EARUELETRIC ATS

Contents

EARU Electric ATS Dual Power Automatic Transfer Switch User Manual

Model: ATS | Brand: EARUELETRIC

1. Introduction

The dual power automatic switch is a newly developed miniature household power switch, which is mainly used to test whether the main power supply or standby power supply is normal. When the normal power supply is abnormal, the standby power supply starts to work immediately, which ensures the continuity, reliability and safety of power supply. This product is specially designed for household rail installation and is specially used for PZ30 distribution box.

The dual power automatic switch is suitable for emergency power supply systems with 50 or 60Hz and rated 400V AC. ATS has the characteristics of solid structure, reliable conversion, convenient installation and maintenance and long service life. It is widely used in various occasions where power failure cannot be sustained, and can be operated by electricity or manually. ATS is composed of TSE and controller. According to IEC60947-6-1, Part 6-1: multifunctional equipment and switchgear is formulated. It can be seen that ATS is the most qualified low-voltage switchgear and control device.

EARU Electric ATS Dual Power Automatic Transfer Switch with manual/automatic free switching and dual power conversion
Product overview showing manual/automatic switching and dual power conversion options.
Video demonstrating the product, its manual, and automatic switching functionality.

2. Safety Information

Please read and understand all safety instructions before installing, operating, or maintaining this device. Failure to follow these instructions may result in serious injury or property damage.

  • Installation and wiring must be performed by qualified professionals.
  • Always disconnect all power supplies before performing any work on the ATS.
  • Ensure proper grounding to prevent electrical shock.
  • Do not operate the device if it is damaged or shows signs of malfunction.
  • Keep the device away from moisture, dust, and corrosive environments.
  • Verify all connections are secure and correct before applying power.

3. Product Overview

Key Features:

  • Integrated Design: Small volume and light weight for easy integration.
  • Industrial Silver Contact: Enhances product lifespan and reliability.
  • Passive Signal Output: Allows connection to external signal lights for remote observation.
  • Rail Mounted Installation: Features a fixed buckle for easy and secure installation.
  • Fast Switching Speed: Realizes uninterrupted power supply switching function, typically less than 8ms.
Features of EARU Electric ATS Dual Power Automatic Transfer Switch: Integrated design, industrial silver contact, passive signal output, rail mounted installation
Key features of the ATS device.

Components and Indicators:

Labeled diagram of EARU Electric ATS Dual Power Automatic Transfer Switch components including main terminals, manual handle, power indicators, and signal outputs
Labeled diagram of the ATS components and terminals.
  1. Status position indication
  2. Main power terminal and passive signal (AC220V)
  3. Manual/automatic switch
  4. Manual handle
  5. Main terminal of common power side
  6. Main terminal of standby power side
  7. Main terminal of load connection side
  8. A power indicator
  9. B power indicator
  10. Standby power terminal and passive signal (AC220V)

4. Specifications

General Parameters:

Specification Value
Rated current le (A)16, 20, 25, 32, 40, 50, 63, 80, 100
Insulation voltage UiAC690V, 50Hz
Rated voltage UeAC400V, 50Hz
ClassificationPC class: can be manufactured and withstood without short-circuit current
Utilization categoryAC-33iB, AC-31B
Pole No.2P, 3P, 4P
Weight (kg)1.7 (2P), 2.1 (3P), 2.6 (4P)
Electrical Life2000 times; Manual operation: 5000 times
Rated short circuit current Iq50kA
Short circuit protection device (fuse)RT16-00-63A
Rated impulse withstand voltage8kV
Control circuitRated control voltageUs: AC220V/50Hz; Normal working conditions: 85-110%Us
Auxiliary circuit2 relays, each with two sets of contact converter capacity: AC220V/50HZ le = 5y
Conversion time of contactor<50ms
Operation conversion time<50ms
Return conversion time<50ms
Power off time<50ms
Product dimensions and parameters table for EARU Electric ATS Dual Power Automatic Transfer Switch
Product dimensions and a summary of key parameters.

