About This Manual
Purpose
This manual describes the assembly, installation, operation and troubleshooting of this unit. Please read this manual carefully before installations and operations. Keep this manual for future reference.
Scope
This manual provides safety and installation guidelines as well as information on tools and wiring.
Safety Instructions
WARNING: This chapter contains important safety and operating instructions. Read and keep this manual for future reference.
- Before using the unit, read all instructions and cautionary markings on the unit, the batteries and all appropriate sections of this manual.
- CAUTION --To reduce risk of injury, charge only deep-cycle lead acid type rechargeable batteries. Other types of batteries may burst, causing personal injury and damage.
- Do not disassemble the unit. Take it to a qualified service center when service or repair is required. Incorrect re-assembly may result in a risk of electric shock or fire.
- To reduce risk of electric shock, disconnect all wirings before attempting any maintenance or cleaning. Turning off the unit will not reduce this risk.
- CAUTION - Only qualified personnel can install this device with battery.
- NEVER charge a frozen battery.
- For optimum operation of this inverter/charger, please follow required spec to select appropriate cable size. It's very important to correctly operate this inverter/charger.
- Be very cautious when working with metal tools on or around batteries. A potential risk exists to drop a tool to spark or short circuit batteries or other electrical parts and could cause an explosion.
- Please strictly follow installation procedure when you want to disconnect AC or DC terminals. Please refer to INSTALLATION section of this manual for the details.
- Fuse is provided as over-current protection for the battery supply.
- GROUNDING INSTRUCTIONS -This inverter/charger should be connected to a permanent grounded wiring system. Be sure to comply with local requirements and regulation to install this inverter.
- NEVER cause AC output and DC input short circuited. Do NOT connect to the mains when DC input short circuits.
- Warning!! Only qualified service persons are able to service this device. If errors still persist after following troubleshooting table, please send this inverter/charger back to local dealer or service center for maintenance.
Introduction
This is a multi-function inverter/charger, combining functions of inverter, MPPT solar charger and battery charger to offer uninterruptible power support with portable size. Its comprehensive LCD display offers user-configurable and easy-accessible button operation such as battery charging current, AC/solar charger priority, and acceptable input voltage based on different applications.
Features
- Pure sine wave inverter
- Inverter running without battery
- Built-in MPPT solar controller
- Configurable input voltage range for home appliances and personal computers via LCD setting
- Configurable battery charging current based on applications via LCD setting
- Configurable AC/Solar Charger priority via LCD setting
- Compatible to mains voltage or generator power
- Auto restart while AC is recovering
- Overload/ Over temperature/ short circuit protection
- Smart battery charger design for optimized battery performance
- Cold start function
Basic System Architecture
The following illustration shows basic application for this inverter/charger. It also includes following devices to have a complete running system: Generator or Utility, PV modules (option). Consult with your system integrator for other possible system architectures depending on your requirements. This inverter can power all kinds of appliances in home or office environment, including motor-type appliances such as tube light, fan, refrigerator and air conditioner.

Product Overview



Components
The inverter features an LCD display, status indicator, charging indicator, and fault indicator. Function buttons and a power on/off switch are also present. Connection ports include AC input/output, PV input, battery input, RS232, parallel communication (for parallel models), RS485, and grounding. It also has a WiFi module avoidance hole, RS485 communication line outlet, and battery positive/negative outlet holes.
NOTE: For parallel model installation and operation, please check the parallel installation guide for the details.
Installation
Unpacking and Inspection
Before installation, please inspect the unit. Be sure that nothing inside the package is damaged. You should have received the following items inside of package:
- The unit x 1
- User manual x 1
Preparation
Before connecting all wirings, please take off the bottom cover by removing two screws.
Mounting the Unit
Consider the following points before selecting where to install:
- Do not mount the inverter on flammable construction materials.
- Mount on a solid surface.
- Install this inverter at eye level in order to allow the LCD display to be read at all times.
- The ambient temperature should be between 0°C and 55°C to ensure optimal operation.
- The recommended installation position is to be adhered to the wall vertically.
- Be sure to keep other objects and surfaces as shown in the right diagram to guarantee sufficient heat dissipation and to have enough space for removing wires.
SUITABLE FOR MOUNTING ON CONCRETE OR OTHER NON-COMBUSTIBLE SURFACE ONLY.

Battery Connection
CAUTION: For safety operation and regulation compliance, it's requested to install a separate DC over-current protector or disconnect device between battery and inverter. It may not be requested to have a disconnect device in some applications, however, it's still requested to have over-current protection installed. Please refer to typical amperage in below table as required fuse or breaker size.
WARNING! All wiring must be performed by a qualified personnel. It's very important for system safety and efficient operation to use appropriate cable for battery connection. To reduce risk of injury, please use the proper recommended cable for battery connection.
Recommended battery cable, stripping length (L2) and tinning length (L1), terminal size:
| Model | Maximum Amperage | Battery capacity | Wire Size | Cable mm² | Terminal size(mm) | Torque value | ||
|---|---|---|---|---|---|---|---|---|
| L | W | D | ||||||
| 6.2KVA | 137A | 200AH | 2AWG | 38 | 37 | 18 | 6.4 | 2~3 Nm |
To implement battery connection:
- 6.2KVA: Make positive and negative cables based on recommended terminal size.
- Connect all battery packs as units requires. It's suggested to use recommended battery capacity.
