INVT MG5KTL

Contents

INVT 5000W MPPT Grid Tie Solar Inverter

Model: MG5KTL | Brand: INVT

Preface

This manual provides detailed information regarding the product, including installation, application, troubleshooting, precautions, and maintenance of iMars series grid-tied solar inverters. It does not contain all information about the photovoltaic system. Please read this manual carefully and adhere to all safety precautions during moving, installation, operation, and maintenance to ensure correct use and high performance of the inverter.

The use of iMars series grid-tied solar inverters must comply with local laws and regulations concerning grid-tied power generation.

This manual should be kept accessible at all times. All rights reserved. The contents of this document are subject to change without notice. Data deviations may occur due to product improvements; detailed information will align with the final product.

1. Safety Precautions

iMars series grid-tied solar inverters are designed and tested strictly in accordance with relevant international safety standards. As an electrical and electronic device, all relevant safety regulations must be strictly complied with during installation, operation, and maintenance. Incorrect use or misuse may result in:

  • Injury to the life and personal safety of the operator or other people.
  • Damage to the inverter or other property belonging to the operator or other people.

To avoid personal injury and damage, please strictly observe the following safety precautions. This chapter describes various warning symbols and provides safety instructions for installation, operation, maintenance, and use of the iMars series grid-tied solar inverters.

1.1 Icons

This manual uses icons to highlight physical and property safety information to prevent device damage and physical injury. The icons used are:

Icons Name Instruction Abbreviation
Danger icon Danger Serious physical injury or even death may occur if not follow the relative requirements
Warning icon Warning Physical injury or damage to the devices may occur if not follow the relative requirements
Do not icon Do not Damage may occur if not follow the relative requirements
Hot sides icon Hot sides Sides of the device may become hot. Do not touch.
Note icon Note Physical hurt may occur if not follow the relative requirements Note

1.2 Safety Guidelines

  • Upon receipt, check for any visible damage to the package or inverter. If damage is suspected, contact the shipping company and local dealer before installation.
  • Only qualified electricians are permitted to operate on the inverter.
  • Do not perform any wiring, inspection, or component changes while power is applied.
  • This product can cause residual current in the external protective earth conductor. If a residual current-operated protective (RCD) or monitoring (RCM) device is used for protection against direct or indirect contact, only a Type B RCD or RCM is allowed on the supply side.
  • Ensure no electromagnetic interference from other electrical and electronic equipment at the installation site.
  • Do not modify the inverter without authorization.
  • All electrical installations must comply with national or local laws and standards.
  • The temperature of individual parts or the inverter enclosure (especially the heat sink) may become hot during normal operation. There is a risk of burns. Do not touch.
  • Do not open the inverter cover without authorization. Electrical parts and components inside the inverter are electrostatic. Take precautions to avoid electrostatic discharge during operation.
  • The inverter must be reliably grounded.
  • Ensure that DC and AC side circuit breakers have been disconnected and wait at least 5 minutes before wiring and checking.

Note: Technical personnel performing installation, wiring, commissioning, maintenance, troubleshooting, and replacement of iMars series grid-tied solar inverters must meet the following requirements:

  • Operators need professional training.
  • Operators must read this manual completely and master related safety precautions.
  • Operators need to be familiar with relevant safety regulations for electrical systems.
  • Operators need to be fully familiar with the composition and operating principle of the entire grid-tied photovoltaic power generation system and related standards of the countries/regions where the project is located.
  • Operators must wear personal protective equipment.

1.2.1 Delivery and Installation

  • Keep the package and unit complete, dry, and clean during storage and delivery.
  • Please remove and install the inverter with two or more people, as the inverter is heavy.
  • Remove and install the inverter with appropriate tools to ensure safe and normal operation and avoid physical injury or death. Personnel should also use mechanical protective measures, such as protective shoes and work clothes.
  • Only qualified electricians are allowed to install the inverter.

1.2.2 Grid-tied Operation

  • Do not put or install the inverter on or close to combustible materials.
  • Keep the installation site away from children and other public places.
  • Remove metal jewelry (rings, bracelets) before installation and electrical connection to avoid electric shock.
  • Cover solar modules with light-tight materials. Exposed to sunlight, solar modules will output dangerous voltage.
  • The inverter input voltage must not exceed the maximum input voltage; otherwise, inverter damage may occur.
  • The positive and negative poles of solar modules cannot be grounded, as this may cause irrecoverable damage.
  • Ensure proper grounding of the inverter; improper connection or no grounding may cause the inverter to stop.
  • Ensure reliable installation and electrical connection.
  • When photovoltaic generator cells are exposed to light (even if dim), the generator supplies DC voltage to the inverter.

Note: iMars series grid-tied solar inverters are only for crystalline silicon solar modules.

1.2.3 Maintenance and Inspection

  • Only qualified electricians are allowed to perform maintenance, inspection, and component replacement of the inverter.
  • Contact the local dealer or supplier for maintenance.
  • To prevent unauthorized personnel from entering the maintenance area, temporary warning labels must be placed, and a fence used for isolation.
  • Firstly, disconnect all power supplies from the grid to the inverter before any maintenance, then disconnect the breakers and wait for at least 5 minutes until the inverter is discharged.
  • Follow electrostatic protection norms and take correct protective measures due to electrostatic sensitive circuits and devices in the inverter.
  • Do not use parts and components not provided by the manufacturer during maintenance.
  • Restart the inverter after resolving any fault or problem that may affect its safety and performance.
  • Do not touch any metal conductive part of the grid or inverter, as this may cause electric shock, physical injury, death, or fire. Observe all warning icons and instructions related to "electric shock."

