eBoost 16 Scalable Energy Storage System
Product Information
Specifications
- Product Name: eBoost 16
- Manufacturer: Fortress Power, LLC
- Warranty: Proper system configuration required for
warranty
Product Usage Instructions
1. Introduction
Before installing the eBoost 16, ensure that the system
configuration is verified. Warranty support is contingent on a
proper system design. Always refer to the latest installation
manual for updated information.
2. Product Specifications and System Design
Review the datasheet for detailed product specifications. Proper
system sizing is essential for optimal performance.
3. Safety
Follow safety guidelines provided in the installation manual to
prevent accidents or damage during installation or use.
4. Unboxing Check List
Check the contents of the package, including the eBoost Battery
and eBoost eWay if sold separately, against the provided
checklist.
5. Battery Specifications
Refer to the dimensions and definitions section for specific
details about the eBoost Battery and eBoost eWay (if sold
separately).
FAQ
Q: What should I do if I encounter issues during
installation?
A: If you face any challenges during installation, refer to the
troubleshooting section of the installation manual or contact
customer support for assistance.
eBoost 16
INSTALLATION MANUAL
Important: Verify the system configuration before installing. A proper system design is required for warranty purposes. Improper system configuration will void the warranty.
Always refer to the latest installation manual for the most up-to-date information. Information subject to change without notice.
2025 Fortress Power, LLC. All rights reserved.
Contents
1. ABBREVIATIONS ……………………………………………………………………………………………………………………………….4
2. CHANGE LOG …………………………………………………………………………………………………………………………………..5
3. INTRODUCTION ………………………………………………………………………………………………………………………………..5
3.1 ABOUT FORTRESS POWER………………………………………………………………………………………………………………………. 5 3.2 WARRANTY SUPPORT……………………………………………………………………………………………………………………………. 5
4. EBOOST INTRODUCTION…………………………………………………………………………………………………………………….6
5. PRODUCT SPECIFICATIONS AND SYSTEM DESIGN …………………………………………………………………………………..7
5.1 DATASHEET………………………………………………………………………………………………………………………………………. 7 5.2 SYSTEM SIZING ………………………………………………………………………………………………………………………………….. 8
6. SAFETY……………………………………………………………………………………………………………………………………………9
6.1 SYMBOLS ………………………………………………………………………………………………………………………………………… 9 6.2 SAFETY PRECAUTIONS AND INSTRUCTIONS ……………………………………………………………………………………………………11 6.3 TEMPERATURE CONSIDERATIONS………………………………………………………………………………………………………………12 6.4 TRANSPORTATIONANDHANDLING ……………………………………………………………………………………………………………..12 6.5 RESPONSETOEMERGENCY SITUATIONS ……………………………………………………………………………………………………….12 6.6 STORAGE…………………………………………………………………………………………………………………………………………13 6.7 TOOLS & MATERIALS ……………………………………………………………………………………………………………………………13
7. UNBOXING CHECK LIST …………………………………………………………………………………………………………………… 14
7.1 EBOOST BATTERY ……………………………………………………………………………………………………………………………….14 7.2 EBOOST EWAY (SOLD SEPARATELY) ……………………………………………………………………………………………………………14
8. BATTERY SPECIFICATIONS ……………………………………………………………………………………………………………….. 15
8.1 DIMENSIONS AND DEFINITIONS ………………………………………………………………………………………………………………..15 8.1.1 eBoost Battery …………………………………………………………………………………………………………………………15 8.1.2 eBoost eWay(Sold separately) …………………………………………………………………………………………………….16
8.2 COMMUNICATION……………………………………………………………………………………………………………………………….18 8.2.1 LED Status Definition…………………………………………………………………………………………………………………18 8.2.2 Communication Board ………………………………………………………………………………………………………………19 8.2.3 Inverter Communication Protocol ………………………………………………………………………………………………..19
9. SPACING REQUIREMENT …………………………………………………………………………………………………………………. 20
9.1 MINIMUM SPACING REQUIREMENTS ……………………………………………………………………………………………………………20 9.2 ACCEPTABLE BUT NOT LIMITED INSTALLATION CONFIGURATIONS ……………………………………………………………………………20 9.3 UNACCEPTABLE CONFIGURATIONS…………………………………………………………………………………………………………….23 9.4 MAXIMUM WALL HANGED HEIGHT REQUIREMENTS ………………………………………………………………………………………24
10. INSTALLATION ……………………………………………………………………………………………………………………………. 27
10.1 PREINSTALLATION……………………………………………………………………………………………………………………………….27 10.2 MECHANICAL INSTALLATION……………………………………………………………………………………………………………………28
10.2.1 Floor Standing installation. …………………………………………………………………………………………………………28 10.2.2 Floor Standing installation (Front Battery Paralleling) ……………………………………………………………………….36 10.2.3 Connection Overview ………………………………………………………………………………………………………………..38
11. COMMISSIONING…………………………………………………………………………………………………………………………40
COMMISSIONING MULTIPLE EBOOST BATTERIES INPARALLEL …………………………………………………………………………………………..40
12. SETTINGS ………………………………………………………………………………………………………………………………….. 41
12.1 AMPERAGE SETTINGS……………………………………………………………………………………………………………………………41 12.2 CHARGING VOLTAGE: …………………………………………………………………………………………………………………………..41
12.2.1 Low battery cut-off voltage:…………………………………………………………………………………………………………41
FORTRESS POWER LLC
EBM-PV20250824
2
12.2.2 12.2.3 12.2.4
Charging and Discharging Amperage …………………………………………………………………………………………….41 Charging Notes…………………………………………………………………………………………………………………………41 Discharging Notes …………………………………………………………………………………………………………………….42
13. DECOMMISSIONING ……………………………………………………………………………………………………………………. 42
13.1 KEY POINTS SUMMARY ………………………………………………………………………………………………………………………….42 13.2 HEATING ELEMENT OPERATION ………………………………………………………………………………………………………………..43
14. CONTACT INFORMATION ………………………………………………………………………………………………………………. 44
FORTRESS POWER LLC
EBM-PV20250824
3
1. ABBREVIATIONS