- Insert battery cable flatly into battery connector of inverter and make sure the bolts are tightened with torque of 2-3Nm. Make sure polarity at both the battery and the inverter/charge is correctly connected and battery cables are tightly screwed to the battery connector.
AC Input/Output Connection
CAUTION!! Before connecting to AC input power source, please install a separate AC breaker between inverter and AC input power source. This will ensure the inverter can be securely disconnected during maintenance and fully protected from over current of AC input. The recommended spec of AC breaker is 50A. There are two terminal blocks with "IN" and "OUT" markings. Please do NOT mis-connect input and output connectors.
WARNING! All wiring must be performed by a qualified personnel. It's very important for system safety and efficient operation to use appropriate cable for AC input connection. To reduce risk of injury, please use the proper recommended cable size as below.
Suggested cable requirement for AC wires:
| Model | Gauge | Torque Value |
|---|---|---|
| 6.2KVA | 8 AWG | 1.4~1.6Nm |
To implement AC input/output connection:
- Before making AC input/output connection, be sure to open DC protector or disconnector first.
- Remove insulation sleeve 10mm for six conductors. And shorten phase L and neutral conductor N 3mm.
- Insert AC input wires according to polarities indicated on terminal block and tighten the terminal screws. Be sure to connect PE protective conductor (yellow-green) first.
- Then, insert AC output wires according to polarities indicated on terminal block and tighten terminal screws. Be sure to connect PE protective conductor (yellow-green) first.
- Make sure the wires are securely connected.
CAUTION: Important Be sure to connect AC wires with correct polarity. If L and N wires are connected reversely, it may cause utility short-circuited when these inverters are worked in parallel operation.
CAUTION: Appliances such as air conditioner are required at least 2~3 minutes to restart because it's required to have enough time to balance refrigerant gas inside of circuits. If a power shortage occurs and recovers in a short time, it will cause damage to your connected appliances. To prevent this kind of damage, please check manufacturer of air conditioner if it's equipped with time-delay function before installation. Otherwise, this inverter/charger will trig overload fault and cut off output to protect your appliance but sometimes it still causes internal damage to the air conditioner.
PV Connection
CAUTION: Before connecting to PV modules, please install separately a DC circuit breaker between inverter and PV modules.
WARNING! All wiring must be performed by a qualified personnel. It's very important for system safety and efficient operation to use appropriate cable for PV module connection. To reduce risk of injury, please use the proper recommended cable size as below.
| Model | Typical Amperage | Cable Size | Torque |
|---|---|---|---|
| 6.2KVA | 27A | 10 AWG | 1.4~1.6 Nm |
PV Module Selection
When selecting proper PV modules, please be sure to consider below parameters:
- Open circuit Voltage (Voc) of PV modules not exceeds max. PV array open circuit voltage of inverter.
- Open circuit Voltage (Voc) of PV modules should be higher than min. battery voltage.
Solar Charging Mode:
| INVERTER MODEL | 6.2KVA |
|---|---|
| Max. PV Array Open Circuit Voltage | 500VDC |
| PV Array MPPT Voltage Range | 60VDC~500VDC |
Take the 330Wp PV module as an example. After considering above two parameters, the recommended module configurations are listed in the table below.
| SOLAR INPUT | Q'ty of panels | Total input power | |
|---|---|---|---|
| Solar Panel Spec. (reference) 450Wp - Vmp: 34.67Vdc Imp: 13.82A - Voc: 41.25Vdc Isc: 12.98A | 3 pcs in serial | 3 pcs | 1,350 W |
| 4 pcs in serial | 4 pcs | 1,800 W | |
| 5 pcs in serial | 5 pcs | 2,250 W | |
| 6 pcs in serial | 6 pcs | 2,700 W | |
| 7 pcs in serial | 7 pcs | 3,150 W | |
| 8 pcs in serial | 8 pcs | 3,600 W | |
| 9 pcs in serial | 9 pcs | 4,050 W | |
| 10 pcs in serial | 10 pcs | 4,500 W | |
| 11 pcs in serial | 11 pcs | 4,950 W | |
| 12 pcs in serial | 12 pcs | 5,400 W | |
| 6 pieces in serial and 2 sets in parallel | 12 pcs | 5,400 W | |
| 7 pieces in serial and 2 sets in parallel | 14 pcs | 6,300 W | |
| SOLAR INPUT | Q'ty of panels | Total input power | |
| Solar Panel Spec. (reference) 550Wp - Vmp: 42.48Vdc Imp: 12.95A - Voc: 50.32Vdc Isc: 13.70A | 3 pcs in serial | 3 pcs | 1,650 W |
| 4 pcs in serial | 4 pcs | 2,200 W | |
| 5 pcs in serial | 5 pcs | 2,750 W | |
| 6 pcs in serial | 6 pcs | 3,300 W | |
| 7 pcs in serial | 7 pcs | 3,850 W | |
| 8 pcs in serial | 8 pcs | 4,400 W | |
| 9 pcs in serial | 9 pcs | 4,950 W | |
| 4 pieces in serial and 2 sets in parallel | 8 pcs | 4,400 W | |
| 5 pieces in serial and 2 sets in parallel | 10 pcs | 5,500 W | |
| 6 pieces in serial and 2 sets in parallel | 12 pcs | 6,600 W | |
PV Module Wire Connection:
- Remove insulation sleeve 10 mm for positive and negative conductors.
- Check correct polarity of connection cable from PV modules and PV input connectors. Then, connect positive pole (+) of connection cable to positive pole (+) of PV input connector. Connect negative pole (-) of connection cable to negative pole (-) of PV input connector.