1.2.4 What to do after scrapping

Do not dispose of the inverter with household waste. The user is responsible for sending it to a designated organization for recycling and disposal.

2. Product Overview

This chapter describes the appearance, packaging accessories, nameplate, technical parameters, and other information of iMars series grid-tied solar inverters.

2.1 Solar Grid-tied Power Generation System

2.1.1 Application

The photovoltaic grid-tied power generation system consists of solar modules, a grid-tied inverter, metering devices, and the public grid. The grid-tied solar inverter is the core component, converting DC electric energy from solar modules into sinusoidal AC energy with the same frequency and phase as the public grid, which is then fed into the grid.

iMars series grid-tied solar inverters are only applied in solar grid-tied power generation systems where DC input is composed solely of crystalline silicon solar modules whose negative and positive poles are not grounded.

Single Phase Connection Diagram
Figure 2.1: Single Phase Connection Diagram. Shows the inverter connected to solar panels, utility grid, meter, CT sensor, and household loads. Instructions: Configure solar panels and CT cables according to instructions.
Three Phase Connection Diagram
Figure 2.1 (cont.): Three Phase Connection Diagram. Similar to single-phase but with multiple CT sensors (CT1, CT2, CT3) for three-phase loads. Instructions: Configure solar panels and CT cables according to instructions.
  • The recommended solar modules need to comply with IEC61730 Class A rating.
  • iMars series grid-tied solar inverters are only for crystalline silicon solar modules.

2.1.2 Supported Grid Connection Structure

iMars series grid-tied solar inverters support TN-S, TN-C, TN-C-S, and TT grid connections. When applied to TT connection, the N-to-PE voltage should be less than 30V.

Type of Grid Diagrams
Figure 2.2: Diagrams illustrating TN-S, TN-C, TN-C-S, and TT grid connection types for solar inverters.

2.2 Product Appearance

Inverter Product Appearance
Figure 2.3: Front and side view of the inverter, highlighting the operational panel, DC switch, input/output ports, and cooling chamber.
No. Name Instruction
1Cover
2Operational panelLED indicators
3DC switchOn-off of the DC input (optional)
4DC input portFor the connection of solar modules
5AC terminalFor the connection of AC output
6Communication portRS485 and EXT communication port
7Cooling chamber
8Radiator
9Name plateFor rated parameters and safety precautions of the inverter

2.3 Nameplate

Inverter Nameplate
Figure 2.4: Example of an inverter nameplate, showing trademark, model, technical parameters, certifications (CE, RoHS, TUV), and serial number.

The nameplate provides essential information about the inverter:

  1. Trademark and product type
  2. Model and important technical parameters
  3. Certification system of the inverter confirming
  4. Serial number, company name, and country of origin.

2.4 Product Models

Product name Model Rated output power
Single-phase (L, N, PE)
Single-phase grid-tied solar inverteriMars MG750TL750
Single-phase grid-tied solar inverteriMars MG1KTL1000
Single-phase grid-tied solar inverteriMars MG1K5TL1500
Single-phase grid-tied solar inverteriMars MG2KTL2000
Single-phase grid-tied solar inverteriMars MG3KTL3000
Single-phase grid-tied solar inverteriMars MG4KTL3680
Single-phase grid-tied solar inverteriMars MG4K6TL4200
Single-phase grid-tied solar inverteriMars MG5KTL4600
Single-phase grid-tied solar inverteriMars MG3KTL-2M3000
Single-phase grid-tied solar inverteriMars MG4KTL-2M3680
Single-phase grid-tied solar inverteriMars MG4K6TL-2M4200
Single-phase grid-tied solar inverteriMars MG5KTL-2M4600

Note: Refer to the product specifications in chapter 9 for detailed information.

2.5 Dimensions and Weight

Product Size Comparison
Figure 2.5: Product Size Comparison for 3KW, 5KW, 6KW, and 10KW single-phase and three-phase inverters.
Model H (mm) W (mm) D (mm) Net weight (kg)
MG750TL/MG1KTL/MG1K5TL/MG2KTL/MG3KTL2803001389.5
MG4KTL/MG4K6TL/MG5KTL36536015015
MG3KTL-2M/MG4KTL-2M/MG4K6TL-2M/MG5KTL-2M42036015017

Package Dimensions and Gross Weight

Model H (mm) W (mm) D (mm) Gross weight (kg) Packaging Material
MG750TL/MG1KTL/MG1K5TL/MG2KTL/MG3KTL41141825111Paper
MG4KTL/MG4K6TL51848028417Paper
MG3KTL-2M/MG4KTL-2M/MG4K6TL-2M/MG5KTL-2M57348028419Paper

3. Storage

If the inverter is not put into use immediately, its storage should meet the following requirements:

  • Do not remove the outer packing.
  • The inverter needs to be stored in a clean and dry place, protected from dust and water vapor.
  • The storage temperature should be kept between -40°C and +70°C, and the relative humidity between 5%RH and 95%RH.
  • Stacking of inverters is recommended according to the number of stacking layers in the original shipment. Place the inverter carefully during stacking to avoid personal injury or equipment damage caused by falling.
  • Keep away from chemically corrosive substances that may corrode the inverter.
  • Periodic inspections are required. If damage from worms or rats, or packaging damage is found, the packaging materials must be replaced promptly.

