1. Product Overview

The TNCE FHM3-100E Series Dual Power Automatic Transfer Switch is a dedicated, purely mechanical switching device designed for reliable manual transfer between two single-phase power sources. It ensures continuous power supply to the load by preventing simultaneous connection of both power sources through a robust mechanical interlock mechanism. This switch is suitable for 220-240V, 50-60Hz systems.

Key Features:

  • PC Level Switching: Fast transfer time of less than 8ms, ensuring no interruption during power switching.
  • Dual Power Source Compatibility: Designed for city power and generator, or PV system and inverter applications.
  • Manual and Automatic Modes: Features both manual operation via an external handle and an automatic mode.
  • Flame Retardant Housing: Constructed with flame-retardant materials for good insulation and enhanced safety.
  • Din Rail Mounting: Standard 35mm Din Rail installation for easy integration into household lighting distribution boxes or other compatible enclosures.
TNCE Dual Power Automatic Transfer Switch Overview
Figure 1: TNCE Dual Power Automatic Transfer Switch Overview (2P/4P models shown with City Power/Generator and City Power/Solar Energy configurations)

2. Important Safety Warnings

Incorrect installation and operation may cause severe electric shock, equipment damage, fire, or even personal injury.

Safety Information:

  • Professional Installation: The installation, wiring, and maintenance of this product MUST be performed by a qualified electrician.
  • Strictly No Live Work: Before performing any installation, wiring, or transfer operation, you MUST ensure that BOTH incoming power sources upstream of the switch are completely disconnected, and verify that all terminals are de-energized using appropriate voltage testers. A warning sign such as "Do Not Close, Men at Work" should be posted at the worksite.
  • Safe Operation Principles: During operation, ensure the switch is securely in one of the three stable positions: "Normal Source ON", "OFF", or "Reserve Source ON". It is strictly forbidden to force operation or bypass the mechanical interlock when both incoming power sources are live.
  • Usage Environment: Install in a clean, dry, and well-ventilated indoor distribution cabinet.

3. Setup and Installation

3.1. Unpacking and Inspection

After unpacking, please check that the main product body, operating handle, mounting screws, and this manual are complete. Inspect the product for any visible damage caused during transportation. Manually operate the handle to feel the transition between the three positions ("Normal Source ON" - "OFF" - "Reserve Source ON"), ensuring it is smooth, distinct, and without sticking.

3.2. Mechanical Installation

  1. Drill holes on the mounting plate of the distribution cabinet according to the switch's mounting hole spacing.
  2. Mount the switch body vertically and securely.
  3. Test the operation with the handle to ensure the mechanism moves flexibly and positions correctly.
35mm Standard Guide Rail Mounting
Figure 2: 35mm Standard Guide Rail Mounting in a distribution box
35mm Standard Rail Installation
Figure 3: Direct installation in a household lighting distribution box

3.3. Electrical Wiring (CRITICAL! Power MUST be OFF before proceeding!)

Confirm all power sources are completely disconnected and verify de-energization before proceeding with wiring.

Incoming Connection:

  • Connect the Line (L) and Neutral (N) wires of the Normal Power Source (N) to the upper terminals on the "N" side of the switch body.
  • Connect the Line (L) and Neutral (N) wires of the Reserve Power Source (R) to the upper terminals on the "R" side of the switch body.

Outgoing Connection:

  • Connect the cables from the Load side to the lower output terminals of the switch.

Check all connections to ensure they are secure and correct, and clean the work area.

2P Product Wiring Diagram
Figure 4: 2P Product Wiring Diagram (Common power input, Common control lines, Backup power input, Backup control line, Load output)
4P Product Wiring Diagram
Figure 5: 4P Product Wiring Diagram (Common power input, Common control lines, Backup power input, Backup control line, Load output)

4. Operating Instructions

4.1. Manual Transfer Procedure

Transferring from Normal Source to Reserve Source:

  1. Turn OFF the upstream circuit breaker on the Normal source side.
  2. Move the operating handle from the "Normal Source ON" position, through the "OFF" position, to the "Reserve Source ON" position. You should feel a definite detent at each position.
  3. Turn ON the upstream circuit breaker on the Reserve source side. The load is now powered by the reserve source.

Transferring back from Reserve Source to Normal Source:

  1. Turn OFF the upstream circuit breaker on the Reserve source side.
  2. Move the operating handle from the "Reserve Source ON" position, through the "OFF" position, back to the "Normal Source ON" position.
  3. Turn ON the upstream circuit breaker on the Normal source side. The load is now restored to power from the normal source.