- Make sure the wires are securely connected.
Schematic diagram of wiring cover disassembly hole
- Use a Phillips screwdriver to remove two screws.
- Remove the baffle.
Final Assembly
After connecting all wirings, please put the bottom cover back by screwing two screws.
Operation
Power ON/OFF
Once the unit has been properly installed and the batteries are connected well, simply press the On/Off switch (located on the bottom of the case) to turn on the unit.
Operation and Display Panel
The operation and display panel, shown in the chart below, is on the front panel of the inverter. It includes three indicators, four function keys and an LCD display, indicating the operating status and input/output power information.
LED Indicator:
| LED Indicator | Messages | ||
|---|---|---|---|
| AC / INV | Green | Solid On | Output is powered by utility in Line mode. |
| Flashing | Output is powered by battery or PV in battery mode. | ||
| CHG | Green | Solid On | Battery is fully charged. |
| Flashing | Battery is charging. | ||
| FAULT | Red | Solid On | Fault occurs in the inverter. |
| Flashing | Warning condition occurs in the inverter. |
Function Keys:
| Function Key | Description |
|---|---|
| ESC | To exit setting mode |
| UP | To go to previous selection |
| DOWN | To go to next selection |
| ENTER | To confirm the selection in setting mode or enter setting mode |
LCD Display Icons
| Icon | Function description |
|---|---|
| Input Source Information | |
| AC | Indicates the AC input. |
| PV | Indicates the PV input |
| INPUTBATT | Indicate input voltage, input frequency, PV voltage, battery voltage and charger current. |
| Configuration Program and Fault Information | |
| 88 | Indicates the setting programs. |
| Indicates the warning and fault codes. | |
| Warning: | flashing with warning code. |
| Fault: | lighting with fault code |
| Output Information | |
| OUTPUTBATTLOAD | Indicate output voltage, output frequency, load percent, load in VA, load in Watt and discharging current. |
| Battery Information | |
| CHARGING | Indicates battery level by 0-24%, 25-49%, 50-74% and 75-100% in battery mode and charging status in line mode. |
Load Information:
| OVER LOAD | Indicates overload. | |||
| Indicates the load level by 0-24%, 25-49%, 50-74% and 75-100%. | ||||
| 100% | 0%~24% | 25%~49% | 50%~74% | 75%~100% |
| 25% | ||||
Mode Operation Information:
| Indicates unit connects to the mains. | |
| Indicates unit connects to the PV panel. | |
| BYPASS | Indicates load is supplied by utility power. |
| Indicates the utility charger circuit is working. | |
| Indicates the DC/AC inverter circuit is working. |
Mute Operation:
| Indicates unit alarm is disabled. |
LCD Setting
After pressing and holding the ENTER button for 3 seconds, the unit will enter setting mode. Press "UP" or "DOWN" button to select setting programs. And then, press "ENTER" button to confirm the selection or ESC button to exit.
Setting Programs:
| Program | Description | Selectable option | |
|---|---|---|---|
| 01 | Output source priority: To configure load power source priority | Solar first | Solar energy provides power to the loads as first priority. If solar energy is not sufficient to power all connected loads, battery energy will supply power the loads at the same time. Utility provides power to the loads only when any one condition happens: Solar energy is not available, Battery voltage drops to either low-level warning voltage or the setting point in program 12. |
| Utility first (default) | Utility will provide power to the loads as first priority. Solar and battery energy will provide power to the loads only when utility power is not available. | ||
| SBU priority | Solar energy provides power to the loads as first priority. If solar energy is not sufficient to power all connected loads, battery energy will supply power to the loads at the same time. Utility provides power to the loads only when battery voltage drops to either low-level warning voltage or the setting point in program 12. | ||
| SUB priority | Solar energy is charged first and then power to the loads. If solar energy is not sufficient to power all connected loads, Utility energy will supply power to the loads at the same time. | ||
| 02 | Maximum charging current: To configure total charging current for solar and utility chargers. (Max. charging current = utility charging current + solar charging current) | 10A, 20A, 30A, 40A, 50A, 60A (default), 70A, 80A | Sets the maximum charging current. |
| 03 | AC input voltage range | Appliances (default) | If selected, acceptable AC input voltage range will be within 90-280VAC. |
| UPS | If selected, acceptable AC input voltage range will be within 170-280VAC. | ||
| Generator | If selected, acceptable AC input voltage range will be within 170-280VAC and compatible with generators. Note: Because generators are unstable, maybe the output of inverter will be unstable too. | ||
| 04 | Power saving mode enable/disable | Saving mode disable (default) | If disabled, no matter connected load is low or high, the on/off status of inverter output will not be effected. |
| Saving mode enable | If enabled, the output of inverter will be off when connected load is pretty low or not detected. | ||
| 05 | Battery type | AGM (default) | Flooded |
| User-Defined | If "User-Defined" is selected, battery charge voltage and low DC cut-off voltage can be set up in program 26, 27 and 29. | ||
| 06 | Auto restart when overload occurs | Restart disable / Restart enable (default) | Configures auto restart behavior after overload. |
| 07 | Auto restart when over temperature occurs | Restart disable / Restart enable (default) | Configures auto restart behavior after over temperature. |
| 08 | Output voltage | 220V, 230V (default), 240V | Sets the AC output voltage. |
| 09 | Output frequency | 50Hz (default), 60Hz | Sets the AC output frequency. |
