CONCENTRIC HORIZONTAL FLUE ASSEMBLY MODELS – CPM58, CPM77
COMPONENTS INCLUDED
Item No. Description Included
LV310757 CONCENTRIC HORIZONTAL TERMINAL – Ø80/125mm PP 1
M28925B TERMINAL WALL PLATES 1
LV310735 CONCENTRIC BEND 90° Ø80/125mm PP 1
Maximum resistance in the flue system ≤200pa
 
Additional Flue Ancillary Items
Item No. Description Dimensions
LV310740B CONCENTRIC EXTENSION – Ø80/125mm PP FIXED 250mm
LV310745B CONCENTRIC EXTENSION – Ø80/125mm PP 500mm
LV310742B CONCENTRIC EXTENSION – Ø80/125mm PP FIXED 1000mm
LV310743B CONCENTRIC EXTENSION – Ø80/125mm PP FIXED 2000mm
LV310744B CONCENTRIC EXTENSION – Ø80/125mm PP TELESCOPIC 240mm-360mm
LV310734B CONCENTRIC BEND 45° Ø80/125mm PP See Drawing Below
LV310735B CONCENTRIC BEND 90° Ø80/125mm PP See Drawing Below
M84481B WALL CLAMP Ø125mm N/A

Lochinvar CMP58 CPM Boiler Range Flue fig 2

CPMH003 CONCENTRIC HORIZONTAL FLUE ASSEMBLY MODELS – CPM96, CPM116
COMPONENTS INCLUDED
Item No. Description Included
LV310758B CONCENTRIC HORIZONTAL TERMINAL Ø100/150mm PP 1
M84410B CONCENTRIC BEND 90° Ø100/150mm PP SHORT RADIUS 1
Maximum resistance in the flue system ≤200pa
 
CPMH004 CONCENTRIC HORIZONTAL FLUE ASSEMBLY MODELS – CPM144, CPM175
COMPONENTS INCLUDED
Item No. Description Included
LV310758B CONCENTRIC HORIZONTAL TERMINAL Ø100/150mm PP 1
E61-001-172B CONCENTRIC CONVERSION KIT 1
M84410B CONCENTRIC BEND 90° Ø100/150mm PP SHORT RADIUS 1
Maximum resistance in the flue system ≤200pa
 
Additional Flue Ancillary Items
Item No. Description Dimensions
M84405B CONCENTRIC EXTENSION Ø100/150mm Cutable 500mm
M84402B CONCENTRIC EXTENSION Ø100/150mm PP FIXED 1000mm
M84412B CONCENTRIC BEND 90° Ø100/150mm PP See Drawing Below
M84413B CONCENTRIC BEND 45° Ø100/150mm PP See Drawing Below
M84421B SAMPLING POINT Ø100/150mm PP 115mm
M87196B WALL CLAMP Ø150mm  

Lochinvar CMP58 CPM Boiler Range Flue fig 3Lochinvar CMP58 CPM Boiler Range Flue fig 4

PLUME MANAGEMENT KITS
LG800008B PLUME MANAGEMENT KIT Ø80/125mm
LG800009B PLUME MANAGEMENT KIT Ø100/150mm
No Description CPM58 CPM77 CPM96 CPM116 CPM144 CPM175
1 CONCENTRIC BEND 90°-PP Ø80/125mm Ø80/125mm Ø100/150mm Ø100/150mm N/A N/A
2 CONCENTRIC HORIZONTAL PLUME KIT TERMINAL -PP Ø80/125mm Ø80/125mm Ø100/150mm Ø100/150mm N/A N/A
3 EXTENSION -PP CUTABLE (1000mm) Ø80mm Ø80mm Ø100mm Ø100mm N/A N/A
4 BEND 90°-PP Ø80mm Ø80mm Ø100mm Ø100mm N/A N/A
5 PLUME KIT BIRD GUARD Ø80mm Ø80mm Ø100mm Ø100mm N/A N/A
6 PLUME KIT FLUE EXIT-PP Ø80mm Ø80mm Ø100mm Ø100mm N/A N/A
7 WALL CLAMP Ø80mm Ø80mm Ø100mm Ø100mm N/A N/A
A INTERNAL DIAMETER Ø80mm Ø80mm Ø100mm Ø100mm N/A N/A
B EXTERNAL DIAMETER Ø125mm Ø125mm Ø150mm Ø150mm N/A N/A
CPMV001 CONCENTRIC VERTICAL FLUE ASSEMBLY MODELS – CPM58, CPM77
COMPONENTS INCLUDED
Item No. Description Included
LV310753 CONCENTRIC VERTICAL TERMINAL – Ø80/125mm PP 1
LV310745B CONCENTRIC EXTENSION – Ø80/125mm PP (500mm) 1
LV310742B CONCENTRIC EXTENSION – Ø80/125mm PP FIXED (1000mm) 1
Maximum resistance in the flue system ≤200pa
 