A = Amperes AC = Alternating Current Ah = Amperes hour(s) AWG = American Wire Gauge BAT = Battery BMS = Battery Management System CAN = Controller Area Network CC = Constant Current (Bulk) CCV = Closed Circuit Voltage °C = Degrees Celsius CT = Current Transformer CV = Constant Voltage (Absorption) DC = Direct Current ESS = Energy Storage System EOL = End of Life °F = Degrees Fahrenheit HV = High Voltage HVCO = High Voltage Cut-Off I/O = Input or Output ISC = Short Circuit Current IP-Ingress Protection in = Inches lb. = Pounds LED = Light Emitting Diode LFCO = Low Voltage Cut-Off LFP = Lithium Ferro Phosphate LN1 = AC Line 1 LN2 = AC Line 2 LV = Low Voltage
m = Meters mA = milliamperes mV = millivolts N = Neutral NEC = National Electric Code NEMA = The National Electrical Manufacturers Association NFPA = National Fire Protection Association NO = Normally Open NC = Normally Closed OCV = Open Loop Voltage OSHA = Occupational Safety and Health Administration OT = Over Temperature OV = Over Voltage PE = Protective Earth (Ground) PV = Photovoltaic R = Electrical Resistance (Ohms) RS485 = Recommended Standard 485 SOC = State of Charge SOC = State of Health UT = Under Temperature UV = Under Voltage V = Voltage VAC = Volts Alternating Current VDC = Volts Direct Current VPP = Virtual Power Plant W = Watts (Power)
FORTRESS POWER LLC
EBM-PV20250824
4
2. CHANGE LOG
VERSION
CHANGE DESCRIPTION
3. INTRODUCTION
3.1 ABOUT FORTRESS POWER Our mission is to provide compact, user-friendly, and affordable energy storage solutions using the latest technology for all homes and businesses. Fortress Power solar energy storage batteries can easily integrate with new and existing PV systems and work with a wide range of existing inverter and charge controller manufacturers for ease in system design.
Contact Information
Corporate Headquarter Address: 2010 Cabot Blvd West, STE L Langhorne, PA 19047 United States
Website: www.fortresspower.com Email: sales@fortresspower.com Phone: US: 877-497-6937
LATAM: 215-710-8960
3.2 WARRANTY SUPPORT Unless otherwise submitting a Fortress warranty through the Guardian hub, please submit your eBoost warranty here: https://fortresspower.com/warranty Beyond this product manual, you may also find our inverter guides useful to system installation and commissioning: https://support.fortresspower.com/portal/en/kb/inverter-guides
Beyond that, please find additional resources within our Support Portal https://support.fortresspower.com/portal/en/kb
· Create a support ticket. · Product Manuals · Firmware Updates · Warranty Submittal · System Design · Application Notes · Scheduled Meetings · Accessories
FORTRESS POWER LLC
EBM-PV20250824
5
4. EBOOST INTRODUCTION
The eBoost Battery is an advanced energy storage solution designed to cater to both residential and commercial energy needs. This battery is manufactured by Fortress Power, known for its innovative approach to providing reliable and efficient energy storage solutions.
The eBoost battery is available in various configurations to build into DC ESS system, including 16 kWh, and 32 kWh options and scalable to 256kWh, making it a solution that can be tailored to different energy requirements. The nominal voltage of the battery is 51.2V and can operate within a voltage range of 41.6V to 57.6V, offering flexibility in various applications.
Technology and Features:
Cell Type: The eBoost battery uses Top Tier Grade A Prismatic LFP (Lithium Iron Phosphate) cells, which are known for their safety, long life, and stability.
Scalability: The battery system can be expanded by adding multiple units in parallel, with a maximum of 16 units, depending on the configuration. This makes it suitable for large-scale energy storage needs.
Communication: It supports RS485, Wi-Fi, and CAN communication protocols, enabling integration with various energy management systems and monitoring tools.
Ingress Protection: With an IP65 rating, the eBoost battery is highly resistant to dust and water, IP65 making it suitable for both indoor and outdoor installations.
Included Heating Elements: Integrated heaters, ensuring optimal performance and longevity in colder climates. These heaters maintain the battery’s internal temperature within an optimal range, preventing performance degradation caused by low temperatures. This feature is especially valuable during winter months, ensuring consistent energy storage and reliable power supply even in extreme weather conditions.
Mounting Options: The battery has versatile mounting options, including ground-mount, floorstanding, and wall-mounted configurations. Benefits and Applications The eBoost battery is designed to provide numerous benefits across various applications: 1. Energy Independence and Off-Grid: It allows homeowners and businesses to store excess energy generated from renewable sources like solar panels, reducing reliance on the grid and providing energy independence. 2. Backup Power: The battery provides a reliable source of backup power during grid outages, ensuring continuous operation of essential systems. 3. Peak Shaving: By storing energy during off-peak hours and discharging during peak demand, the eBoost battery helps in reducing electricity costs and increasing your return of investment. 4. Grid Export, Net Metering and VPP: Allow the eBoost to discharge/charge energy to and from the grid during high demand hours and getting credit/money on your energy bill allowing savings and bankability. 5. Safety and Longevity: With a cycle life of 8000 cycles at 70% End of Life (EOL), and a 10-year warranty the eBoost battery offers long-term reliability, providing peace of mind.