4.2. Automatic Switching Function

The switch supports automatic switching after a power failure, with a transfer time of less than 8ms, ensuring an uninterruptible power supply. This means computers and other electronic devices will not be turned off during the power source transition.

Automatic Switching after Power Off
Figure 6: Automatic switching after power off (Power failure <8ms)
Manual and Automatic Adjustment Methods
Figure 7: The switch offers both manual handle and manual/automatic switch options

4.3. Function Display Video

Video 1: Unboxing and demonstration of the switch's function and operation.

5. Maintenance

Periodic Inspection (Recommended annually): A qualified electrician should inspect the tightness of connections, remove dust, and test the smoothness of manual operation with power completely off.

Warning: Any disassembly or adjustment of the switch body must be performed by trained professionals only.

6. Troubleshooting

SymptomPossible CauseProfessional Recommendation
Handle cannot be operated or is stuck
  • Both incoming power sources are live, locking the interlock.
  • Foreign object inside or damage to the mechanical mechanism.
  • Operating handle not installed correctly.
  • STOP operation immediately! Check and ensure at least one power source is fully disconnected.
  • Have the internal mechanism inspected by a professional.
  • Reinstall the operating handle correctly.
Load has no power after switching
  • The target power source is not energized.
  • Incorrect or loose wiring.
  • Damaged switch contacts.
  • Check the voltage of the target power source.
  • Check all wiring after power is off.
  • Have the switch inspected by a qualified electrician.
Abnormal sparking or noise during operation
  • Operation was performed without disconnecting the upstream power sources (Extremely Hazardous!).
  • Short-circuit fault on the load side.
  • Poor contact of the contacts.
  • Stop all operations immediately and disconnect ALL incoming power sources!
  • Contact professional maintenance personnel for a comprehensive inspection.

7. Specifications

ParameterSpecificationNotes
ModelFHM3-100E
Brand NameTNCE
TypeMini Circuit breaker, ATS
Rated Operational Voltage (Ue)AC 230V / 220/380VSingle-Phase / Three-Phase
Rated Insulation Voltage (Ui)AC 500V
Rated Current (le)63A / 100A / 125ARefer to the product nameplate
Rated Frequency50/60 Hz
Number of Poles2P / 4P
Operation ModeManual (External handle operation)No motorized mechanism or display
Switch ModeAutomatic or manual
Conversion Power Outage Time<8MS
Mechanical InterlockEnforced Mechanical InterlockPrevents paralleling of two sources
Protection DegreeIP20 (when installed inside an enclosure)
Smart DeviceNo
Wireless FunctionalityNo
Battery IncludedNo
EU LVD VoltageHigh voltage: Above 50Vac or 75Vdc
High-concerned chemicalNone

7.1. Dimensions

FHM3-100E/2P Dimensions
Figure 8: FHM3-100E/2P Dimensions (107mm x 96mm x 76mm)
FHM3-100E/4P Dimensions
Figure 9: FHM3-100E/4P Dimensions (142mm x 96mm x 76mm)

7.2. Applications

High Power Load Support Applications
Figure 10: The switch supports 100A high power loads, suitable for central air conditioning, machine tool equipment, motor water pumps, and study rooms.

8. User Tips

  • Always ensure all connections are secure and correctly wired according to the diagrams before powering on.
  • Familiarize yourself with both manual and automatic operation modes to best suit your power management needs.
  • Regularly inspect the switch and its connections as part of your electrical system maintenance to ensure optimal performance.

9. Warranty and Support

9.1. Compliance Declaration

This product is designed and manufactured in accordance with the EU Low Voltage Directive LVD Directive 2014/35/EU and its harmonized standards, meeting its essential safety requirements. Referenced harmonized standards include but are not limited to EN 60947-1, EN 60947-3, etc.

CE RoHS

9.2. Further Assistance

For detailed information, troubleshooting, or technical support, please refer to the complete PDF user manual provided with your product. You can also scan the QR code below with the AliExpress app for professional consultation and guidance.

QR Code for AliExpress Support
Scan this QR code for professional consultation and support.
Documents and downloads

Ask a question about this manual

Ask about setup, troubleshooting, compatibility, parts, safety, or missing instructions. Manuals+ will review the question and use this page’s manual context to help answer it.

After a successful submission, we securely hash the supplied account or form email before sending it to Microsoft Advertising for conversion attribution. Privacy details.