Additional Flue Ancillary Items
Item No. Description Dimensions
LV310740B CONCENTRIC EXTENSION – Ø80/125mm PP FIXED 250mm
LV310745B CONCENTRIC EXTENSION – Ø80/125mm PP 500mm
LV310742B CONCENTRIC EXTENSION – Ø80/125mm PP FIXED 1000mm
LV310743B CONCENTRIC EXTENSION – Ø80/125mm PP FIXED 2000mm
LV310744B CONCENTRIC EXTENSION – Ø80/125mm PP TELESCOPIC 240-360mm
LV310734B CONCENTRIC BEND 45° Ø80/125mm PP See Drawing Below
LV310735B CONCENTRIC BEND 90° Ø80/125mm PP See Drawing Below
M84481B WALL CLAMP Ø125mm N/A
LV302520 FLAT ROOF FLASHING Ø140mm ALU N/A

Lochinvar CMP58 CPM Boiler Range Flue fig 5

CPMV003 CONCENTRIC VERTICAL FLUE ASSEMBLY MODELS – CPM96, CPM116
COMPONENTS INCLUDED
Item No. Description Included
LV310754B CONCENTRIC VERTICAL TERMINAL Ø100/150mm PP 1
M84405B CONCENTRIC EXTENSION Ø100/150mm (500mm) Cutable 1
M84402B CONCENTRIC EXTENSION Ø100/150mm (1000mm) PP FIXED 1
Maximum resistance in the flue system ≤200pa
 
Additional Flue Ancillary Items
Item No. Description Dimensions
M84405B CONCENTRIC EXTENSION Ø100/150mm Cutable 500mm
M84402B CONCENTRIC EXTENSION Ø100/150mm PP FIXED 1000mm
M84412B CONCENTRIC BEND 90° Ø100/150mm PP See Drawing Below
M84413B CONCENTRIC BEND 45° Ø100/150mm PP See Drawing Below
M84421B SAMPLING POINT Ø100/150mm PP 115mm
M87196B WALL CLAMP Ø150mm  

Lochinvar CMP58 CPM Boiler Range Flue fig 6

CONCENTRIC FLUE SIZING/CALCULATIONS

 

Item

Resistance in Pa
CPM 58 80/125 CPM 77 80/125 CPM 96 100/150 CPM 116 100/150 CPM 144 100/150 CPM 175 100/150
Wall terminal 13 22 19 24 40 48
Roof terminal 34 61 39 45 69 86
Straight tube (m) 9 12 8 10 14 16
45° Elbow 5 7 8 9 14 16
90° Elbow 8 13 11 13 22 28
Plume kit 10 10 20 25 n/a n/a

Use the table below to calculate the total flue system resistance

Item Quantity Resistance Total
Wall terminal      
Roof terminal      
Straight tube (m)      
45° Elbow      
90° Elbow      
Plume kit      
Total Resistance (Pa)  

TWIN-PIPE FLUE SYSTEMS TYPE C53

CPM TWIN-PIPE FLUE ASSEMBLY MODELS CPM58 CPM77
COMPONENTS REQUIRED TO START INSTALLATION
VERTICAL FLUE
Item No Description No Required
LV305030B APPLIANCE AIR INTAKE GUARD Ø80/125mm 1
LV310753B CONCENTRIC VERTICAL TERMINAL Ø80/125mm PP 1
LV305016 HORIZONTAL AIR INLET Ø80mm 1
M28925B TERMINAL WALL PLATES (PAIR) 1
 