After long-term storage, inverters need to be inspected and tested by qualified personnel before use.

4. Installation

This chapter describes how to install the inverter and connect it to the grid-tied solar system (including connections between solar modules, public grid, and inverter). Read this chapter carefully and ensure all installation requirements are met before installation. Only qualified electricians are allowed to install the inverter.

4.1 Unpacking Inspection

Inspect the order information and nameplate to ensure the product matches the order and that there is no damage to the package. If any problems are found, contact the supplier as soon as possible. If not used immediately, store the inverter in its package, protected from humidity and dust.

After unpacking, check the following:

  1. Ensure no damage to the inverter unit.
  2. Ensure the operation manual, port, and installation accessories are in the package.
  3. Ensure no damage or loss to the items in the package.
  4. Ensure the information on the order matches that on the nameplate.

Packing List:

No. Name Quantity
1MG750TL/MG1KTL/MG1K5TL/MG2KTL/MG3KTL/MG4KTL/MG4K6TL/MG5KTL/MG3KTL-2M/MG4KTL-2M/MG4K6TL-2M/MG5KTL-2M inverter1
2Installation bracket1
3Operation manual1
4Hexagon assembling bolt M5*202
5Expansion bolts M6*603pcs (for MG750TL-MG3KTL), 4pcs (for MG4KTL-MG5KTL-2M)
6DC connector1 pair (for MG750TL-MG3KTL), 2 pairs (for MG4KTL-MG5KTL-2M)
7AC connector1

4.2 Before Installation

4.2.1 Installation Tools

No. Installation tools Instruction
1Marking penMark the installation hole
2ElectrodrillDrill in the bracket or wall
3HammerHammer on the expansion bolts
4Monkey wrenchFix the installation bracket
5Allen driverFasten the screws, remove and install AC wiring box
6Straight screwdriverFor AC wiring
7MeggerMeasuring insulation performance and impedance
8MultimeterCheck the circuit and AC and DC voltage
9Electric ironWeld communications cable
10Wire crimperCrimp DC terminals

4.2.2 Installation Place

Select the installation place based on the following considerations:

  1. Height from ground level should be enough to ensure that display and status LEDs are easy to read.
  2. Select a well-ventilated place sheltered from direct sun radiation and rain.
  3. Allow sufficient space around the inverter to enable easy installation and removal from the mounting surface.
  4. The environment temperature is between -25°C and 60°C.
  5. The installation position keeps away from the interface of other electrical devices.
  6. The inverter needs to be installed on a firm and sturdy surface, such as a wall or metal bracket.
  7. The installation surface should be perpendicular to the horizontal line.
  8. The installation should ensure that the inverter is reliably grounded, and the material of the grounded metal conductor should be consistent with the metal material reserved for the grounding of the inverter.
Installation Precautions Diagram
Figure 4.1: Installation Precautions. Diagram showing required clearances (450mm top/bottom, 200mm sides) and acceptable/unacceptable mounting orientations.

Ensure there is sufficient space for heat-releasing. Generally, the following space requirements should be met:

Minimum clearance
Lateral200mm
Top450mm
Bottom450mm

Warning: Do not remove any part or component of the inverter unintentionally; otherwise, damage to the device and physical injury may occur.

4.2.3 Connection Cables

Select connection cables according to the table below:

Model DC side AC side
Cross-section (length ≤50m) mm² Cross-section (length >50m) mm² Mini cross-section mm² (L) Mini cross-section mm² (N/PE)
MG750TL/MG1KTL/MG1K5TL/MG2KTL/MG3KTL444
MG4KTL/MG4K6TL/MG5KTL/MG3KTL-2M/MG4KTL-2M/MG4K6TL-2M/MG5KTL-2M446

4.2.4 Miniature Circuit Breakers

It is strongly recommended to install circuit breakers or fuses at the DC input and AC output to ensure safe installation and operation.

  • To protect the PCE, user, and installer, external DC and AC circuit breakers shall be equipped at the end-use application.
  • Wiring shall comply with local electrical codes. Choose proper cables for power input and output lines. Input and output cables shall be PV private cables suitable for outdoor use.
Breaker Specifications:
Model DC input AC output
Recommended DC breakers (optional for length >100m) Recommended AC breakers
MG750TL/MG1KTL/MG1K5TLDC500V, C10A, 2PAC240V, C10A, 2P
MG2KTLDC500V, C16A, 2PAC240V, C16A, 2P
MG3KTL/MG3KTL-2MDC500V, C16A, 2PAC240V, C20A, 2P
MG4KTL/MG4KTL-2MDC600V, C20A, 2PAC240V, C25A, 2P
MG4K6TL/MG5KTL/MG4K6TL-2M/MG5KTL-2MDC600V, C25A, 2PAC240V, C32A, 2P

4.3 Mechanical Installation

Since the installation place can be made of different construction materials, the inverter can be installed by various mounting methods. Taking a typical concrete wall environment as an example, this manual describes how to install the inverter. The inverter should be mounted in a vertical position, 90° to the horizontal line.