Specific Configurations:

Specifications City Grid-Generator City Grid-City Grid City Grid-PV Energy
Main Power SupplyCity PowerCity PowerPV Solar Energy
Standby Power SupplyGeneratorCity PowerCity Power
Transfer SpeedCity Power to Generator <8ms
Generator to City Power <8ms
City Power to City Power <8ms
City Power to City Power <8ms
Solar Energy to City Power <8ms
City Power to Solar Energy <8ms
Rated Current125A
Rated Voltage220/230VAC
Rated Frequency50/60Hz
Rated Short Circuit Current Iq50KA
Electrical Life2000 times; Manual operation: 5000 times
Conversion Time of Contactor<50ms
Operation Conversion Time<50ms
Return Conversion Time<50ms
Power Off Time<50ms
Detailed specifications table for different power source configurations of the ATS switch
Detailed specifications for various power supply configurations.

5. Setup and Installation

5.1 Normal Operation Time and Installation Conditions

5.1.1 Ambient Air Temperature

The maximum temperature shall not exceed 40°C, the minimum temperature shall not be lower than -5°C, and the average temperature within 24 hours shall not be higher than 35°C.

5.1.2 Altitude

The altitude of the installation site should not be higher than 2000m.

5.1.3 Atmospheric Conditions

When the maximum temperature reaches 40°C, the relative humidity of the installation site should not exceed 50%; when the temperature is the minimum temperature -5°C, the relative humidity is higher, for example, the temperature is 25°C, and the relative humidity is 90%. Due to the temperature change, special measures should be taken to deal with the occasional condensation on the surface of the product.

5.1.4 Pollution Grade

The pollution grade of ATS conforms to grade 3 specified in IEC60947-6-1.

5.1.5 Installation Category

The installation type of ATS conforms to the category specified in IEC60947-6-1.

5.1.6 Installation Conditions

ATS can be installed vertically in control cabinet or distribution cabinet. Make sure the installation distance meets the requirements in Figure 8 (Overall and installation dimension of 100).

5.2 Installation and Wiring

7.1 Ensure that professionals read this manual before installation and wiring.

7.2 Please check the integrity of ATS before installation, then open and close ATS with the operating handle, check the flexibility of transmission device and detect the load generation and disconnection conditions of common and standby power supplies at each stage.

7.3 See the figures below for the correct installation steps. The trademark is in front of the product. If the installation cannot be carried out according to the correct procedures due to wiring and other reasons, please contact us. The safe distances S1, S2 should not be lower than the labels in Figure 8. (See figure below for details)

7.4 Detection control voltage: 50Hz, AC220V. The coil in the control circuit cannot be too long. The cross-sectional area of copper wire should not be greater than 2.0mm².

7.5 According to the installation requirements of power distribution system, please provide appropriate circuit breakers to ensure the safety of staff and equipment.

Wiring Diagrams:

Internal wiring diagram for ATS switch (Figure 1)
Figure 1: Internal wiring diagram. K1: manual/automatic selector switch, K2, K3: internal valve position switch, J1: common 220V A power relay, J2: standby 220V B power relay, 1: passive signal output of A power supply, 2: passive signal output of B power supply.
Controller wiring diagram for ATS switch (Figure 2)
Figure 2: Controller wiring diagram.
100/2P wiring diagram for ATS switch (Figure 3)
Figure 3: 100/2P wiring diagram.
100/3P wiring diagram for ATS switch (Figure 4)
Figure 4: 100/3P wiring diagram.
100/4P wiring diagram for ATS switch (Figure 5)
Figure 5: 100/4P wiring diagram.
Timing switching connection mode for ATS switch (Figure 6)
Figure 6: Timing switching connection mode.
Special connection mode of photovoltaic inverter for ATS switch (Figure 7)
Figure 7: Special connection mode of photovoltaic inverter.
Overall and installation dimension of 100 for ATS switch (Figure 8)
Figure 8: Overall and installation dimension of 100. Safe distance: S1: ≥30mm, S2: ≥203mm.
Correct installation direction of 100 for ATS switch (Figure 9)
Figure 9: Correct installation direction of 100.

6. Operation

6.1 Manual/Automatic Operation

ATS can guarantee the performance of power generation and power failure during circuit operation, but for manual operation, ATS cannot guarantee the above performance due to the difference of power generation and power failure speed or operator. During manual power generation and power failure, excessive silver alloy loss may occur. