TNCE FHM3-100E

Contents

TNCE FHM3-100E Series Dual Power Automatic Transfer Switch

User Manual for Manual Operation Type (2P/4P)

1. Product Overview

The TNCE FHM3-100E Series Dual Power Automatic Transfer Switch is a dedicated, purely mechanical switching device designed for reliable manual transfer between two power sources. It ensures continuous power supply to the load by preventing the simultaneous connection of both power sources through a robust mechanical interlock mechanism.

This series supports both 2-pole (2P) and 4-pole (4P) configurations, catering to single-phase and three-phase applications respectively. The switch operates manually via an external operating handle.

Typical Applications: Communication equipment, security systems, small medical instruments, lighting circuits, and other critical loads requiring power backup from sources like city grids, generators, or PV energy systems.

TNCE Dual Power Automatic Transfer Switch showing 2P and 4P models with different power source configurations (City Power, Solar Energy, Generator).

Figure 1: TNCE Dual Power Automatic Transfer Switch (2P and 4P models)

Product Demonstration Video

Video 1: Unboxing and Function Display of the TNCE Automatic Transfer Switch.

2. Important Safety Warnings

Incorrect installation and operation may cause severe electric shock, equipment damage, fire, or even personal injury.

Safety Information:

  • Professional Installation: The installation, wiring, and maintenance of this product MUST be performed by a qualified electrician.
  • Strictly No Live Work: Before performing any installation, wiring, or transfer operation, you MUST ensure that BOTH incoming power sources upstream of the switch are completely disconnected, and verify that all terminals are de-energized using appropriate voltage testers.
  • A warning sign such as "Do Not Close, Men at Work" should be posted at the worksite.

Safe Operation Principles:

  • During operation, ensure the switch is securely in one of the three stable positions: "Normal Source ON", "OFF", or "Reserve Source ON".
  • It is strictly forbidden to force operation or bypass the mechanical interlock when both incoming power sources are live.
  • Usage Environment: Install in a clean, dry, and well-ventilated indoor distribution cabinet.

3. Technical Specifications

Item Parameter Notes
Model FHM3-100E
Rated Operational Voltage (Ue) AC 220/380V Single-Phase (2P) or Three-Phase (4P)
Rated Insulation Voltage (Ui) AC 500V
Rated Current (Ie) 63A / 100A / 125A Refer to the product nameplate for specific model rating
Rated Frequency 50/60 Hz
Number of Poles 2P / 4P No motorized mechanism or display
Operation Mode Manual (External handle operation)
Mechanical Interlock Enforced Mechanical Interlock Prevents paralleling of two sources
Conversion Power Outage Time <8MS Uninterruptible power supply switching function
Protection Degree IP20 When installed inside an enclosure

Dimensions:

Dimensions for FHM3-100E/2P and FHM3-100E/4P models. The 2P model is 107mm wide, 96mm high, and 76mm deep. The 4P model is 142mm wide, 96mm high, and 76mm deep.

Figure 2: Dimensions for 2P and 4P models.

4. Unpacking and Inspection

Upon receiving your TNCE Dual Power Automatic Transfer Switch, carefully unpack the contents and perform the following checks:

  1. Verify that the main product body, operating handle, mounting screws, and this user manual are complete and present.
  2. Inspect the product for any visible damage that may have occurred during transportation.
  3. Manually operate the handle to feel the transition between the three stable positions ("Normal Source ON" - "OFF" - "Reserve Source ON"). Ensure the movement is smooth, distinct, and without sticking.

5. Installation and Wiring Guide

This procedure MUST be performed by a qualified electrician.

Step 1: Mechanical Installation

  1. Drill holes on the mounting plate of the distribution cabinet according to the switch's mounting hole spacing.
  2. Mount the switch body vertically and securely.
  3. Test the operation with the handle to ensure the mechanism moves flexibly and positions correctly.
TNCE Dual Power Automatic Transfer Switch mounted on a 35mm Din Rail inside a distribution box.

Figure 3: 35 mm Standard Guide Rail Mounting.

Step 2: Electrical Wiring

CRITICAL! Power MUST be OFF before proceeding!

  1. Confirm all power sources are completely disconnected and verify de-energization using appropriate voltage testers.
  2. Incoming Connection (Normal Source): Connect the Line (L) and Neutral (N) wires of the Normal Power Source to the upper terminals on the "N" side of the switch body.
  3. Incoming Connection (Reserve Source): Connect the Line (L) and Neutral (N) wires of the Reserve Power Source to the upper terminals on the "R" side of the switch body.
  4. Outgoing Connection (Load): Connect the cables from the Load side to the lower output terminals of the switch.
  5. Check all connections to ensure they are secure and correct, and clean the work area.