4.3.1 Installation of Single-phase Inverter

Installation steps:

  1. First, take the installation bracket from the package.
  2. Place the installation bracket at the appropriate height and position on the wall, mark the hole locations according to the fixing holes, drill holes to a depth of about 70mm, and mount the bracket according to the arrow sign.
  3. Lift the inverter to suspend it on the installation bracket using M8 hex socket cap screws.
  4. Finally, fasten M5 hex socket cap screws connecting the inverter with the bracket and tighten the screws to 2 Nm. For firm installation, operators must not release the device until the inverter is firmly installed on the bracket.
Installation of Inverter
Figure 4.5: Step-by-step diagram showing the mechanical installation of the inverter onto a wall bracket.

4.4 Electrical Installation

This section describes detailed electrical installation and related safety instructions.

Block Diagram of Grid-tied Solar System
Figure 4.6: Block diagram illustrating the components of a grid-tied solar system, including solar PV modules, inverter, feeding meter, public grid, SPD, and monitoring equipment.
  • Improper operation during the wiring process can cause fatal injury to the operator or irrecoverable damage to the inverter. Only qualified personnel can perform the wiring work.
  • All electrical installations must comply with local and national electrical codes.
  • All cables must be firmly attached, undamaged, properly insulated, and adequately dimensioned.
  • It is not allowed to close the AC and DC breakers before the inverter is electrically connected.
  • Read and follow the instructions provided in this section while observing all safety warnings.
  • Always note the rated voltage and current defined in this manual. Never exceed the limits.

4.4.1 Connection of Solar Modules

Connection steps:

  1. Lightning, short-circuit, and other protection measures that meet local electrical safety laws and regulations are needed before the AC connection.
  2. Connect the output cables of solar modules to the DC connector as shown in Figure 4.7. Loosen the nut of the connector and remove about 15mm of the DC cable's isolation layer. Insert it into the connector and press until you hear a lock sound. Finally, tighten the nut to a torque of 2.5-3 Nm. The wiring of the negative pole is the same as that of the positive pole. Ensure the poles of solar modules are well connected with the connectors.
  3. After the DC connector is connected, use a multimeter to measure the voltage of the DC input string, verify the polarity of the DC input cable, and ensure that the voltage of each string is within the allowable range of the inverter.
DC Connector Connection
Figure 4.7: Diagram showing the steps for connecting DC cables to the inverter's DC connector.
DC Input Voltage Measuring
Figure 4.8: Illustration of using a multimeter to measure DC input voltage from solar modules.
  • Only qualified cables under local electrical safety laws and regulations are allowed to connect.
  • The solar modules connected with the inverter must be the configured ones, not unauthorized connecting devices. Otherwise, device damage, unstable operation, or fire may occur.
  • Connect the DC connector with the inverter and ensure it is tightly fastened.
  • Insert a screwdriver into the hole of the connector to remove it from the inverter.
  • Unclench the pressed cover with a screwdriver to remove the cables from the connector.

4.4.2 AC Connection

Connection steps for single-phase inverter:

  1. Before connecting the single-phase AC grid cable to the inverter, take lightning and short-circuit protection measures in accordance with local electrical safety codes.
  2. As shown in Figure 4.9, connect and fasten L, N, and PE conductors of the single-phase common grid to the AC terminal, tightening to 0.5 Nm. Assemble the terminal, tightening to 2.5-3 Nm, and then connect the terminal to the AC port of the inverter.
  3. Fix and connect the DC output cables of the PV board with the matched DC connectors, and then connect the connectors to the DC port of the inverter.
AC Connection of Single-phase Inverter
Figure 4.9: Diagram illustrating the steps for connecting the AC output cable to the single-phase inverter.
  • Only qualified cables under local electrical safety laws and regulations are allowed to connect.
  • Only with the permission of the local electric power company can the inverter be connected to the utility grid.

5. Operation

This chapter describes the detailed operation of the inverter, including inspection before operation, grid-tied operation, stopping, and daily maintenance.

5.1 Inspection Before Operation

Perform the following checks before operation:

  1. Ensure the installation site meets the requirements mentioned in section 4.2.2 for easy installation, removal, operation, and maintenance.
  2. Ensure the mechanical installation meets the requirements mentioned in section 4.3.
  3. Ensure the electrical installation meets the requirements mentioned in section 4.4.
  4. Ensure all switches are "off".
  5. Ensure the voltage meets the requirements mentioned in chapter 9.
  6. Ensure all electrical safety precautions are clearly identified at the installation site.

Warning: Perform the above checks before any operation if the system or inverter needs to be installed, refitted, or maintained.

5.2 Grid-tied Operation

  • When powering on the inverter for the first time, refer to section 6.5 to complete grid certification choice.
  • Keep the inverter powered on for at least 30 minutes to charge the internal clock battery.

To start the inverter:

  1. Ensure the requirements mentioned in section 5.1 are met.
  2. Switch on the breakers at the AC side.
  3. Switch on the integrated DC switch.
  4. Switch on the switch on the DC side.
  5. Observe the LED indicators and information displayed on the screen. Refer to chapter 6 for detailed information.
  • Run: Green indicator blinks, others off: the inverter is powered on and in self-inspection.
  • Run: Green indicator on, others off: the inverter is in power generation after self-inspection (successful commissioning).
  • "Warn" or "Fault" indicators are on or blinking: the inverter is powered on, but a fault occurs. Refer to section 6.3 for detailed information, then stop as mentioned in section 5.3. Settle the problems as described in chapter 8. If all faults are resolved, proceed as mentioned in chapter 5.

