Andersen A3 Installer Installation Guide

Andersen-A3-Installer-logo

Andersen A3 Installer

Andersen-A3-Installer-product

Overview

The Andersen A3 charging point is an equipment intended to be installed and commissioned by a qualified electrician, following relevant UK electrical regulations and the manual’s installation and commissioning steps to ensure safe operation.

Specifications

Rated power 7.2kW (1-phase)
Rated supply voltage 230V AC, single phase
Voltage tolerance/frequency +10% / -6%, 50Hz
Rated current 32A
Charging mode/protocol Mode 3 (IEC 61851-1 compliant communication protocol)
Connector type Type tethered cable, IEC 62196-2 compliant
Ingress protection/enclosure IP65 – Type 2 cable, IP44
Operating temperature/humidity -25°C to +40°C; up to 95% RH non-condensing
 Standby power 10 Watts
Earth leakage protection 6mA DC protection (EN 62955), 30mA AC
Compliance (listed) RED 2014/53/EU, LVD 2014/35/EU, EMC 2014/30/EU, EN 61851-1:2019, EN 62196, EN 62955:2018, RoHS 2011/65/EU, WEEE 2012/19/EU, CE and UKCA Certified
Wi‑Fi 802.11 b/g/n support; 802.11 n (2.4 GHz); up to 150 Mbps
Bluetooth BLE 5 (set-up only)
Supported mobile devices Apple iOS / Android
Internet/security (listed) Remote software enabled charge point locking; 128-bit data SSL AES encryption for smart connectivity
Dimensions (unboxed) 430 x 310 x 148 mm
Installed mounting height 0.75m to 1.2m from ground level
CT sensor cable Maximum extended length 30m unshielded CAT5/6 or 50m shielded CAT6; any shielding suitably earthed
Recommended upstream protection (listed) 40A RCBO (BSO EN 61009) or Type A RCD/RCCB (BSO EN 61008) + 40A MCB (BSO EN 60898) – B curve
Supply terminal capacity 0-120A / 25mm2 maximum cable size (split core); 4mm2 live conductors / 32A max current
Max voltage drop allowance <3% on supply cable (dependent on length)
Mounting requirement (listed) Wall capable of supporting at least four times the unit weight (44kg) and must be fire resistant

Setup and Use

  1. Unpack and check the unit for damage; report any damage to Andersen.
  2. Remove the front fascia and lower panel (loosen the 2 screws, then remove the fascia; remove the 2 screws holding the lower panel and cable guide, then release and remove the lower panel).
  3. Mount the unit to the wall using appropriate hardware for the structure (not provided). Ensure the unit core sits flush to the wall (use spacers if the surface is uneven).
  4. Plan cable entry: install the provided compression gland(s) for the allowed bottom or rear entry positions and ensure cables entering the unit are adequately sealed.
  5. Terminate sensor cables as required (Solar CT sensor cables are optional); gently pull the plug downwards to ease termination before replacing.
  6. Connect the mains supply to the mains terminals. Ensure stranded cables are ferruled and crimped. Set mains terminal torque to 1.2Nm; set terminal cover screws torque to 0.7Nm.
  7. Refit the terminal cover, cable guide, and lower panel; connect the LED loom by inserting the plug and pushing until you hear a click.
  8. Commissioning (network setup): On the charge point, firmly press the multi-function button three times to enter setup mode (LED repeatedly flashes cyan/blue). On the Andersen app, log out, open the app toolbox, and connect via Bluetooth. Select Wi‑Fi and enter the Wi‑Fi password. When prompted, enter the PIN for power settings.

Package Contents

  • Welcome Pack
  • A3 Unit
  • Grid CT Clamp
  • Solar CT Clamp (if applicable)
  • Terminal Cover Fitting Screws

Tools Required

  • Pozidrive screwdriver
  • 3mm HEX key
  • T-25 Anti-Tamper Security bit

Included in fitting kit

  • 1x 25mm Compression Gland for cable entry
  • M5 x12mm Hex for front fascia
  • M3 x8mm PZ1 for terminal cover

Andersen-A3-Installer-fiAndersen-A3-Installer-figure-23gure-2

SETUP MULTI-FUNCTION OPERATION

  • Reset RCM (Two button presses)
  • Enter Network setup mode (Three button presses)
  • Exit Network setup mode (One button presses)
  • Enter unit reset mode (Five button presses)

Multi-function button located on the bottom, next to the convenience light.

Andersen-A3-Installer-figure-3

OPERATION LED STATUS LIGHT

Andersen-A3-Installer-figure-4

Unpacking and Preperation

Preparation – Recommended Steps

  • Carefully Remove A3 From Box
  • Check A3 For Any Damage
  • Remove Front Fascia
  • Remove Lower Panel & Terminal Cover
  • Please use drill template provided
  • Mount To Wall

Step 1: Remove A3 Front Fascia & Lower Panel

  • Loosen the 2 screws, lift and carefully remove the front fascia.
  • Remove the 2 screws in both the lower panel & the lower cable guide. Pull the lower panel forward and down to release and remove cable guide.

Andersen-Aaaaaac3-Installer-figure-5 Andersen-A3-Installer-figure-6

Step 2: LED Loom Connection Point

Note:
With new installations this plug will be delivered disconnected.

Andersen-A3-Installer-figure-7

Step 3: Mount A3 Assembly To The Permanent Structure
The mounting hardware (screws, wall plugs etc) must be selected and be appropriate for the specific structure. These are not provided.

Andersen-A3-Installer-figure-8 Andersen-A3-InstAndersen-A3-Installer-figure-8aller-figure-9 Andersen-A3-Installer-figure-10

RECOMMENDED

Note:
If the mounted surface is uneven, use spacers to ensure the unit core is sitting flush to the wall.

Step 4: Cable Entry

  • Cable can enter the unit from 2 positions. One on the underside through provided gland or rear entry into this compartment.

Andersen-A3-Installer-figure-11

  • 1x Compression Gland (Not included) for any separate data cable. Size dependent on cable type used.

Andersen-A3-Installer-figure-12

  • Rear entry location from the bottom left wall mount fixing point.

Andersen-A3-Installer-figure-13

Cable Entry Continued

  • Cable entry can enter the unit from two positions. Both of these positions must include the installation of the provided gland.
  • Andersen-A3-Installer-figure-14Rear entry location from the bottom left wall mount fixing point.

Andersen-A3-Installer-figure-15

Andersen-A3-Installer-figure-16Step 5: Terminate Sensor Cables
Please ensure you follow the installer guides to commission this feature correctly

Andersen-A3-Installer-figure-17 Andersen-A3-Installer-figure-18

Step 6: Mains Supply Connection

Note:
Any stranded cables to be ferruled and crimped.

Andersen-A3-Installer-figure-19

Step 7: Refit Terminal Cover, Cable Guide & Lower Panel

Andersen-A3-Installer-figure-20 Andersen-A3-Installer-figure-21

Andersen-A3-Installer-figure-22

Step 8: Connect LED Loom
Insert the plug from the front fascia into the socket in the core of the unit. Gently push ensuring you hear a click to confirm connection.

Andersen-A3-Installer-figure-23

Step 9: Refit Front Fascia
Locate the fascia hooking the bottom and top into the core and gently lower into place. Fit and tighten screws.

Andersen-A3-Installer-figure-24

Andersen-A3-Installer-figure-25What you will need

  • A smartphone (iPhone or Android) with Bluetooth enabled
  • A wireless broadband router and the Wi-Fi password

Commissioning

  • Open the Andersen App
  • Ensure you are logged out
  • Press the toolbox located in the bottom right of the screen.
  • Follow the steps on the next screen to connect your charge point.
  • On your charge point, find and firmly press the multi-functionbutton three times.

Andersen-A3-Installer-figure-27

  • The Andersen App will start scanning for your charge point usingBluetooth. Tap the ‘Connect’ Button on the app to enter set-up.
  • Once the Andersen App has found all available networks, please select the Wi-Fi you wish to connect to and enter the Wi-Fi password.

Andersen-A3-Installer-figure-29

  • Once you have connected to the Wi-Fi network successfully your signal strength will be displayed here along with confirmation of connection.

Andersen-A3-Installer-figuAndersen-A3-Installer-figure-29re-30

  • You will now be prompted to enter a PIN to access the power settings. If you are a current Andersen affiliate, you may already have this PIN. Alternatively, please contact us.

Telephone: 01234 916125

Troubleshooting

  • Flashing cyan LED: the charge point is in setup mode (used during network setup).
  • All colours in a pulsating sequence: firmware update in progress; wait for the update to complete.
  • Solid red LED: the charge point has detected an error. Review installation/connection steps and ensure commissioning requirements were followed.
  • Pulsating yellow LED: the charge point is rebooting; allow it to complete rebooting before retrying setup.

Documents / Resources

PDF thumbnailAndersen A3 Installer
Installation Guide · Andersen, A3, Revision 1.4, EV Charger, Installer Manual

References

Ask a Question

Use this section to ask about setup, compatibility, troubleshooting, or anything missing from this manual.

Ask a Question

Ask about setup, compatibility, troubleshooting, or anything missing from this manual. Name and email are optional.