| 10 | Auto bypass | manual (default), auto | When selecting "auto", if the mains power is normal, it will automatically bypass, even if the switch is off. |
| 11 | Maximum utility charging current | 2A, 10A, 20A, 30A (default), 40A, 50A, 60A, 70A, 80A | Sets the maximum charging current from utility. |
| 12 | Setting voltage point back to utility source when selecting "SBU priority" or "Solar first" in program 01. | Available options in 48V models: 44V, 45V, 46V (default), 47V, 48V, 49V, 50V, 51V, 52V, 53V, 54V, 55V. Setting range is from 44.0V to 57.2V for 48V model, but the max setting value must be less than the value of program 13. | Sets the voltage threshold for switching back to utility. |
| 13 | Setting voltage point back to battery mode when selecting "SBU priority" or "Solar first" in program 01. | Battery fully charged (default), 48V, 49V, 50V, 51V, 52V, 53V, 54V, 55V, 56V, 57V, 58V, 59V, 60V, 61V, 62V. Setting range is from 48V to full (the value of program 26-0.4V), but the max setting value must be more than the value of program 12. | Sets the voltage threshold for switching back to battery. |
| 16 | Charger source priority: To configure charger source priority | Solar first | Solar energy will charge battery as first priority. Utility will charge battery only when solar energy is not available. |
| Utility first / Solar and Utility (default) / Only Solar | Configures the priority for charging sources. If this inverter/charger is working in Battery mode or Power saving mode, only solar energy can charge battery. Solar energy will charge battery if it's available and sufficient. | ||
| 18 | Buzzer mode | Mode1 (Buzzer mute) | Mutes all buzzer sounds. |
| Mode2 | The buzzer sounds when the input source changes or there is a specific warning or fault. | ||
| Mode3 | The buzzer sounds when there is a specific warning or fault. | ||
| Mode4 (default) | The buzzer sounds when there is a fault. | ||
| 19 | Auto return to default display screen | Return to default display screen (default) | If selected, no matter how users switch display screen, it will automatically return to default display screen (Input voltage /output voltage) after no button is pressed for 1 minute. |
| Stay at latest screen | If selected, the display screen will stay at latest screen user finally switches. | ||
| 20 | Backlight control | Backlight on (default) | Keeps the LCD backlight on. |
| Backlight off | Turns the LCD backlight off. | ||
| 23 | Overload bypass: When enabled, the unit will transfer to line mode if overload occurs in battery mode. | Bypass disable / Bypass enable (default) | Enables or disables the overload bypass function. |
| 25 | Modbus ID Setting | Modbus ID Setting Range: 001 (default)~247 | Sets the Modbus ID for communication. |
| 26 | Bulk charging voltage (C.V voltage) | 48V models default setting: 56.4V. If self-defined is selected in program 5, this program can be set up. Setting range is from 48.0V to 62.0V for 48V model. But the setting value must be more than or equal the value of program 27. Increment of each click is 0.1V. | Sets the bulk charging voltage for the battery. |
| 27 | Floating charging voltage | 48V models default setting: 54.0V | Sets the floating charging voltage for the battery. |
| 28 | AC output mode | Single: This inverter is used in single phase application. | Configures the inverter for single-phase operation. |
| Parallel: This inverter is operated in parallel system. (Need hardware support) | Configures the inverter for parallel operation. | ||
| L1 phase / L2 phase / L3 phase | Configures the inverter for specific phases in a 3-phase application. | ||
| 29 | Low DC cut-off voltage | 48V models default setting: 42.0V. If self-defined is selected in program 5, this program can be set up. Setting range is from 40.0V to 54.0V for 48V model. The setting value must be less than the value of program 12. Increment of each click is 0.1V. Low DC cut-off voltage will be fixed to setting value no matter what percentage of load is connected. | Sets the low DC cut-off voltage to protect the battery. |
| 32 | Bulk charging time (C.V stage) | Automatically (Default) / 5 min / 900 min. The setting range is from 0 min to 900 min. Increment of each click is 5 min. | Sets the duration for bulk charging. |
| 33 | Battery equalization | Battery equalization enable / Battery equalization disable (default) | Enables or disables battery equalization. |
| 34 | Battery equalization voltage | 48V models default setting is 58.4V. Setting range is from 48V ~ 64V. Increment of each click is 0.1V. | Sets the voltage for battery equalization. |
| 35 | Battery equalized time | 60min (default). Setting range is from 0min to 900min. Increment of each click is 5min. | Sets the duration for battery equalization. |
| 36 | Battery equalized timeout | 120min (default). Setting range is from 0min to 900 min. Increment of each click is 5 min. | Sets the timeout for battery equalization. |
| 37 | Equalization interval | 30days (default). Setting range is from 1 to 90 days. Increment of each click is 1 day. | Sets the interval between battery equalization cycles. |
| 39 | Equalization activated immediately | Enable / Disable (default) | Activates battery equalization immediately. |
| 46 | Maximum discharge current protection | Default OFF / 100% | Disables or enables current discharge protection. Only available in Single model. |
Display Setting
The LCD display information will be switched in turns by pressing "UP" or "DOWN" key. The selectable information is switched as below order: input voltage, input frequency, PV voltage, MPPT charging current, MPPT charging power, charging current, charging power, battery voltage, output voltage, output frequency, load percentage, load in VA, load in Watt, DC discharging current, main CPU Version and second CPU Version.