5.3 Stopping

Stop the inverter as follows if maintenance, inspection, or troubleshooting is required:

  1. Switch off the breakers at the AC side.
  2. Switch off the integrated DC switch.
  3. Switch off the switch on the DC side.
  4. Wait at least 5 minutes until the internal parts and components are discharged. Then stop the inverter.

5.4 Daily Maintenance

The inverter can perform power generation, start, and stop automatically even with day/night shifts and seasonal changes. To prolong its service life, daily maintenance and inspection are necessary, following the instructions in this manual.

5.4.1 Regular Maintenance

Maintenance contents Maintenance methods Maintenance cycle
Store the operation dataUse real-time monitoring software to read inverter running data, regularly back up all inverter running data and stats. Check the monitoring software and inverter LCD screen to make sure the parameters are set correctly.Once each quarter
Check inverter operation statusCheck to make sure the inverter installation is solid, no damage or deformation. When inverter running, check to make sure the sound and variables are normal. When inverter running, use thermal imager to check whether the case cooling is normal.Every six months
Clean the surfaceCheck the ambient humidity and dust around inverter, clean the inverter when necessary. See Section 5.4.2.Every six months
Check electrical connectionCheck the cable connection and inverter terminals, make sure they are connected reliably, not loose, and no damage, insulation reliable.Every six months
Check the security featuresCheck the off-on feature of inverter: use monitoring software or LCD and keyboard on the inverter, do "off" and "on" operation, to confirm its off-on feature intact. At the same time, make sure monitoring software can normally communicate with the inverter. Check the warning label on or around the inverter, if necessary replaced.Every six months

5.4.2 Maintenance Guide (Clean the Inverter)

Cleaning procedure:

  1. Disconnect the input and output switches.
  2. Wait ten minutes.
  3. Use a soft brush or a vacuum cleaner to clean the surface and the inlet and outlet of the inverter.
  4. Repeat Section 5.1 operating content.
  5. Restart the inverter.

6. Display Panel

This chapter describes the panel display and how to operate it, including the LCD display, LED indicators, and operation panel.

6.1 LED Indicators

There are three LED indicators on the panel:

  1. "Run", operation indicator, green;
  2. "Warn" recoverable fault indicator, yellow;
  3. "Fault" unrecoverable fault indicator, red.

The inverter state includes 6 states: stand-by, self-inspection, power generation, recoverable fault, and unrecoverable fault. LED indicators are on, off, or blinking. Refer to Table 6-1 for detailed states.

  • ☐: LED indicator is off;
  • (green), (yellow), (red): LED indicator is blinking at every 0.25S or 0.5S;
  • (Green), (yellow), (red): LED indicator is on.

Inverter State and LED Indicators:

Inverter state LED indicators Description
Stand-by☐ Run, ☐ Warn, ☐ FaultNo power on. All indicators off.
Self-inspection☑ Run, ☐ Warn, ☐ FaultGreen indicator blinks in every 0.25s, others off. Power on and ready for self-inspection.
Power generation☑ Run, ☐ Warn, ☐ FaultGreen indicator keeps on, others off. Grid-tied power generation.
● Run, ● Warn, ☐ Fault(1) Grid-tied power generation, but clock fault (A007); (2) Grid-tied power generation, but DC input fault (A001 or E001); (3) Grid-tied power generation, but fan fault (E006 or E012); Green and yellow indicator keeps on, others off.
Recoverable fault☐ Run, ● Warn, ☐ FaultInverter stand-by. The public grid fault (A001, A003, A004, A005 or A006); Yellow indicator blinks in every 0.5s, others off.
Unrecoverable fault☐ Run, ☐ Warn, ☑ FaultHardware or software fault (E003, E004, E005, E008, E009, E011, E013 or E015). De-couple the inverter from the system before maintenance. Red indicator blinks in every 0.5s, others off.
☐ Run, ☐ Warn, ☑ FaultCurrent-leakage or unqualified output power energy of the inverter (E007, E010, E014, E017, E018 or E020). De-couple the inverter from the system before maintenance. Red indicator keeps on, others off.
Artificial turned off● Run, ● Warn, ● FaultStop after the communication or panel command. All indicators are on.

Note: Please refer to chapter 5 and 7 for detailed fault information and troubleshooting.

6.2 Operation Panel

There are 4 buttons on the panel:

  1. "ESC": exit and return;
  2. "^" (Up arrow): back to the front page and data increasing;
  3. "V" (Down arrow): to the next page and data decreasing;
  4. "ENT": enter.

The machine can be turned on and off by pressing "ESC" and "ENT" simultaneously (about 3 seconds) for quick start-up and stop.

6.3 LCD Screen

LCD Screen and Operation Panel
Figure 6.1: Diagram of the inverter's LCD screen and operation panel, showing LED indicators and control buttons.

All information is displayed on the LCD screen. The background illumination of the LCD screen will turn off after 15 seconds of no button operation to save power, but it can be reactivated by pressing any button. Press "ENT" to enter the main interface if the background illumination is on. All parameters can be viewed and set on the interface.

There are main interface and menu interfaces on the LCD screen. The main interface is the default after power on, while menu interfaces are used to view and set parameters or perform other manual operations, such as viewing monitoring parameters, history records, system information, statistics, fault information, and setting the displayed language, time, communication address, password, and factory defaults.