FORTRESS POWER LLC
EBM-PV20250824
6
5. PRODUCT SPECIFICATIONS AND SYSTEM DESIGN
5.1 DATASHEET
FORTRESS POWER LLC
EBM-PV20250824
7
5.2 SYSTEM SIZING Please refer to our sizing guide and warranty letter for appropriate sizes between various inverter models and the eBoost. https://support.fortresspower.com/portal/en/kb/articles/minimum-battery-sizing . Under no circumstance should you install an inverter with charging capacity greater than 250A per eBoost even if you intend to limit the charge or discharge capacity of the inverter either manually or digitally.
INVERTER
FORTRESS POWER ENVY 8KW FORTRESS POWER ENVY 10KW FORTRESS POWER ENVY 12KW FORTRESS POWER ENVY DUO 21 FORTRESS POWER SOLO 6.5 KW FORTRESS POWER EDGEON DUO 9 FORTRESS POWER EDGEON DUO 15 SCHNEIDER ELECTRIC XW PRO 6848 SCHNEIDER ELECTRIC XW+ 6848 SCHNEIDER ELECTRIC XW+ 5548 SCHNEIDER ELECTRIC SW 4048 OUTBACK POWER RADIAN 8048A OUTBACK POWER RADIAN 4048A OUTBACK POWER VFXR 3648A OUTBACK POWER FXR 3048A SOL-ARK 5K SOL-ARK 8K SOL-ARK 12K SOL-ARK 15K STUDER INNOTEC AJ 400-48 STUDER INNOTEC AJ 700-48 STUDER INNOTEC XTS 1400-48 STUDER INNOTEC XTS 2600-48 STUDER INNOTEC XTS 4000-48 STUDER INNOTEC XTS 6000-48 STUDER INNOTEC XTS 8000-48 MAGNUM / SENSATA MS 4448 MAGNUM / SENSATA MS 4048 VICTRON ENERGY QUATTRO 48/3000/35 VICTRON ENERGY QUATTRO 48/5000/70 VICTRON ENERGY QUATTRO 48/10000/140 VICTRON ENERGY QUATTRO 48/15000/200
EBOOST 16 OPEN-LOOP 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1
1
1
EBOOST 16 CLOSED-LOOP
1 1 1 1 1 1 1 1 n/a n/a n/a n/a n/a — n/a 1 1 1 1 1 1 1 1 1 1 1 — — 1
1
1
1
FORTRESS POWER LLC
EBM-PV20250824
8
6. SAFETY
6.1 SYMBOLS
Risk of electrical shock, fire, or Damage
Important instructional note
FORTRESS POWER LLC
EBM-PV20250824
9
FORTRESS POWER LLC
EBM-PV20250824
10
6.2 SAFETY PRECAUTIONS AND INSTRUCTIONS Damage to the product may lead to a leakage of electrolyte or flammable gas. During installation of the battery, the utility grid and solar input must be disconnected from the Battery Pack wiring. Wiring must be carried out by qualified personnel. The battery pack contains no user serviceable parts. High voltage or current is present in the device. The electronics inside the Battery Pack are vulnerable to electrostatic discharge. Observe the following precautions:
Risks of explosion Do not subject the battery pack to strong impacts. Do not crush or puncture the battery pack. Do not dispose of the battery pack in a fire.
Risks of fire Do not expose the battery pack to temperatures more than 140°F (60°C). Do not place the battery pack near a heat source such as a fireplace or open flame Do not expose the battery pack to direct sunlight. Do not allow the battery connectors to touch conductive objects.
Risks of electric shock Do not disassemble the battery pack. Do not touch the battery pack with wet hands. Do not expose the battery pack to moisture or liquids. Keep the battery pack away from children and animals.
Risks of damage to the battery pack Do not allow the battery pack to come in contact with liquids. Do not subject the battery pack to high pressures. Do not place any objects on top of the battery pack.
IMPORTANT NOTE: Circuit Breakers, Disconnects and Fuses should be employed throughout the energy storage system and generation installation to isolate effectively and protect all components against faults, short circuits, polarity reversals or failure of any component in the installation. Fuses, breakers, wiring ratings and values should be determined by established standards and evaluated by certified electricians, licensed installers, and regional code authorities. The eBoost B a t t e r y Management System (BMS) alone will not protect the batteries from these extreme electrical events. Failure to adhere to proper installation protocol will void the warranty.
CAUTION! Verify polarity at all connections with a digital voltmeter before energizing the system. Reverse polarity at the battery terminals will void the warranty and destroy the batteries. Do not short circuit the batteries. Most batteries pose some risk of shock or sparking during the installation and initial wiring and connection process. Wearing insulated gloves, clothing and footwear and using electrically insulated tools are required when working with the eBoost. Cover or remove jewelry or conductive objects (metal bracelets, rings, belt buckles, metal snaps, zippers, etc.) when working with any electrical or mechanical device. Cover or restrain long hair and loose clothing when working with any electrical or mechanical device. CAUTION! Do not disassemble or modify the battery. If the battery housing is damaged, do not touch the exposed contents.
FORTRESS POWER LLC
EBM-PV20250824
11
6.3 TEMPERATURE CONSIDERATIONS
CAUTION! Do not attempt to charge the battery below -4 degrees F (-20 degrees C). Attempts to charge below these temperatures can adversely affect State of Health (SOH) and cycle life and will void the warranty; never charge battery if it is frozen; never charge a visibly damaged battery. Charging the battery near freezing should only be done with a low amperage external charger or closed-loop communication inverter unless the battery bank is heated. There is no need to heat the batteries above 50F.
Do not charge the battery when the ambient temperature is freezing or below. Discharge current at sub-freezing temperatures should also be significantly reduced.