HORIZONTAL FLUE
Item No Description No Required
LV305030B APPLIANCE AIR INTAKE GUARD Ø80/125mm 1
LV310757B CONCENTRIC HORIZONTAL TERMINAL Ø80/125mm PP 1
LV305016 HORIZONTAL AIR INLET Ø80mm 1
M28925B TERMINAL WALL PLATES (PAIR) 1

Lochinvar CMP58 CPM Boiler Range Flue fig 7

Additional Flue Ancillary Items
Item No. Description Dimensions
LV310718B EXTENSION – Ø80mm PP CUT TO LENGTH 250mm
M85271B EXTENSION Ø80mm PP CUT TO LENGTH 500mm
M85272B EXTENSION Ø80mm PP CUT TO LENGTH 1000mm
LV310721B EXTENSION – Ø80mm PP CUT TO LENGTH 2000mm
LV310722B EXTENSION – Ø80mm PP TELESCOPIC 240-360mm
M85292B BEND 45° 80mm PP See Drawing Below
M85291B BEND 90° 80mm PP See Drawing Below
M87191B WALL CLAMP Ø80mm N/A
CPM TWIN-PIPE FLUE ASSEMBLY MODELS CPM96,CPM116
COMPONENTS REQUIRED TO START INSTALLATION
VERTICAL FLUE
Item No Description No

Required

LV304872B APPLIANCE AIR INTAKE GUARD Ø100/150mm 1
LV310754B CONCENTRIC VERTICAL TERMINAL Ø100/150mm PP 1
 
HORIZONTAL FLUE
Item No Description No Required
LV304872B APPLIANCE AIR INTAKE GUARD Ø100/150mm 1
LV310758B CONCENTRIC HORIZONTAL TERMINAL Ø100/150mm PP 1
LV305039B HORIZONTAL AIR INLET Ø100mm ALU 1

 

Additional Flue Ancillary Items
Item No. Description Dimensions
M85176B EXTENSION Ø100mm PP CUT TO LENGTH 500mm
M85177B EXTENSION Ø100mm PP CUT TO LENGTH 1000mm
M85181B BEND 90° 100mm PP See Drawing Below
M85182B BEND 45° 100mm PP See Drawing Below
M87193B WALL BAND (100mm) n/a

Lochinvar CMP58 CPM Boiler Range Flue fig 8

TWIN-PIPE FLUE SIZING/CALCULATIONS

Item Size (mm) Resistance (Pa)
CPM 58 CPM 77 CPM 96 CPM 116 CPM 144 CPM 175
Straight tube (per metre) 80 4 7.5 X X n/a n/a
Straight tube (per metre) 100 1.2 3 3.5 4 n/a n/a
Straight tube (per metre) 130 0.4 0.7 0.8 1.1 n/a n/a
45° Elbow 80 2 3.5 X X n/a n/a
45° Elbow 100 0.6 1.5 1.7 2 n/a n/a
45° Elbow 130 0.2 0.4 0.4 0.5 n/a n/a
90° Elbow 80 4 7 X X n/a n/a
90° Elbow 100 1.2 3 3.5 4 n/a n/a
90° Elbow 130 0.3 0.7 0.8 1.1 n/a n/a
Vertical inlet cap 80 10.4 18.1 X X n/a n/a
Vertical inlet cap 100 4.2 7.4 11.4 16.7 n/a n/a
Vertical inlet cap 130 1.5 2.6 4 5.8 n/a n/a

To be used for Lochinvar supplied M&G air inlet system components resistance only