Wiring Diagram for 2P Model:

Wiring diagram for the 2P TNCE Dual Power Automatic Transfer Switch. Shows common power input, backup power input, common control lines, backup control line, and load output connections.

Figure 4: Product Wiring Diagram for 2P (FHM3-100E/2P).

Wiring Diagram for 4P Model:

Wiring diagram for the 4P TNCE Dual Power Automatic Transfer Switch. Shows common power input, backup power input, common control lines, backup control line, and load output connections.

Figure 5: Product Wiring Diagram for 4P (FHM3-100E/4P).

6. Operation Instructions

Manual Transfer Procedure:

Transferring from Normal Source to Reserve Source:

  1. Turn OFF the upstream circuit breaker on the Normal source side.
  2. Move the operating handle from the "Normal Source ON" position, through the "OFF" position, to the "Reserve Source ON" position. You should feel a definite detent at each position.
  3. Turn ON the upstream circuit breaker on the Reserve source side. The load is now powered by the reserve source.

Transferring back from Reserve Source to Normal Source:

  1. Turn OFF the upstream circuit breaker on the Reserve source side.
  2. Move the operating handle from the "Reserve Source ON" position, through the "OFF" position, back to the "Normal Source ON" position.
  3. Turn ON the upstream circuit breaker on the Normal source side. The load is now restored to power from the normal source.
The TNCE Dual Power Automatic Transfer Switch showing the manual handle and the auto/manual selector switch.

Figure 6: Manual handle and Auto/Manual switch.

7. Troubleshooting

Symptom Possible Cause Professional Recommendation
Handle cannot be operated or is stuck
  • Both incoming power sources are live, locking the interlock.
  • Foreign object inside or damage to the mechanical mechanism.
  • Operating handle not installed correctly.
  • STOP operation immediately! Check and ensure at least one power source is fully disconnected.
  • Have the internal mechanism inspected by a professional.
  • Reinstall the operating handle correctly.
Load has no power after switching
  • The target power source is not energized.
  • Incorrect or loose wiring.
  • Damaged switch contacts.
  • Check the voltage of the target power source.
  • Check all wiring after power is off.
  • Have the switch inspected by a qualified electrician.
Abnormal sparking or noise during operation
  • Operation was performed without disconnecting the upstream power sources (Extremely Hazardous!).
  • Short-circuit fault on the load side.
  • Poor contact of the contacts.
  • Stop all operations immediately and disconnect ALL incoming power sources!
  • Contact professional maintenance personnel for a comprehensive inspection.

8. Maintenance

Periodic Inspection (Recommended annually): A qualified electrician should inspect the tightness of connections, remove dust, and test the smoothness of manual operation with power completely off.

Warning: Any disassembly or adjustment of the switch body must be performed by trained professionals only.

9. User Tips

  • Always prioritize safety. Before any interaction with the switch, ensure all power sources are disconnected and verified de-energized.
  • Regularly check for any signs of wear, loose connections, or unusual sounds/smells. Address these promptly with a qualified professional.
  • Keep the installation environment clean, dry, and well-ventilated to ensure optimal performance and longevity of the device.
  • Familiarize yourself with the manual and practice the transfer procedure (with power off) to ensure smooth operation during an actual power event.

10. Compliance Declaration & Support

This product is designed and manufactured in accordance with the EU Low Voltage Directive LVD Directive 2014/35/EU and its harmonized standards, meeting its essential safety requirements. Referenced harmonized standards include but are not limited to EN 60947-1, EN 60947-3, etc.

CE and RoHS compliance logos

CE and RoHS Compliant

For detailed item guides and documents, including a PDF version of the user manual, please refer to the official product page or contact customer support. The PDF manual can be found at: User manual (PDF).

For 24-hour professional consultation, guidance, and after-sales service, please scan the QR code on the product packaging or visit the TNCE Intelligent Store on AliExpress.

Documents and downloads

Ask a question about this manual

Ask about setup, troubleshooting, compatibility, parts, safety, or missing instructions. Manuals+ will review the question and use this page’s manual context to help answer it.

After a successful submission, we securely hash the supplied account or form email before sending it to Microsoft Advertising for conversion attribution. Privacy details.