CAUTION! Do Not Operate Fortress Lithium Batteries where average internal battery temperature exceed 30 °C / 86 °F over the life of the battery. Recommended operating parameters of charger/Inverters For 3,000 Cycles:
· Internal battery temperature range: 32 F to 120 F (0 °C to 49°C) without close-loop communication. · Bulk voltage and absorb voltage should be set to 55.2V if no battery-inverter communication is
available. Recommended operating parameters of charger/Inverters For 8,000+ Cycles:
· Operating temperature range: 50°F to 110°F (0°C to 60°C) per Fortress Power recommend charge and discharge inverter configuration.
6.4 TRANSPORTATION AND HANDLING · Do not knock, drop, puncture, or crush the battery. · Do not expose battery to flames, incinerate or direct sunlight. · Do not open the battery case or disassemble the battery. · Do not lift battery by the terminal cables. · Do not vibrate the battery. · Do not expose the battery to water or other fluids. · Do not expose battery to open flame. · Do not place the product nearby highly flammable materials, it may lead to fire or explosion in case of accident, Store at cool and dry place. · Do not store in greenhouses and storage areas for hay, straw, chaff, animal feed, fertilizers, vegetables, or fruit products. · Store the product on a flat surface; A ventilated area is strongly recommended for handling the product. · Store the product out of reach of children and animals. · Store the product where there is minimal dust and dirt in the area; do not transport battery upside down or with the terminals towards the ground. · Batteries must be discharged to 30% state of charge or 51.2V resting voltage before transporting.
6.5 RESPONSE TO EMERGENCY SITUATIONS · The battery pack consists of multiple batteries and a sophisticated Battery Management System that is designed to prevent hazards resulting from failures. However, Fortress Power cannot guarantee their absolute safety. Leaking Batteries: · If the battery pack leaks electrolyte, avoid contact with the leaking liquid or gas. If a person is exposed to the leaked substance, perform the actions described below immediately. · Inhalation: Evacuate the contaminated area and seek medical attention. · Contact with eyes: Rinse eyes with flowing water for 15 minutes and seek medical attention. · Contact with skin: Wash the affected area thoroughly with soap and water and seek medical attention. · Ingestion: Induce vomiting, and seek medical attention · Fire
FORTRESS POWER LLC
EBM-PV20250824
12
· In case of fire, make sure that an extinguisher is available near the battery pack. If possible, move the battery pack to a safe area before it catches fire.
Note: Fire extinguisher · Water, carbon dioxide, dry chemical powder and foam are the most effective means to extinguish a Lithium Ferrous Phosphate (LFP) battery fire. · Use an ABC Fire extinguisher, if the fire is not from battery and has not spread to it yet.
6.6 STORAGE
Store batteries away from direct sunlight and in locations with temperatures ranging between 0°C and 35°C (32°F to 95°F) to avoid exposure to high temperatures. · Turn off the battery during long-term storage to reduce the self-discharge rate, which is about 1%
when the SOC is above 20%. · Maintain a Relative Humidity (RH) level between 5% and 95% in a dry and clean indoor environment.
Prevent contact with corrosive materials and keep away from fire and heat sources. · For storage durations exceeding one month, ensure the battery’s State of Charge (SOC) is
maintained between 30% to 50%. It is crucial to charge and discharge the battery every six months to maintain health. · Regularly check the battery every 3 months to ensure the SOC remains above 20% (greater than 51.2V). If it falls below this level, charge the battery up to 51.8V before returning it to storage. · When placing systems into storage, set the SOC to 30~50% and periodically verify that it does not drop below 20%. If you expect the battery to be left unattended for extended periods, set a higher battery cutoff voltage as a precaution. This is particularly important if the power supply is critical, and the charging sources (like solar panels) may be obstructed by snow or dust. In such scenarios, installing a backup generator with an AutoStart feature is advisable. Note that the inverter and battery management system may impose a minor load on the battery, potentially depleting it over long durations without any charging sources. Following these guidelines will help ensure your battery’s longevity and reliability, even during extended storage periods. 6.7 TOOLS & MATERIALS The following tools and materials are required and are not included:
· OSHA approved personal protective equipment, Safety Shoes, Safety Glasses, Insulated Gloves, and Weightlifting Belt.
· Bendable Screwdriver extension · Metric hex socket set · Metric wrench set · Phillip and Flat Head Screwdriver Set. · Power Drill and wood or and concrete drill bit set · Hand Truck (Optional) · Positive and negative battery cables, we recommend copper cable starting at 3/0 for runs
of less than 10ft. Please refer to your adopted version of the National Electric Code or Local Authority Having Jurisdiction for more guidance (not included). · UL Battery Cable & Positive and Negative Terminal lugs. Note that the eWay ring terminal hole size is 3/8in. · Wire Stripper and Crimper (Up to 4/0)
FORTRESS POWER LLC
EBM-PV20250824
13
7. UNBOXING CHECK LIST
7.1 EBOOST BATTERY
A
eBoost Module x1
eBoost Template x1
G F
Battery-Battery Bracket x4
Battery-Wall Bracket x2
5x12mm Hex Bolt x5
M6*60mm expansion bolt x8
7.2EBOOST EWAY (SOLD SEPARATELY)
M8*60mm Stainless Steel Wood Screw x8
M4x12mm Hex Bolt x11
D
eBoost eWay
M6x12mm x4 FORTRESS POWER LLC
Cable Separator Manual x1 x1
Communication Cables x3
EBM-PV20250824
14
8. BATTERY SPECIFICATIONS
8.1 DIMENSIONS AND DEFINITIONS 8.1.1 eBoost Battery
All dimensions are depicted in inches.