Item Size (mm) Resistance (Pa)
CPM 58 CPM 77 CPM 96 CPM 116 CPM 144 CPM 175
Straight tube (per metre) 80 5 8 X X n/a n/a
Straight tube (per metre) 100 2 3.5 4 6.5 n/a n/a
Straight tube (per metre) 130 0.5 0.8 1.2 1.8 n/a n/a
45° Elbow 80 2.5 4 X X n/a n/a
45° Elbow 100 1 1.7 2 3.2 n/a n/a
45° Elbow 130 0.2 0.4 1.6 0.8 n/a n/a
90° Elbow 80 5 8 X X n/a n/a
90° Elbow 100 2 3.5 4 6.5 n/a n/a
90° Elbow 130 0.4 0.8 1.2 1.8 n/a n/a
Vertical exhaust cap 80 13.8 24 X X n/a n/a
Vertical exhaust cap 100 5.6 9.8 15.2 22.1 n/a n/a
Vertical exhaust cap 130 2 3.5 5.3 7.8 n/a n/a

Use the table below to calculate the flue system resistance.

 

 

 

Flue exhaust

Item Quantity Resistance Total
Straight tube (m)      
45° Elbow      
90° Elbow      
Concentric Vertical terminal      
Total Resistance flue exhaust (Pa)  
 

 

 

Air Inlet

Item Quantity Resistance Total
Straight tube (m)      
45° Elbow      
90° Elbow      
Air Inlet      
Total Resistance air inlet (Pa)  
Total Resistance air inlet and flue exhaust (Pa)  

CONVENTIONAL (EXHAUST ONLY) FLUE SYSTEMS TYPE B23

CPM CONVENTIONAL FLUE ASSEMBLY MODELS CPM58-CPM77
COMPONENTS REQUIRED TO START INSTALLATION
VERTICAL FLUE
Item No Description No Required
LV305030B APPLIANCE AIR INTAKE GUARD Ø80/125mm 1
M86864B CONCENTRIC VERTICAL TERMINAL Ø80/125mm PP 1
Additional Flue Ancillary Items
Item No. Description Dimensions
LV310718B EXTENSION – Ø80mm PP CUT TO LENGTH 250mm
M85271B EXTENSION Ø80mm PP CUT TO LENGTH 500mm
M85272B EXTENSION Ø80mm PP CUT TO LENGTH 1000mm
LV310721B EXTENSION – Ø80mm PP CUT TO LENGTH 2000mm
LV310722B EXTENSION – Ø80mm PP TELESCOPIC 240-360mm
M85292B BEND 45° 80mm PP See Drawing Below
M85291B BEND 90° 80mm PP See Drawing Below
M87191B WALL CLAMP Ø80mm N/A

Lochinvar CMP58 CPM Boiler Range Flue fig 9

CPM CONVENTIONAL FLUE ASSEMBLY MODELS CPM96-CPM116
COMPONENTS REQUIRED TO START INSTALLATION
VERTICAL FLUE    
Item No. Description No Required
LV304872B APPLIANCE AIR INTAKE GUARD Ø100/150mm 1
LV310754B CONCENTRIC VERTICAL TERMINAL Ø100/150mm PP 1

Lochinvar CMP58 CPM Boiler Range Flue fig 10

CONVENTIONAL FLUE SIZING/CALCULATIONS 

Item Size (mm) Resistance (Pa)
CPM 58 CPM 77 CPM 96 CPM 116 CPM 144 CPM 175
Straight tube (per metre) 80 4 7.5 X X n/a n/a
Straight tube (per metre) 100 1.2 3 3.5 4 n/a n/a
Straight tube (per metre) 130 0.4 0.7 0.8 1.1 n/a n/a
45° Elbow 80 2 3.5 X X n/a n/a
45° Elbow 100 0.6 1.5 1.7 2 n/a n/a
45° Elbow 130 0.2 0.4 0.4 0.5 n/a n/a
90° Elbow 80 4 7 X X n/a n/a
90° Elbow 100 1.2 3 3.5 4 n/a n/a
90° Elbow 130 0.3 0.7 0.8 1.1 n/a n/a
Vertical inlet cap 80 10.4 18.1 X X n/a n/a
Vertical inlet cap 100 4.2 7.4 11.4 16.7 n/a n/a
Vertical inlet cap 130 1.5 2.6 4 5.8 n/a n/a

Use the table below to calculate the flue system resistance.