Main Interface of LCD Screen
Figure 6.2: Main interface of the LCD screen, showing the status area, text parameter display area, and fault code area.

The main interface of the LCD screen displays the following:

  1. The curve displays the power changing at the current day.
  2. The words on the screen display the current key parameters of the inverter. Three lines of words are displayed at a time, but if the inverter is in operation or stand-by state, the words are rolling forward every 3s. The user can press "^" or "V" to look up the information freely.
  3. 5 states of the inverter are displayed on the screen.
  4. If the inverter is in fault or warning state, up to 8 corresponding fault codes can be displayed on the screen.

6.4 Functions Operation

Most parameters can be viewed and set through the LCD screen and operation panel.

Main Menu Flowchart
Figure 6.3: Flowchart of the main menu and sub-menus for monitoring, statistics, setup, system info, and fault info.

6.4.1 Monitoring Parameters

Press "^" and "V" in the main interface to select "Monit Param", then press "ENT" to view the parameters shown in Figure 6.4. Navigate through pages using "^" and "V", and return using "ESC".

Monitoring Parameters Display
Figure 6.4: Example display of current state monitoring parameters, including energy today (E-tod), total energy ($-tod), and input power (P-in).

6.4.2 History

Press "^" and "V" in the main interface to select "History", then press "ENT" to view the parameters shown in Figure 6.5.

History Parameters Display
Figure 6.5: Example display of history parameters, showing date, time, and fault codes (e.g., A005: Grid under freq).

There are 32 history records in total. Press "^" and "V" to review the history record and press "ESC" to exit. The numbers on the top right indicate the serial number of the record, and the numbers in the second line display the date when faults occurred and were settled. If the color of the third line illuminates, a fault is active; otherwise, the fault is resolved.

6.4.3 Statistics

Press "^" and "V" in the main interface to select "Statistics", then press "ENT" to view the parameters shown in Figure 6.6.

Statistic Information Display
Figure 6.6: Example display of the statistical menu, showing options for Lifetime and Today's statistics.

The information in Table 6-2 can be viewed in the statistical menu.

Statistic Information:
Content Detailed
LifetimeTotal operation time, total power produced, total power saved, total CO₂ reduction in lifetime
Day statisticsTotal power produced, total power saved, peak power and total CO₂ reduction in current day

6.4.4 Parameter Settings

Press "^" and "V" in the main interface to select "Setup Menu", then press "ENT" to view the parameters shown in Figure 6.7. Parameters can be set in this interface.

Setting Information Flowchart
Figure 6.7: Flowchart illustrating the setup menu options, including Address, Cash/price, Date/Time, and Language settings.
Parameters Setting:
Setting item LCD display Instruction
RS485 AddressRS485 Address 001Enter the interface and edit data using "^" or "V". Press "ENT" again for the next bit. After editing three bits, press "ENT" to save and "ESC" to exit.
User passwordUser Password 0000Enter the interface and edit data using "^" or "V". Press "ENT" again for the next bit. After editing four bits, press "ENT" to save and "ESC" to exit.
Setup CashSetup Cash Type: EUR Val/kWh: 00.50€/1 kWhEnter the interface and edit currency type and cash using "^" or "V". Press "ENT" again for the next line. After editing four bits, press "ENT" to save and "ESC" to exit. Currency types include EUR, POD, CNY, and USD.
Setup Date/TimeSetup Date/Time Date: 2012/01/15 Time: 12:14:30Enter the interface and edit date and time using "^" or "V". Press "ENT" again for the next line. After editing four bits, press "ENT" to save and "ESC" to exit.
LanguageCurr. Language: English English Dutch Chinese GermanEnter the interface and edit language using "^" or "V". Press "ENT" again to save and "ESC" to exit. The default language is English.
Select CountryCountry: Australia German Greece Denmark England Holland AustraliaEnter the interface and select country using "^" or "V". Press "ENT" again to save and "ESC" to exit.
Setup modeSetup Model: Independ Independ ParallelThe DC input mode includes "independent" and "parallel". "Independent mode" is the independent MPPT of Track A and Track B; "parallel mode" is the parallel MPPT of Track A and Track B. The default mode is "independent". The input mode setting is invisible if the inverter is in power generation. It is only available during DC power on and AC power off. Press "^" or "V" to select the setting mode and press "ENT" to save the setting or "ESC" to return. If the situation of section 6.4.8 occurs, it is necessary to switch the DC input to "parallel" mode.

6.4.5 System Information

Press "^" and "V" in the main interface to select "System Information", then press "ENT" to view the parameters shown in Figure 6.8. The system information includes "product model", "serial No.", "software version", and "certificate version".

System Information Display
Figure 6.8: Example display of system information, including Part No., Serial No., and Soft Ver.
System Version Display
Figure 6.9: Example display of system version details, including Version 1, Version 2, and MCU Version.

6.4.6 Faults

Press "^" and "V" in the main interface to review the fault history, then press "ENT" to view the sub-menu shown in Figure 6.10.

Fault Information Display
Figure 6.10: Example display of fault information, showing fault codes and descriptions (e.g., A005 Grid under freq, A001 Input under Volt).

There are 8 pieces of fault information in the record. If no faults are present, it will display "No Fault!". Refer to section 6.4.2 for more detailed information.