TOP SIDE
FRONT SIDE FORTRESS POWER LLC
LEFT SIDE
BACK SIDE
EBM-PV20250824
15
8.1.2 eBoost eWay(SOLD SEPARATELY) All dimensions are depicted in inches. Each eBoost battery requires either an eBoost eWay or eBoost eWay Lite to operate. For the
latest details and updates, please visit: https://www.fortresspower.com/products/eboost/ LEFT SIDE
TOP SIDE
FRONT SIDE (Closed)
BACK SIDE
FRONT SIDE (Opened)
FORTRESS POWER LLC
EBM-PV20250824
16
Cable requirements
Inverter
Cable Size
ENVY 12kW
Up to 4/0
ENVY 10kW
Up to 3/0
ENVY 8kW
Up to 3/0
eWay -eWay Up to 4/0
Voltage 600 600 600 600
Qty 1 pair per eWay 1 pair per eWay 1 pair per eWay 1-2 pair per eWay
eWay Busbar Torque Specifications 6.2lbf-ft (8.5Nm) 6.2lbf-ft (8.5Nm) 6.2lbf-ft (8.5Nm) 7.37-8.85lbf-ft (10~12) Nm
KNOCKOUT HOLE SIZE (IN) A 0.87 B 1.11 C 1.38 D 1.73 E 2.00 F 2.48
CONDUIT SIZE (IN) ½ ¾ 1.00 1 ¼ 1 ½ 2.00
8.1.2.1 eWay Sections
Power Switch Allows user to power on the eBoost by press and hold the power button for 1 second. At the same time provide a method to select the inverter protocol by holding the push button for 2 seconds. Press and hold for 10 seconds to power off.
E-Stop Feature A safe means of disconnecting the battery from a 48V HYBRID inverter and disabling battery voltage output. Lockout hole measures 0.24″. When paired with the Envy True 12kW/10kW/8kW it allows the option of providing complete ESS disconnection when enabling Rapid Shut Down (RSD) allowing first responders to safely mitigate any hazardous event within the property.
Guardian Antenna Port Allows user to extend the Guardian WIFI capability. Use the antenna included with the Guardian.
Backlight Status Indicator Serves to indicate Normal battery operation or a Fault. When White, the system is in Normal function, When Yellow there is a fault present in the battery.
Normal
Fault
FORTRESS POWER LLC
EBM-PV20250824
17
8.2 COMMUNICATION 8.2.1 LED STATUS DEFINITION
8
7
5
6 4
7 3
Table Legend
Solid
2
Quick Flash
Slow Flash
1
OPERATING STATUS POWER ON CHARGING
DISCHARGING
CHARGE DISCHARGE
FAULT ADDRESSING AND COMMUNICATION
PROTECTION/ ALARM/ NORMAL
Alarm normal Overcharge protection Over-temperature, undertemperature, over-current protection Alarm normal Over-temperature, undertemperature, over-current protection Over-discharge protection, acquisition failure (temperature or voltage), short circuit, reverse polarity protection succeed
fail
SOC%
>95 75~95
50~75
25~50
0~25 0
>95 75~95 50~75 25~50 0~25
0
LED5
off off off off off
off off off off off
LED4
off off off off
off off off off
LED3 LED2 LED1 Boot in 5seconds
off
off
off
off
off
off
off
off
off
off
off
off
The corresponding SOC percentage is illuminated
LED6 off
LED7 LED8
off off
FORTRESS POWER LLC
EBM-PV20250824
18
8.2.2 COMMUNICATION BOARD
Terminator Do not remove for Single Battery installation
Common RJ45 ports Battery-Inverter nor Battery-Battery
Cable needs to be modified.
8.2.2.1
PIN 1 2 3 4 5 6 7 8
Port Definition
COLOR (B FORMAT0 White-Orange Orange White-Green Blue White-Blue Green White-Brown Brown
ASSIGNMENT Can1_H Can1_L Can2_G Can2_H Can2_L RS485G1 RS485A1 RS485B1
FUNCTION BAT-BAT communication Guardian CAN Communication
n/a PCS CAN communication
n/a PCS 485 Communication
8.2.3 INVERTER COMMUNICATION PROTOCOL To select the inverter protocol to achieve closed loop communication, you must press and hold the power button for 5 seconds, then release it. Immediately the LED 6&7 will start flashing following the current inverter protocol status. In this stage, press the button once until you select the correct protocol as shown in the images below.
Once selected wait for less than 10seconds until the LED indicator returns to normal operation. You must do this while all batteries in the field.
Hold 2s
FORTRESS POWER LLC
FORTRESS POWER /SOLARK/APSYSTEMS/SCHNEIDER
VICTRON
GROWATT
EBM-PV20250824
19
9. SPACING REQUIREMENT
9.1MINIMUM SPACING REQUIREMENTS
*The placement of the Envy inverter is for
reference only. Please refer to the Envy
Manual for more details.
8in
may have a tolereance of +-0.20 inches
6in
8in
8in
8in
6in
9.2 ACCEPTABLE BUT NOT LIMITED INSTALLATION CONFIGURATIONS Floor Mounted
Option 1
Option 2
Option 3
FORTRESS POWER LLC
EBM-PV20250824
20
Envy 12k/Envy Duo 21 right side Installation measurements (Floor Mounted)
Floor
FORTRESS POWER LLC
EBM-PV20250824
21
Envy 8k/10k right side Installation measurements (Floor Mounted)
Floor
FORTRESS POWER LLC
EBM-PV20250824
22
Wall Hanged Option 1
Option 2
Warning! Make sure that the wall is structurally sound and that it may hold a heavy load. Failure to do so may result in injury or death.
This configuration includes the option of bolting the included eBoost wall bracket in the wall. Make sure the Power Switch or the PV DC disconnect from the Inverter does not surpass 6’7″ per NEC Code.
9.3UNACCEPTABLE CONFIGURATIONS
One eBoost 16kWh with two Envy inverters /Two front mounted
batteries
Figure A
Figure B
Notes
Figure A. The eBoost maximum discharge current is 250A continuous. Each Envy 8k/10k/12k/Envy 21 Duo maximum continuous output is 167A/210A/ 250A/250A Respectively Use always 1:1 ratio when paring an eBoost with any model of the Envy inverters.
