E-BOX 48100R-C Solar Storage System
“
Product Information
Specifications:
- Model: E-BOX 48100R-C
- Replacement: B+ and B- Cord
- Tools Required: Electric screwdriver (Sleeve 8mm), Insulating
tape, Five zip ties
Product Usage Instructions
1. Tools Preparation
Before starting the replacement process, ensure you have the
following tools ready:
- Electric screwdriver with Sleeve 8mm
- Positive and Negative cables
- Insulating tape
- Five zip ties
2. Production Process
2.1 Opening the Cover
Use an electric screwdriver to unscrew the fourteen screws on
the upper cover and open it.
FAQ
Q: What should I do if I encounter difficulties during the
replacement process?
A: If you face any challenges or difficulties while replacing
the B+ and B- cord, please refer to the user manual for detailed
instructions. If the issue persists, contact our customer support
for assistance.
“`
E-BOX 48100R-C Replacement Instructions for B+ and B- Cord
1. Tools preparation
Electric screwdriver and Sleeve8mm) Positive cable and Negative cable
Insulating tape
Five zip ties
2. Production process
2.1 Use an electric screwdriver to unscrew the fourteen screws on the upper cover and open the cover.
Figure 1
Figure 2
Figure 3
Figure 4
2.2 Unscrew the left and right fixing screws and remove the crossbeam.
. Figure 5
Figure 6
Figure 7 2.3 Disconnect the power cable.
Figure 8
2.4 Remove the sampling lines from the BMS board in the order of J3,J2,J1 and disconnect the inter board communication line- MCU.
Figure 9
Figure 10
2.5 Disconnect B- lead out line,remove the positive electrode insulation as shown in the Figure 12unscrew the fixing screw with a socket as shown in the Figure
13,disconnect B+ lead and insulate it as shown in the Figure 14.
Figure 11
Figure 12
Figure 13
Figure 14
2.6 Remove the PC insulation sheet and loosen the 8 long fixing screws,loosen the
nuts securing the positive/negative leads and serial bronze medal.
Figure 15
Figure 16
Figure 17
Figure 18
2.7 Stand the battery pack upright, loosen the screws on the battery pack PC
insulation sheet of B+ and B- and remove them.Remove the old positive and
negative cables.
Figure 19
Figure 20
Figure 21
2.8 Connect the prepared new B+and B- cables to the battery pack, cover the PC
insulation sheet and secure the screws.
Figure 22
Figure 23
2.9 Position the battery pack(positive rear,negative front),put the series bronze
medal in the right position.
Figure 24
Figure 25
2.10 Tighten the nuts on the positive/negative leads and series bronze medal then
add the PC insulation sheet.
Figure 26
Figure 27
2.11 Thread the B+ lead terminal through the middle hole of the bronze plate, fix it
with screws shown in the Figure 28 and then wrap the metal part of the terminal
with insulating tape shown in the Figure 29.
Figure 28
Figure 29
2.12 Insert B-lead cable, insert the inter board communication line- MCU and insert
the sampling lines into the BMS board in the order of J1, J2,J3, finally reconnect
the positive power cable.
Figure 30
Figure 31
2.13 Use zip ties to thread through the holes on both sides of the battery pack,
secure the wiring harness, and insert 4 screws to fix the crossbeam.
Figure 32
Figure 33
2.14 Install the cover plate and tighten the 14 screws with an electric screwdriver.
Figure 34 Figure 36
Figure 35
Documents / Resources
![]() |
Pytes E-BOX 48100R-C Solar Storage System [pdf] Instructions E-BOX 48100R-C Solar Storage System, E-BOX 48100R-C, Solar Storage System, Storage System |