6.4.7 Inverter Control

Press "^" and "V" in the control interface, then press "ENT" to view the sub-menu shown in Figure 6.11.

Control Interface Display
Figure 6.11: Example display of the control menu, showing options for On/Off, Clear, Restart, and Factory settings.

Refer to the table below for detailed information:

Control item LCD display Instruction
On/Off controlOn/Off Ctrl ON OFFControl the "On/Off" through the panel. Press "^" and "V" in the control interface to select the operation. Press "ENT" to ensure the operation and press "ESC" to return.
RestartRestart Press ENT to execute. Press ESC to cancel.Restart the inverter through the panel. Save all settings and operation records. Press "ENT" to ensure restarting and the inverter will begin to self-inspect or press "ESC" to return.
Record clearClear all Record: Sure? Press ENT to execute. Press ESC to cancel.Press "ENT" to ensure clear all records or press "ESC" to return. "Record clear" clears all setting parameters through the panel, restores to factory setting, and saves all history operation records.
Restore to factoryRestore to Factory Press ENT to execute. Press ESC to cancel."Restore to factory" clears all setting parameters and history operation records through the panel, restores to the factory setting. Press "ENT" to ensure clear or press "ESC" to return.

6.4.8 Mode Settings

The default mode of the series grid-tied solar inverter is "independent". However, if the current of solar modules are joined into the inverter, it is necessary to switch the mode to "parallel".

  • Only when there is more than 100V DC voltage input, the LCD display is working, and the AC switch is off, can you query and modify the inverter DC input mode via the LCD screen and keypad.

6.5 Grid Certification Choice

When powering on the inverter by DC input for the first time or after restoring factory settings, the LCD screen will prompt as follows:

SOLAR INVERTER
Initialing......Waiting
>>>>>>>
      

After a few seconds, a list of countries will appear on the LCD screen, requiring the user to choose the country of use. Press "^" or "V" to navigate the country, then press "ENT" to complete the setting.

After determining the location, follow the user manual for proper use of the inverter. The user can change the location through the following ways: LCD Screen: MENU → Main Menu: Setup → Setup Menu: Country → Country.

The user can query the grid certification that has been set through the following ways: LCD Screen: MENU → Main Menu: System Info → System Information: Cert. Area → Certificate Area.

Comparison Table: Available Countries and their Grid Certification

No. Country Certification Remark
1GermanyVDE0126 & AR-N4105
2UKG83/G59
3AustraliaAS4777
4GreeceVDE0126
5DenmarkTF321
6HollandC10/C11
7ChinaCQC
8ThailandPEA
9OtherVDE0126

Reference Table: Grid Certification and Grid Voltage and Frequency of Some Countries

No. Country Certification Single-phase voltage Grid frequency
1GermanyVDE0126 & AR-N4105220~230V50Hz
2France
3Greece
4Turkey
5Romania
6Slovakia
7Portugal
8Poland
9Hungary
10Switzerland
11Austria
12UKG83-2/G59-3240V50Hz
13AustraliaAS4777.2 & AS4777.3 AS/NZS3100230~240V50Hz
14Singapore
15New Zealand
16Belgium
17LuxembourgC10/C11220~230V50Hz
18Holland
19DenmarkTF3.2.1220~230V50Hz
20ThailandPEA220V50Hz
21ChinaCGC/CF001220V50Hz
22ItalyENEL230V50Hz

7. Monitoring Communication

This chapter describes the communication connection between the inverter and monitoring systems (industrial master, private computers, smart phones, etc.).

The standard communication mode of iMars grid-tied solar inverter is RS485, which includes "RS485-M" and "RS485-S" ports. The RS485-M ports can communicate with private computers, smart phones, and so on. The system monitoring solution is shown in Figure 7.1.

Monitoring System of Inverter
Figure 7.1: Diagram illustrating wired and wireless monitoring system solutions for the inverter, showing connections via WiFi, GPRS, and Ethernet to various devices.

7.1 Standard Communication

Pins on Inverter Instruction:

Pin on inverter Definition
1+5VDC
2A (RS485+)
3B (RS485-)
4GND
RS485 Pin on Inverter
Figure 7.2: Diagram showing the RS485 pinout on the inverter.
Communication Connector
Figure 7.3: Image of the communication connector.

Connection steps:

  1. Weld communication cables to the RS485 terminals of the inverter as shown in Figure 7.4. Ensure the cable corresponds to the pin as shown in Table 7-1 and the welding is tight enough.
  2. According to Table 7-1, connect the communication connector pinout to the user's device, making sure the connection is correct.
  3. Please download the monitoring software "iMars WinExpert" and its operation instruction.
Detailed Connection Diagram
Figure 7.4: Detailed diagram showing the connection of communication cables to the inverter's RS485 terminals.

8. Troubleshooting

This chapter describes fault alarms and fault codes for quick troubleshooting.