Operating Mode Description:
| Operation mode | Description | LCD display |
|---|---|---|
| Standby mode / Power saving mode Note: *Standby mode: The inverter is not turned on yet but at this time, the inverter can charge battery without AC output. *Power saving mode: If enabled, the output of inverter will be off when connected load is pretty low or not detected. | No output is supplied by the unit but it still can charge batteries. | Charging by utility and PV energy. |
| Charging by utility. | ||
| Charging by PV energy. | ||
| No charging. | ||
| Fault mode Note: *Fault mode: Errors are caused by inside circuit error or external reasons such as over temperature, short circuited and so on. | PV energy and utility can charge batteries. | Charging by utility and PV energy. |
| Charging by utility. | ||
| Charging by PV energy. | ||
| Line Mode | The unit will provide output power from the mains. It will also charge the battery at line mode. | Charging by utility and PV energy. |
| Charging by utility. | ||
| If "solar first" is selected as output source priority and solar energy is not sufficient to provide the load, solar energy and the utility will provide the loads and charge the battery at the same time. | ||
| If "SUB" is selected as output source priority and battery is connected, solar energy will charge battery as first priority. If solar energy is sufficient for charging, solar and the utility will provide the loads. | ||
| Battery Mode | The unit will provide output power from battery and PV power. | Power from battery and PV energy. |
| PV energy will supply power to the loads and charge battery at the same time. | ||
| Power from battery only. |
Battery Equalization
Equalization function is added into the charge controller. It reverses the buildup of negative chemical effects like stratification, a condition where acid concentration is greater at the bottom of the battery than at the top. Equalization also helps to remove sulfate crystals that might have built up on the plates. If left unchecked, this condition, called sulfation, will reduce the overall capacity of the battery. Therefore, it's recommended to equalize battery periodically.
How to Apply Equalization Function
You must enable battery equalization function in monitoring LCD setting program 33 first. Then, you may apply this function in device by either one of following methods:
- Setting equalization interval in program 37.
- Active equalization immediately in program 39.
When to Equalize
In float stage, when the setting equalization interval (battery equalization cycle) is arrived, or equalization is active immediately, the controller will start to enter Equalize stage.
Equalize charging time and timeout
In Equalize stage, the controller will supply power to charge battery as much as possible until battery voltage raises to battery equalization voltage. Then, constant-voltage regulation is applied to maintain battery voltage at the battery equalization voltage. The battery will remain in the Equalize stage until setting battery equalized time is arrived. However, in Equalize stage, when battery equalized time is expired and battery voltage doesn't rise to battery equalization voltage point, the charge controller will extend the battery equalized time until battery voltage achieves battery equalization voltage. If battery voltage is still lower than battery equalization voltage when battery equalized timeout setting is over, the charge controller will stop equalization and return to float stage.
Setting for Lithium Battery
Lithium Battery Connection
If choosing a lithium battery for the inverter, you are allowed to use the lithium battery only which we have configured. There are two connectors on the lithium battery, RS485 port of BMS and power cable.
Please follow below steps to implement lithium battery connection:
- Assemble battery terminal based on recommended battery cable and terminal size (same as Lead acid, see section Lead-acid Battery connection for details).
- Connect the end of RS485 port of battery to BMS(RS485) communication port of inverter.
Lithium battery communication and setting
If choosing a lithium battery, make sure to connect the BMS communication cable between the battery and the inverter. This communication cable delivers information and signal between the lithium battery and the inverter. This information is listed below:
- Re-configure charging voltage, charging current and battery discharge cut-off voltage according to the lithium battery parameters.
- Have the inverter start or stop charging according to the status of the lithium battery.
Connect the end of RS485 of battery to RS485 communication port of inverter:
Make sure the lithium battery RS485 port connects to the inverter is Pin to Pin, the communication cable is inside of package and the inverter RS485 port pin assignment shown as below:
| Pin number | RS485 Port |
|---|---|
| PIN1 | RS485-B |
| PIN2 | RS485-A |
| PIN7 | RS485-A |
| PIN8 | RS485-B |
LCD setting for Lithium Battery:
After connecting, you need to finish and confirm some settings as follow:
| Program | Description | Selectable option | |
|---|---|---|---|
| 05 | Battery type | AGM (default) / Flooded / User-Defined / Standard communication Protocol form inverter supplier / Support PYLON US2000 Protocol / Customized Protocol or Support FOX ESS Lithium Battery Protocol / Customized Protocol | Selects the battery type. |
| 43 | Setting SOC point back to utility source when selecting "SBU priority" or "Solar first" in program 01 | Default 50%, 5%~50% Settable | Sets the State of Charge (SOC) point for switching to utility. |
| 44 | Setting SOC point back to battery mode when selecting "SBU priority" or "Solar first "in program 01 | Default 95%, 60%~100% Settable | Sets the SOC point for switching to battery. |
| 45 | Low DC cut-off SOC | Default 20%, 3%~30% Settable | Sets the low DC cut-off SOC to protect the battery. |
Note: Program 43/44/45 are only available with successful communication, they will replace the Program 12/13/29 function, at the same time, program 12/13/29 become unavailable.
LCD Display for Lithium Battery:
If communication between the inverter and battery is successful, there is some information showing on the LCD as follow:
| Item | Description | LCD display | |
|---|---|---|---|
| 1 | Communication successful icon | Li will be flashing | Indicates successful communication. |
| 2 | Max lithium battery charging voltage | Shows the maximum charging voltage. | |
| 3 | Max lithium battery charging current | Shows the maximum charging current. | |
| 4 | Lithium battery discharging is forbidden | Li will flash once every 1 second | Indicates discharging is forbidden. |
| 5 | Lithium battery charging is forbidden | Li will flash once every 2 second | Indicates charging is forbidden. |
| 6 | Lithium battery SOC(AH) | Shows the State of Charge in Amp-hours. | |
| 7 | Lithium battery SOC(%) | Shows the State of Charge in percentage. |
Setting for PYLON US2000 lithium battery
1). PYLONTECH US2000 lithium battery setting:
Dip Switch: There are 4 Dip Switches that sets different baud rate and battery group address. If switch position is turned to the "OFF" position, it means "0". If switch position is turned to the "ON" position, it means "1". Dip 1 is "ON" to represent the baud rate 9600. Dip 2, 3 and 4 are reserved for battery group address. Dip switch 2, 3 and 4 on master battery (first battery) are to set up or change the group address. NOTE: "1" is upper position and "0" is bottom position.
Specifications
Table 1 Line Mode Specifications
| INVERTER MODEL | 6.2KVA |
|---|---|
| Input Voltage Waveform | Sinusoidal (utility or generator) |
| Nominal Input Voltage | 230Vac |
| Low Loss Voltage | 170Vac±7V (UPS) 90Vac±7V (Appliances) |
| Low Loss Return Voltage | 180Vac±7V (UPS); 100Vac±7V (Appliances) |
| High Loss Voltage | 280Vac±7V |
| High Loss Return Voltage | 270Vac±7V |
| Max AC Input Voltage | 300Vac |
| Nominal Input Frequency | 50Hz / 60Hz (Auto detection) |
| Low Loss Frequency | 40±1Hz |
| Low Loss Return Frequency | 42±1Hz |
| High Loss Frequency | 65±1Hz |
| High Loss Return Frequency | 63±1Hz |
| Output Short Circuit Protection | Line mode: Circuit Breaker Battery mode: Electronic Circuits |
| Efficiency (Line Mode) | >95% (Rated R load, battery full charged) |
| Transfer Time | 10ms typical (UPS); 20ms typical (Appliances) |
| Output power derating: When AC input voltage drops to 95V or 170V depending on models, the output power will be derated. |
Table 2 Inverter Mode Specifications
| INVERTER MODEL | 6.2KVA |
|---|---|
| Rated Output Power | 6.2KVA/6.2KW |
| Output Voltage Waveform | Pure Sine Wave |
| Output Voltage Regulation | 230Vac±5% |
| Output Frequency | 60Hz or 50Hz |
| Peak Efficiency | 94% |
| Surge Capacity | 2* rated power for 5 seconds |
| Nominal DC Input Voltage | 48Vdc |
| Cold Start Voltage | 46.0Vdc |
| Low DC Warning Voltage | @ load < 20%: 44.0Vdc |
| @ 20% ≤ load < 50%: 42.8Vdc | |
| @ load ≥ 50%: 40.4Vdc | |
| Low DC Warning Return Voltage | @ load < 20%: 46.0Vdc |
| @ 20% ≤ load < 50%: 44.8Vdc | |
| @ load ≥ 50%: 42.4Vdc | |
| Low DC Cut-off Voltage | @ load < 20%: 42.0Vdc |
| @ 20% ≤ load < 50%: 40.8Vdc | |
| @ load ≥ 50%: 38.4Vdc |
Table 3 Charge Mode Specifications
| Utility Charging Mode | |||
|---|---|---|---|
| INVERTER MODEL | 6.2KVA | ||
| Max Charging Current (PV+AC) | 120Amp (@ VI/P=230Vac) | ||
| MaxCharging Current (AC) | 80Amp (@ VI/P=230Vac) | ||
| Bulk Charging Voltage | Flooded Battery | 58.4Vdc | |
| AGM / Gel Battery | 56.4Vdc | ||
| Floating Charging Voltage | 54Vdc | ||
| Overcharge Protection | 63Vdc | ||
| Charging Algorithm | 3-Step | ||
Table 4 General Specifications
| INVERTER MODEL | 6.2KVA |
|---|---|
| Safety Certification | CE |
| Operating Temperature Range | -10°C to 55°C |
| Storage temperature | -15°C~60°C |
| Humidity | 5% to 95% Relative Humidity (Non-condensing) |
| Dimension (D*W*H), mm | 450x300x130 |
| Net Weight, kg | 9.6 |
Troubleshooting
Fault Reference Code:
| Fault Code | Fault Event | Icon on |
|---|---|---|
| 01 | Over temperature of inverter module | 01 |
| 02 | Over temperature of DCDC module | 02 |
| 03 | Battery voltage is too high | 03 |
| 04 | Over temperature of PV module | 04 |
| 05 | Output short circuited. | 05 |
| 06 | Output voltage is too high. | 06 |
| 07 | Overload time out | 07 |
| 08 | Bus voltage is too high | 08 |
| 09 | Bus soft start failed | 09 |
| 10 | PV over current | 10 |
| 11 | PV over voltage | 11 |
| 12 | DCDC over current | 12 |
| 13 | Over current or surge | 13 |
| 14 | Bus voltage is too low | 14 |
| 15 | Inverter failed (Self-checking) | 15 |
| 16 | Over DC voltage in AC output | 16 |
| 17 | Reserved | |
| 18 | Op current offset is too high | 18 |
| 19 | Inverter current offset is too high | 19 |
| 20 | DC/DC current offset is too high | 20 |
| 21 | PV current offset is too high | 21 |
| 22 | Output voltage is too low | 22 |
| 23 | Inverter negative power | 23 |
Warning Indicator:
| Warning Code | Warning Event | Audible Alarm | Icon flashing |
|---|---|---|---|
| 02 | Temperature is too High | Beep three times every second | 02 |
| 04 | Low battery | Beep once every second | 04 |
| 07 | Overload | Beep once every 0.5 second | 07 |
| 10 | Output power derating | Beep twice every 3 seconds | 10 |
| 15 | PV energy is low | Beep twice every 3 seconds | 15 |
| 19 | Lithium Battery communication is failed | Beep once every 0.5 second | 19 |
| 20 | Battery low and it isn't up to the setting value of program 13 | Beep twice every 3 seconds | 20 |
| E9 | Battery equalization | None | E9 |
| bP | Battery is not connected | None | bP |
Troubleshooting Table:
| Problem | LCD/LED/Buzzer | Explanation / Possible cause | What to do |
|---|---|---|---|
| Unit shuts down automatically during startup process. | LCD/LEDs and buzzer will be active for 3 seconds and then complete off. | The battery voltage is too low | 1. Re-charge battery. 2. Replace battery. |
| No response after power on. | No indication. | 1. The battery voltage is far too low. 2. Battery polarity is connected reversed. | 1. Check if batteries and the wiring are connected well. 2. Re-charge battery. 3. Replace battery. |
| Input voltage is displayed as 0 on the LCD and green LED is flashing. | Input protector is tripped | Check if AC breaker is tripped and AC wiring is connected well. | |
| Mains exist but the unit works in battery mode. | Green LED is flashing. | Insufficient quality of AC power. (Shore or Generator) | 1. Check if AC wires are too thin and/or too long. 2. Check if generator (if applied) is working well or if input voltage range setting is correct. (UPS→Appliance) |
| Green LED is flashing. | Set "Solar First" as the priority of output source. | Change output source priority to Utility first. | |
| When the unit is turned on, internal relay is switched on and off repeatedly. | LCD display and LEDs are flashing | Battery is disconnected. | Check if battery wires are connected well. |
| Fault code 07 | Overload error. The inverter is overload 110% and time is up. | Reduce the connected load by switching off some equipment. | |
| Fault code 05 | Output short circuited. | Check if wiring is connected well and remove abnormal load. | |
| Fault code 02 | Internal temperature of inverter component is over 100°C. | Check whether the air flow of the unit is blocked or whether the ambient temperature is too high. | |
| Buzzer beeps continuously and red LED is on. | Fault code 03 | Battery is over-charged. | Return to repair center. |
| The battery voltage is too high. | Check if spec and quantity of batteries are meet requirements. | ||
| Fault code 06/22 | Output abnormal (Inverter voltage below than 190Vac or is higher than 260Vac) | 1. Reduce the connected load. 2. Return to repair center | |
| Fault code 08/09/15 | Internal components failed. | Return to repair center. | |
| Fault code 13 | Over current or surge. | Restart the unit, if the error happens again, please return to repair center. | |
| Fault code 14 | Bus voltage is too low. | ||
| Fault code 16 | Output voltage is unbalanced. | ||
| Another fault code | If the wires is connected well, please return to repair center. |
Parallel Installation Guide
1. Instruction
This inverter can be used in parallel with two different operation modes.
- Parallel operation in single phase with up to 12 units.
- Maximum 12 units work together to support three-phase equipment. 10 units support one phase maximum.
2. Package Contents
In parallel kit, you will find the following items in the package:
- Parallel communication cable
3. Mounting the Unit
When installing multiple units, please follow below chart.

NOTE: For proper air circulation to dissipate heat, allow a clearance of approx. 20 cm to the side and approx. 50 cm above and below the unit. Be sure to install each unit in the same level.
4. Wiring Connection
NOTICE: It's requested to connect to battery for parallel operation. The cable size of each inverter is shown as below:
Recommended battery cable and terminal size for each inverter:
| Model | Wire Size | Cable mm² | Terminal size(mm) | Torque value | ||
|---|---|---|---|---|---|---|
| L | W | D | ||||
| 6.2KVA | 2AWG | 38 | 37 | 18 | 6.4 | 2~3 Nm |
WARNING: Be sure the length of all battery cables is the same. Otherwise, there will be voltage difference between inverter and battery to cause parallel inverters not working.
Recommended AC input and output cable size for each inverter:
| Model | AWG no. | Torque |
|---|---|---|
| 6.2KVA | 8 AWG | 1.4~1.6Nm |
You need to connect the cables of each inverter together. Take the battery cables for example: You need to use a connector or bus-bar as a joint to connect the battery cables together, and then connect to the battery terminal. The cable size used from joint to battery should be X times cable size in the tables above. "X" indicates the number of inverters connected in parallel. Regarding AC input and output, please also follow the same principle.
CAUTION!! Please install the breaker at the battery and AC input side. This will ensure the inverter can be securely disconnected during maintenance and fully protected from over current of battery or AC input. The recommended mounted location of the breakers is shown in the figures in Point 5.
Recommended breaker specification of battery for each inverter:
| Model | 1 unit* |
|---|---|
| 6.2KVA | 100A/60VDC |
*If you want to use only one breaker at the battery side for the whole system, the rating of the breaker should be X times current of 1 unit. "X" indicates the number of inverters connected in parallel.
