1. Product Overview
The TNCE FHM3-100E Series Dual Power Automatic Transfer Switch is a dedicated, purely mechanical switching device designed for reliable manual transfer between two single-phase power sources. It ensures continuous power supply to the load by preventing simultaneous connection of both power sources through a robust mechanical interlock mechanism. This switch is suitable for 220-240V, 50-60Hz systems.
Key Features:
- PC Level Switching: Fast transfer time of less than 8ms, ensuring no interruption during power switching.
- Dual Power Source Compatibility: Designed for city power and generator, or PV system and inverter applications.
- Manual and Automatic Modes: Features both manual operation via an external handle and an automatic mode.
- Flame Retardant Housing: Constructed with flame-retardant materials for good insulation and enhanced safety.
- Din Rail Mounting: Standard 35mm Din Rail installation for easy integration into household lighting distribution boxes or other compatible enclosures.

2. Important Safety Warnings
Incorrect installation and operation may cause severe electric shock, equipment damage, fire, or even personal injury.
Safety Information:
- Professional Installation: The installation, wiring, and maintenance of this product MUST be performed by a qualified electrician.
- Strictly No Live Work: Before performing any installation, wiring, or transfer operation, you MUST ensure that BOTH incoming power sources upstream of the switch are completely disconnected, and verify that all terminals are de-energized using appropriate voltage testers. A warning sign such as "Do Not Close, Men at Work" should be posted at the worksite.
- Safe Operation Principles: During operation, ensure the switch is securely in one of the three stable positions: "Normal Source ON", "OFF", or "Reserve Source ON". It is strictly forbidden to force operation or bypass the mechanical interlock when both incoming power sources are live.
- Usage Environment: Install in a clean, dry, and well-ventilated indoor distribution cabinet.
3. Setup and Installation
3.1. Unpacking and Inspection
After unpacking, please check that the main product body, operating handle, mounting screws, and this manual are complete. Inspect the product for any visible damage caused during transportation. Manually operate the handle to feel the transition between the three positions ("Normal Source ON" - "OFF" - "Reserve Source ON"), ensuring it is smooth, distinct, and without sticking.
3.2. Mechanical Installation
- Drill holes on the mounting plate of the distribution cabinet according to the switch's mounting hole spacing.
- Mount the switch body vertically and securely.
- Test the operation with the handle to ensure the mechanism moves flexibly and positions correctly.


3.3. Electrical Wiring (CRITICAL! Power MUST be OFF before proceeding!)
Confirm all power sources are completely disconnected and verify de-energization before proceeding with wiring.
Incoming Connection:
- Connect the Line (L) and Neutral (N) wires of the Normal Power Source (N) to the upper terminals on the "N" side of the switch body.
- Connect the Line (L) and Neutral (N) wires of the Reserve Power Source (R) to the upper terminals on the "R" side of the switch body.
Outgoing Connection:
- Connect the cables from the Load side to the lower output terminals of the switch.
Check all connections to ensure they are secure and correct, and clean the work area.


4. Operating Instructions
4.1. Manual Transfer Procedure
Transferring from Normal Source to Reserve Source:
- Turn OFF the upstream circuit breaker on the Normal source side.
- Move the operating handle from the "Normal Source ON" position, through the "OFF" position, to the "Reserve Source ON" position. You should feel a definite detent at each position.
- Turn ON the upstream circuit breaker on the Reserve source side. The load is now powered by the reserve source.
Transferring back from Reserve Source to Normal Source:
- Turn OFF the upstream circuit breaker on the Reserve source side.
- Move the operating handle from the "Reserve Source ON" position, through the "OFF" position, back to the "Normal Source ON" position.
- Turn ON the upstream circuit breaker on the Normal source side. The load is now restored to power from the normal source.
4.2. Automatic Switching Function
The switch supports automatic switching after a power failure, with a transfer time of less than 8ms, ensuring an uninterruptible power supply. This means computers and other electronic devices will not be turned off during the power source transition.


4.3. Function Display Video
5. Maintenance
Periodic Inspection (Recommended annually): A qualified electrician should inspect the tightness of connections, remove dust, and test the smoothness of manual operation with power completely off.
Warning: Any disassembly or adjustment of the switch body must be performed by trained professionals only.
6. Troubleshooting
| Symptom | Possible Cause | Professional Recommendation |
|---|---|---|
| Handle cannot be operated or is stuck |
|
|
| Load has no power after switching |
|
|
| Abnormal sparking or noise during operation |
|
|
7. Specifications
| Parameter | Specification | Notes |
|---|---|---|
| Model | FHM3-100E | |
| Brand Name | TNCE | |
| Type | Mini Circuit breaker, ATS | |
| Rated Operational Voltage (Ue) | AC 230V / 220/380V | Single-Phase / Three-Phase |
| Rated Insulation Voltage (Ui) | AC 500V | |
| Rated Current (le) | 63A / 100A / 125A | Refer to the product nameplate |
| Rated Frequency | 50/60 Hz | |
| Number of Poles | 2P / 4P | |
| Operation Mode | Manual (External handle operation) | No motorized mechanism or display |
| Switch Mode | Automatic or manual | |
| Conversion Power Outage Time | <8MS | |
| Mechanical Interlock | Enforced Mechanical Interlock | Prevents paralleling of two sources |
| Protection Degree | IP20 (when installed inside an enclosure) | |
| Smart Device | No | |
| Wireless Functionality | No | |
| Battery Included | No | |
| EU LVD Voltage | High voltage: Above 50Vac or 75Vdc | |
| High-concerned chemical | None |
7.1. Dimensions


7.2. Applications

8. User Tips
- Always ensure all connections are secure and correctly wired according to the diagrams before powering on.
- Familiarize yourself with both manual and automatic operation modes to best suit your power management needs.
- Regularly inspect the switch and its connections as part of your electrical system maintenance to ensure optimal performance.
9. Warranty and Support
9.1. Compliance Declaration
This product is designed and manufactured in accordance with the EU Low Voltage Directive LVD Directive 2014/35/EU and its harmonized standards, meeting its essential safety requirements. Referenced harmonized standards include but are not limited to EN 60947-1, EN 60947-3, etc.
CE RoHS
9.2. Further Assistance
For detailed information, troubleshooting, or technical support, please refer to the complete PDF user manual provided with your product. You can also scan the QR code below with the AliExpress app for professional consultation and guidance.