Fault Code Table:

Fault code Message Instruction Fault analysis
A
A001Input UVInput undervoltagePV1 undervoltage, PV2 undervoltage
A002Bus UVBus undervoltageDC input
A003Grid UVAC undervoltageLow voltage of the public grid
A004Grid OVAC overvoltageHigh voltage of the public grid
A005Grid UFAC underfrequencyLow frequency of the public grid
A006Grid OFAC overfrequencyHigh frequency of the public grid
A007Clock FailClock alarmWrong setting
A009Cmd ShutManual shutdownStop by the operation panel or upper PC
A011Grid LossThe public grid disconnects.Check if inverter AC connection is well
E
E001Input OVInput overvoltageDC input overvoltage
E003Bus OVBus overvoltageInternal bus voltage
E004Boost FailVoltage-boost faultVoltage-boost fault of the inverter
E005Grid OCAC overcurrentInternal AC overcurrent
E006OTPOvertemperatureInternal overtemperature
E007Riso LowLow isolation impedanceLow isolation impedance of the external port system
E008IGBT drvIGBT drive protectionIGBT drive protection of the inverter
E009Int CommInternal communication faultMaster-slave DSP communication disabled. Error of master-slave DSP check bit.
E010ILeek FailHuge leakage currentHuge leakage current of the system or inverter
E011Relay FaultRelay faultInternal relay fault
E012Fan FailFan faultInternal fan fault
E013EepromMemory errorInternal memory error
E014Dc injectHigh DC injectionHigh DC injection during AC output
E015OutputShortOutput short-circuitOutput short-circuit
E018Input OCInput overcurrentDC input overcurrent
E019IncnstData consistency faultInconsistent grid voltage, frequency, leakage current or AC/DC injection
E020PowerReversedDC power reversedDC power reversed

If any problem occurs, please contact the supplier and provide the following information:

  • Model of the inverter:
  • Serial No. of the inverter:
  • System version: version 1: , version 2: , MCU software version:
  • Fault code:
  • Fault description:

9. Specifications

Detailed technical parameters for the INVT grid-tied solar inverters are provided below.

Technical Parameters:

Model Single-phase
MG750TL MG1KTL MG1K5TL MG2KTL MG3KTL
Input (DC)Max. DC voltage (V)400450450500600
Starting voltage (V)608080120120
MPPT voltage (V)50-40070-40080-410100-410120-500
Operation voltage (V)100-320121-360165-360180-360210-400
MPPT/strings per MPPT1/11/11/11/21/2
Max. DC power (W)9001200170022003300
Max input current (A)8x19x110x112x115x1
Output (AC)Max output power7501000150020003000
Voltage(V)/frequency (Hz)180~270Vac, 50Hz(47~51.5Hz)/60Hz(57~61.5Hz)
Max. AC current (A)3.64.56.5913
Power factor≥0.99 (at rated power)
Harmonic distortion<3% (at rated power)
SystemCoolingNatural cooling
Maximum efficiency96.90%97.20%97.30%97.60%97.60%
European efficiency96.00%96.10%96.30%96.50%96.50%
MPPT efficiency99.9%
Protection degreeIP65
Power consumption<1W
Isolation modeTransformerless
Protective classI
Overvoltage categoryAC:III, PV:II
Inverter topologyNon-isolated
Pollution degree3
Operation temperature-25°C~+60°C (derate after 45°C)
Relative humidity4-100%, Condensation
Max. altitude (m)<2000 (derate if the altitude >2000)
DisplayingLED/LCD, backlit display
System languageEnglish, Chinese, German, Dutch
CommunicationRS485 (standard); handheld keypad; WiFi (optional)
DC terminalBC03A/BC03B
Noise dB(A)<25
Installation modeWall installation
ProtectionInput overvoltage protection, input overcurrent protection, DC isolation monitoring, DC monitoring, grounding fault current monitoring, grid monitoring, island protection, short circuit protection, overheating protection

Note: This table provides specifications for various models. The MG5KTL model is specifically covered in this manual.

10. Warranty & Support

The INVT MG5KTL Solar Inverter comes with a 5-year warranty, ensuring reliability and peace of mind for your solar power system.

For comprehensive details regarding the warranty terms, conditions, and support procedures, please refer to the official user manual PDF available for download. This PDF contains in-depth information on all aspects of product support and service.

A detailed user manual in PDF format is available for download. This document provides extensive information on installation, operation, maintenance, and troubleshooting beyond what is covered here. View User Manual (PDF)

11. User Tips

Based on common user inquiries and product information, here are some helpful tips for your INVT MG5KTL inverter:

  • Optional Accessories: The WiFi module and CT sensors are typically sold separately and are not included with the main inverter unit. Ensure you purchase these if you require real-time monitoring or zero-export functionality.
  • Zero Export Function: If you do not wish to feed power back into the local grid, ensure you utilize the CT (Current Transformer) function. This feature allows the inverter to limit power output to match local consumption.
  • PV Panel Compatibility: For the 5000W model, the maximum recommended PV input panel power is 6000W, with a PV input range of 120-550VDC. Always verify your solar panel array specifications against these limits.
  • WiFi Connection Troubleshooting: If you encounter issues connecting to WiFi, ensure the distance between your WiFi router and the Stick Logger is under 10 meters. If the network is not found, try shortening the distance, checking your router settings, or manually entering the network ID. Avoid enterprise routers that may restrict WiFi connectivity.
  • App Monitoring: For real-time monitoring of inverter data via your smartphone, download the "SOLARMAN" app from the Apple App Store (iOS) or Google Play Store (Android). Follow the in-app instructions for registration and plant creation.

Ask a question about this manual

Ask about setup, troubleshooting, compatibility, parts, safety, or missing instructions. Manuals+ will review the question and use this page’s manual context to help answer it.

After a successful submission, we securely hash the supplied account or form email before sending it to Microsoft Advertising for conversion attribution. Privacy details.