Recommended breaker specification of AC input with single phase:
| Model | 2 units | 3 units | 4 units | 5 units | 6 units | 7 units | 8 units | 9 units | 10 units | 11 units | 12 units |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 6.2KVA | 100A | 150A | 200A | 250A | 300A | 350A | 400A | 450A | 500A | 550A | 600A |
Note1: Also, you can use 40A breaker (50A for 6.2KVA) for only 1 unit, and each inverter has a breaker at its AC input.
Recommended battery capacity:
| Inverter parallel numbers | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Battery Capacity | 400AH | 600AH | 800AH | 1000AH | 1200AH | 1400AH | 1600AH | 1800AH | 2000AH | 2200AH | 2400AH |
WARNING! Be sure that all inverters will share the same battery bank. Otherwise, the inverters will transfer to fault mode.
Communicating with battery BMS in parallel system:
- Only support common battery installation.
- Use RJ45 cable to connect any one of inverters (no need to connect to a specific inverter) and Lithium battery.
Simply set this inverter battery type to "Li 2" in LCD program 5. Others should be default value "AGM".
Note: Make sure only one inverter is connected RJ45 cable and only the one is set as Lithium in LCD program 5.
5. Parallel Operation in Single phase
Two inverters in parallel: Power Connection
Communication Connection
Three inverters in parallel: Power Connection
Four inverters in parallel: Power Connection
Communication Connection
Six inverters in parallel: Power Connection
Communication Connection
Note: Nmax=12units.
6. Support 3-phase equipment
One inverter in each phase: Power Connection
Communication Connection
Three inverters in each phase: Power Connection
Note: It's up to customer's demand to pick 10 inverters on any phase. P1: L1-phase, P2: L2-phase, P3: L3-phase. N=N1+N2+N3, Nmax=12units. N1max=10 is in one phase and one inverter for the other two phases (N2=N3=1).
N1max=N2max=9units is in two phases and one inverter for the one phase (N3=1): Power Connection
Communication Connection
7. PV Connection
Please refer to user manual of single unit for PV Connection.
CAUTION: Each inverter should connect to PV modules separately.
8. LCD Setting and Display
Setting Program:
| Program | Description | Selectable option | |
|---|---|---|---|
| 28 | AC output mode | Single: This inverter is used in single phase application. | Parallel: This inverter is operated in parallel system. (Need hardware support) |
| L1 phase | The inverter is operated in L1 phase in 3-phase application | ||
| L2 phase / L3 phase | The inverter is operated in L2 phase in 3-phase application / The inverter is operated in L3 phase in 3-phase application | ||
| 30 | PV judge condition (Only apply for setting "Solar first" in program 1: Output source priority) | One Inverter (Default) | When "ONE" is selected, as long as one of inverters has been connected to PV modules and PV input is normal, parallel or 3-phase system will continue working according to rule of "solar first" setting. For example, two units are connected in parallel and set "SOL" in output source priority. If one of two units has connected to PV modules and PV input is normal, the parallel system will provide power to loads from solar or battery power. If both of them are not sufficient, the system will provide power to loads from utility. |
| All of Inverters | When "ALL" is selected, parallel or 3-phase system will continue working according to rule of "solar first" setting only when all of inverters are connected to PV modules. For example, two units are connected in parallel and set "SOL" in output source priority. When selecting "ALL" in program 30, it's necessary to have all inverters connected to PV modules and PV input is normal to allow the system to provide power to loads from solar and battery power. Otherwise, the system will provide power to loads from utility. |
9. Commissioning
Parallel in single phase:
Step 1: Check the following requirements before commissioning:
- Correct wire connection
- Ensure all breakers in Line wires of load side are open and each Neutral wires of each unit are connected together.
Step 2: Turn on each unit and set "PAL" in LCD setting program 28 of each unit. And then shut down all units. NOTE: It's necessary to turn off switch when setting LCD program. Otherwise, the setting can not be programmed.
Step 3: Turn on each unit.
NOTE: Master and slave units are randomly defined. If it is master the icon P blinks, if it is slave the icon P normally on.
Step 4: Switch on all AC breakers of Line wires in AC input. It's better to have all inverters connect to utility at the same time. If detecting AC connection, they will work normally.
Step 5: If there is no more fault alarm, the parallel system is completely installed.
Step 6: Please switch on all breakers of Line wires in load side. This system will start to provide power to the load.
User Tips
- For optimal performance and longevity, ensure all battery cables are of the same length and material type when operating in parallel.
- Regularly check the ambient temperature around the inverter to prevent overheating, which can trigger fault codes.
- When setting up for lithium batteries, always connect the BMS communication cable and configure the correct battery type in the LCD settings.
Frequently Asked Questions
- Q: Can this inverter charge batteries in parallel over 3 phases?
- A: Yes, the PowMr Parallel Hybrid Solar Inverter supports parallel operation for up to 12 units and can be configured to support 3-phase equipment. This allows for charging batteries in parallel across a 3-phase system.
Warranty & Support
For technical support or maintenance, please contact:
- Brand: PowMr
- Manufacturer: SHENZHEN HEHEJIN INDUSTRIAL CO.,LTD
- Tel/Fax: +86 755-28219903
- Email: support@powmr.com
- Website: www.powmr.com
- Address: Henggang Street, Longgang District, Shenzhen, Guangdong, China
If errors persist after following the troubleshooting guide, please send your inverter back to your local dealer or service center for maintenance.
You can also refer to the official user manual PDF for more detailed guides and documents: View User Manual (PDF)