FORTRESS POWER LLC
EBM-PV20250824
Figure B. Do not mount a battery in front of another eBoost when hanging the eBoost on the wall as this can cause damage to both the wall and the battery.
23
9.4
MAXIMUM WALL HANGED HEIGHT REQUIREMENTS
Consider NEC CODE SECTION 404.8(A) when wall mounting the eBoost. Please follow the guidelines
below. DO NOT INSTALL the battery system above the stipulated Heigh. The height reference is taken
from the highest disconnect per the NEC code
Wall hanged with Envy 12k/Envy Duo 21k (Measurement in inches)
Wall hanged with Envy 8k/10k (Measurement in inches)
Floor FORTRESS POWER LLC
Floor
EBM-PV20250824
24
Envy 12k/Envy Duo 21 right side Installation measurements (Wall hanged)
Floor
FORTRESS POWER LLC
EBM-PV20250824
25
Envy 8k/10k right side Installation measurements (Wall hanged)
Floor
FORTRESS POWER LLC
EBM-PV20250824
26
10. INSTALLATION
10.1 PREINSTALLATION 1. Select the Mounting Location: · Ensure the surface where the mounting base will be installed is clean, dry, and level. · Measure and mark the mounting points according to the dimensions of the base. · The eBoost Battery should not be installed in direct exposure to the sun (South facing with reference to the Sun). 2. Safety Considerations: · Wear safety glasses and gloves during installation to protect against debris and sharp edges. · Ensure the installation area is free from obstructions and that there is adequate lighting. · Clear the area where the battery module will be installed. 3. Weight Considerations Follow OSHA standards when installing this battery. Each battery module weighs 308.lbs including the eWay. · Ensure the floor is level and capable of supporting the weight of the battery. · Use a lifting machine when wall mounting the battery. Optionally, the battery module may be wheeled in place of the installation site and anchored to the wall with L-SHAPED brackets
We highly recommend using a hand truck or other machinery to move batteries from the transport vehicle to the installation site. Make sure that the arrows on the box are facing upwards before opening. This will facilitate installation procedure moving forward. Open the box, remove protective foams, plastic bag, contents and slide the battery outwards.
Warning. Please use caution when rolling the battery in the width direction to prevent it from tipping over.
FORTRESS POWER LLC
EBM-PV20250824
27
10.2 MECHANICAL INSTALLATION 10.2.1 FLOOR STANDING INSTALLATION.
FORTRESS POWER LLC
EBM-PV20250824
28
Danger Floor must be flat and even. This configuration is not allowed on highly uneven surfaces. If so, consider the following Options:
1. Resurfacing the floor 2. Install the system with wall mounted configuration. Instructions: 1. Clean Area · Clean Area and remove any debris, tools from the floor in the installation area. · Ensure the installation area is well lit and free from obstructions. 2. Attach the Brackets a. Use the provided hardware to attach the brackets to the mounting base. b. Align and screw the two wall fitted brackets to the designated positions. c. Tighten the hardware, place the battery against the wall and mark the holes to be drilled.
FORTRESS POWER LLC
EBM-PV20250824
29
Warning. Failure to do this procedure may result in battery installation misalignment and improper battery to battery or battery to inverter connection.
3. Align the Template a. Position the mounting template (cartonboard) against the wall and rest the bottom to the L-shaped
brackets. · Use a level to ensure that the template is properly aligned vertically and horizontally.Make minor
adjustments to the position of the template as necessary. · Using a marking tool, mark the locations of the mounting holes on the wall or surface where the
inverter will be installed.
Front side
Back side for reference
· Identify with an x the spot in which the mounting holes must be drilled. Remove the template and
drill holes. If mounting on a concrete wall, use a drill with a masonry bit to create holes for anchors.
FORTRESS POWER LLC
EBM-PV20250824
30
4. Secure the eBoost eWay to the eBoost module
D x4
5. Remove the eBoost eWay top cover.
Make sure to leave the rubber seal in place for outdoor installation.
FORTRESS POWER LLC
EBM-PV20250824
31
Battery Installation with Envy on top
7. Secure the Envy wall bracket and hang the inverter.
6. Remove the bottom cover of the Envy inverter
or
FORTRESS POWER LLC
EBM-PV20250824
32
8. Align the Inverter and secure the Envy with the eway to create a proper seal.
9. Finally Secure the Envy with the inlcuded L-shaped brackets.
or
FORTRESS POWER LLC
EBM-PV20250824
33
10. Connect the Electrical and communications cables between the eWay and the Envy inverter
Guardian Cable
RJ45 Terminator
Bat-Inv Cable
Bat-Inv Cable with Envy adapter
FORTRESS POWER LLC
EBM-PV20250824
34
11. Finally, secure the batteries with the red knobs on the battery legs. Operation of the Red Leveling Knobs Each battery support leg is equipped with an integrated caster wheel for mobility and a red twist-style leveling knob for height adjustment and stabilization.
1. Mobility Mode 2. When the red knob is rotated clockwise, the adjustable foot retracts upward, transferring the load
onto the caster wheels. This allows the battery cabinet to be easily moved or repositioned. 3. Stabilization Mode 4. By rotating the red knob clockwise, the adjustable foot extends downward until it makes firm contact
with the floor. Continued turning raises the cabinet slightly off the caster wheels, shifting the weight fully onto the stationary legs. This prevents any rolling or unwanted movement. 5. Fine Height Adjustment The threaded mechanism inside the leg allows for precise height control. This ensures the cabinet can be leveled on uneven floors, improving stability and reducing mechanical stress on the frame.
FORTRESS POWER LLC
EBM-PV20250824
35
10.2.2 FLOOR STANDING INSTALLATION (FRONT BATTERY PARALLELING)
FORTRESS POWER LLC
EBM-PV20250824
36
Remove the Battery wall mounting rack of the second eBoost module.