Item Quantity Resistance Total
Straight tube (m)      
45° Elbow      
90° Elbow      
Concentric Vertical terminal      
Total Resistance flue exhaust (Pa)  

FLUE SYSTEMS USING FLUE NOT SUPPLIED BY LOCHINVAR TYPE C63
In general, boilers are certified with their own purpose supplied Concentrically or Twin Pipe flue systems, C63 certified appliances allow the installer to use other flue systems when installing the boiler however, they must be of a suitable minimum standard as per the table below.

 

 

CE string Flue gas material

 

European standard

 

Temperature class

 

Pressure class

 

Resistance to condensate

Corrosion resistance class  

Metal: liner specifications

Soot fire resistance class Distance to combustible material  

Plastics:

Plastics: fire behaviour  

Plastics:

min. eis PP EN 14471 T120 P1 W 1 n/a O 30 I of E C/E L
min. eis RVS EN 1856-1 T120 P1 W 1 L20040 O 40 n/a n/a n/a
Material Boiler dnom Doutside dinside Linsert
SS CPM58-CPM77 80 80 +0,3/ -0,7 81 +0,3/ -0,3 50 +2/ -2
SS CPM96-CPM116 100 100 +0,3/ -0,7 101 +0,3/ -0,3 50 +2/ -2
SS CPM144-CPM175 130 130 +0,3/ -0,7 131 +0,5/ -0,5 50 +2/ -2
PP CPM58-CPM77 80 80 +0,6/ -0,6   50 +20/ -2
PP CPM96-CPM116 100 100 +0,6/ -0,6   50 +20/ -2
PP CPM144-CPM175 130 130 +0,9/ -0,9   50 +20/ -2

Aluminium flue pipe must not be used on this appliance as it may lead to premature failure of the heat exchanger and will invalidate the warranty. 

COMMON FLUE SYSTEMS
Lochinvar can supply a PP common flue header see separate guide available at www.lochinvar.ltd.uk Alternatively the installer can use a flue installation specialist to design and supply a separate flue system under the flue designation C63 using the specifications shown on page 13 and information in the table below. Any installations using flue type C63 must be designed and installed in compliance with any local Building or planning regulations, but as these systems use a flue system not supplied by Lochinvar, Lochinvar cannot comment/advise or provide support on the design of this type of flue system. To design such a flue system, the installer/contractor must consult a specialist flue supplier who will be responsible for the design and installation of the separate flue system. When designing the type C63 flue system, the instructions in the Installation Manual, provided with the boiler, must be taken into account. Lochinvar will provide pressure loss figures for the specific units, but other than that, Lochinvar cannot provide support on Common Flue requests because flue certification is limited to the certified categories in the table on page 2. Lochinvar cannot accept any responsibility for Flue system design.

  CPM 58 CPM 77 CPM 96 CPM 116 CPM 144 CPM 175
Available pressure at the flue gas outlet 200Pa 200Pa 200Pa 200Pa 200Pa 200Pa
Flue Gas Mass Rate (G20) 96% (g/sec) 22.6 29.8 37.1 45.1 55.6 67.3
Flue Gas Mass Rate (G20) 25% (g/sec) 5.7 7.5 9.3 11.3 13.9 16.8
Flue Gas Mass Rate (G31) 96% (g/sec) 23.2 30.6 38.8 46.2 57 69
Flue Gas Mass Rate (G31) 25% (g/sec) 5.8 7.7 9.7 11.6 14.3 17.3

warning: CPM boiler range does not have an internal Non-Return Valve (NRV) as such any flue must be designed on zero or negative pressure unless a suitable NRV is fitted and if necessary interlocked to the appliance. Non Return Valves are included with the Lochinvar common flue header. 

Documents / Resources

Lochinvar CMP58 CPM Boiler Range Flue [pdf] Instruction Manual
CMP58, CPM77, CPM96, CPM116, CPM146, CPM176, CMP58 CPM Boiler Range Flue, CPM Boiler Range Flue

References

Leave a comment

Your email address will not be published. Required fields are marked *