Attach the combining battery to battery brackets and join second battery to the primary. You may liquid tight conduit To join one eWay with another
FORTRESS POWER LLC
A
EBM-PV20250824
37
10.2.3 CONNECTION OVERVIEW One eBoost Battery and Envy Inverter Electrical Connection Overview
Envy 12kW/10kW/8kW Inverter
Built-in Connections
Required Installation
Unused Ports
LED – PCS Cable
Guardian/Gateway Optional
Primary Battery
Terminator
LED-GATEWAY/GUARDIAN Cable Separate Normally Closed RSD Button
STOP
Included Lever Nut Connector
RSD
eBoost 16kWh
Ground
When operating with one eWay, keep the terminator plug placed in its original position.
Plug one side of the BAT-PCS cable into the RJ45 ports of the Communication board and
the other side into the inverter BAT COM port. RSD features include complete system shut
off by disconnecting the batteries voltage output, Disabling PV Voltage, and Load Output per
NEC 2023 Code. To achieve this, Follow the connections in the above image.
FORTRESS POWER LLC
EBM-PV20250824
Legend
Positive
Negative
Protective Earth Communication
38
Two or more eBoost Battery and Envy Inverter Electrical Connection Overview
Built-in Connections
Required Installation
Unused Ports
Guardian/Gateway Optional
Primary Battery
LED-GATEWAY/GUARDIAN Cable Separate Normally Closed RSD Button
STOP
LED – PCS Cable
Secondary Battery
Terminator Terminator
Bat-Bat Comm Cable
Envy 12kW/10kW/8kW Inverter
Included Lever Nut Connector
eBoost 16kWh
eBoost 16kWh
RSD
Ground
Remove the terminator from the first eWay and place battery to battery communication. Make sure that the secondary eWay keeps the terminator connected in its original port. Repeat this process with batteries connected in parallel by connecting the Battery -Battery RJ45 Cables in daisy chain sequence starting with the first battery to the last. Place the Resistive RJ45 plug into the terminator Port of the last secondary battery following chronological sequence starting with the Primary Battery. For More details of parameter settings, please refer to the Fortress Power Envy 12kW/10kW/8kW Manual.
Legend
Positive
Negative
Protective Earth Communication
FORTRESS POWER LLC
EBM-PV20250824
39
The Guardian Connections are already connected. You use the 120V AC-DC plug for resiliency, but it is not required.
11. COMMISSIONING
For Commissioning batteries where multiple eWay are in parallel, please go to the “Commissioning in Parallel” section.
1. Turn the battery breaker inside the inverter. See below. 2. Turn the RSD Switch to the ON position 3. Verify by applying a voltmeter at the eWay internal busbar. 4. Press the Power button. Make sure to select the correct inverter protocol by holding the power
button for 5 seconds after initiating the battery.
1
2
3
5. Make sure that the Guardian is powered on and follow the Quick Start Guide starting with step 6.
6. Scan the QRCODE on cover page of the manual to download the Guardian APP.
Commissioning multiple eBoost batteries in Parallel For a maximum battery bank size of 256kWH, up to 16 eBoost 16kWh batteries can be connected in parallel. All wires should be an appropriate gauge and constructed to manage the loads that will be placed upon them. A qualified installer should understand this and must adhere to industry standards and published electrical guidelines. The storage capacity and total permissible charging and discharging amperage are increased by parallel arrangement. The overall voltage is not changed. Instead, the available amperage from the system is increased with each additional parallel battery. Double Check if batterybattery communication cable is connected and secured. Please follow this procedure to commission eBoost 16kWh batteries in parallel:
1. Turn all DC Breakers on the ON position (Hybrid Inverter, Charger Controllers)
2. Turn the RSD Switch to the ON position as shown in above figure 2. 3. Turn on the first battery’s Power Switch (the first battery is the one communicating with inverters). Do
not turn on the power button of the other batteries. If all cables are correctly connected, LED will
commence booting sequence, and the other batteries will engage by energizing.
4. Measure Voltage inside the eWay busbar to confirm.
5. Press the Power button. Make sure to select the correct inverter protocol by holding the power
FORTRESS POWER LLC
EBM-PV20250824
40
button for 5 seconds after initiating the battery. Verify by applying a voltmeter at the eWay internal busbar. For inverter-specific settings, visit https://www.fortresspower.com/support for the most recent integration manual for each specific inverter brand.
12. SETTINGS
12.1 AMPERAGE SETTINGS
IMPORTANT The Hybrid Inverters need to be digitally programmed to comply with correct amperage and voltage stated elsewhere in this guide. Special communication cables may need to be field made. If using battery-inverter communication, please consult our inverter guides: https://www.fortresspower.com/inverter-guides
· Do not use unqualified equipment for charging and discharging, please follow the correct instructions for use.
· Do not discharge the battery when the battery is depleted. · Do not charge or discharge batteries that are hot, deformed, or leaking. · The output cable length of the battery should be less than 10 meters long. · Do not connect a power and load that exceeds the power level to the two ends of the
battery. · Do not mix different batteries. Different manufacturers, chemistry, models, and lifespans
cannot be paralleled.
12.2 CHARGING VOLTAGE: Without battery-inverter communication, eBoost batteries should be charged at 54.4V. With battery-inverter communication, eBoost batteries this voltage may be increased according to the published inverter guides: https://www.fortresspower.com/inverter-guides
12.2.1 LOW BATTERY CUT-OFF VOLTAGE: The eBoost battery is below a 20% state-of-charge when its resting voltage is below 51.4V In order to keep the inverter and battery system powered up while waiting for a charge, this is the recommended low battery cut-off voltage. It is appropriate to lower this to 51V if using a generator or grid charge to automatically maintain or charge the battery at 51.4V or above. Many older battery inverters cannot program a low battery cut-out voltage above 48V. The eBoost has a safety feature that will cut around this voltage level if necessary. If you regularly deep discharge the eBoost down to 48V, please increase your battery size or upgrade your inverter to maintain warranty compliance.
12.2.2 CHARGING AND DISCHARGING AMPERAGE
Precautions should be taken when adding charging sources which are not controlled by a single inverter or control system (Ex. using different manufacturer’s DC charge controllers and inverters, solar + wind inverters, EV chargers etc.) to ensure the total system charges or discharges the battery within its specification. Controllers do not charge the battery concurrently, when and if their combined charge current totals are greater than the charge current of the combined battery bank.
Take additional extra precautions when using wind power to charge the battery, or if the inverter and
charge controllers are not the same manufacturer.
12.2.3 CHARGING NOTES
If the following scenarios occur, the battery must be charged before use, otherwise the battery damage
caused is not covered by the warranty:
FORTRESS POWER LLC
EBM-PV20250824
41
· The battery has not been powered on or otherwise discharged without any charging sources available.
· The battery has been turned off for a long period during transportation or storage. · The battery has been deeply discharged and reached under-voltage protection status. · The battery has been aggressively recharged during deep discharge conditions through bypassing
the BMS. · The battery has been recharged during freezing condition through bypassing the BMS. · Bypassing the BMS is not allowed without logging a support ticket with Fortress Technical Support at
https://support.fortresspower.com 12.2.4 DISCHARGING NOTES · Do not regularly discharge battery below 51V, 20% SoC. This capacity should be reserved for power
outages and idling the load until a charging source can be applied. · Do not discharge battery at rates greater than maximum continuous current.
Parameter set up guide for Charger/Inverter Unless explicitly stated in Fortress inverter guides or contrary to the above charging amperages and voltages, charge controller and inverter settings must be programmed per the manufacturer’s recommendations. Consult the manufacturer’s manuals and/or access technical support. To achieve extended life cycles and to comply with the Warranty, the following guidelines should be followed:
Understanding Charge Stage
1. Bulk Charge: Charge at Constant Current (CC) to Bulk/Absorb Voltage. 2. Absorption Charge: Maintain Constant Bulk/Absorb Voltage (CV). Note – if the battery is not
reaching 100% capacity, it is allowable to adjust this voltage from 54.4V to 55V. Any higher charging voltage must be explicitly stated a Fortress inverter guide specific to that brand of inverter. 3. Unless otherwise stated in a Fortress inverter guide, keep float voltages at 54.4V or less to maintain warranty compliance. While most end users will want to enable a float mode of operation if available to keep batteries at 100%, it is healthier for the battery only to use the bulk/absorb cycle – which allows the batteries to exercise daily.
13. DECOMMISSIONING
At the End of Cycle Life retained capacity is equivalent to 70% Year 1 Capacity. eBoost contains scrap material useful to recycling. Dispose of the battery at a local recycling center or ship back to Fortress Power. Transport end-of-life batteries at 30% state-of-charge, <52V resting. 13.1 KEY POINTS SUMMARY
1. Each Fortress Lithium Battery contains circuitry that protects the Lithium Ferro Phosphate cells from overcharging, over-discharging, and excessive load amperage. If the values specified are exceeded, the battery will enter a protective shut down state. In some cases, this may result in the need to reinitialize an inverter charger or other pieces of equipment in the installation. In other cases, the inverter’s system settings may be saved within the inverter memory storage and will not need to be reset. This is not an absolute standard but is common among most inverter chargers. Check your inverter manufacturer specifications.
2. Although each Fortress Lithium Battery contains circuitry that protects the Lithium Ferro Phosphate cells from overcharging, over-discharging and excessive load amperage, Fortress Lithium Batteries must always be installed with a charge controller and appropriate settings to protect the batteries from open PV and other high voltage sources. Fortress Lithium Batteries alone will not protect from extreme electrical phenomena.
3. GRID TIED SYSTEMS: Once the Fortress Lithium Battery has been installed, turn on the entire system to test. Once testing has been completed, please disconnect the batteries from the load center until
FORTRESS POWER LLC
EBM-PV20250824
42
your local Utility Inspector is ready to turn on the entire system. The charge controllers and inverter monitoring systems can drain the Fortress Lithium Batteries over an extended period when the entire system is not fully operational due to the electrical draw of the system components. 4. OFF GRID SYSTEMS: Do not connect the Fortress Lithium Batteries until the entire system is ready to turn on and is fully operational.
13.2 HEATING ELEMENT OPERATION
TEMPERATURE -4°F (-20°C) -4°F (-20°C) <TMIN32° F(0°C) 32°F(0°C) <TMIN41°F(5°C),
TMIN>41°F(5°C)
VMIN<45V OR SOC<20%
HEATING ELEMENT STATUS (125W) OFF ON ON (Stop Heating @ Tmin>50°F (10 °C) OFF OFF
CHARGE/DISCHARGE STATUS OFF/OFF OFF/ON ON/ON ON/ON/ ON/ON
The integrated heaters are energy-efficient, activating only when necessary, to preserve battery life and enhance overall system efficiency.
FORTRESS POWER LLC
EBM-PV20250824
43
14. CONTACT INFORMATION
For Technical Support Please Contact us at Tech-Support Contact Information
Useful Links
·
Phone:
Tech Support 877-497-6937
Tech Support (Spanish) 215-710-8960
·
Support Tickets: https://www.fortresspower.com/support/
·
Warranty Submittal: https://www.fortresspower.com/warranty/
FORTRESS POWER LLC
EBM-PV20250824
44
Documents / Resources
![]() |
Fortress Power eBoost 16 Scalable Energy Storage System [pdf] Installation Guide eBoost 16 Scalable Energy Storage System, eBoost 16, Scalable Energy Storage System, Storage System, System |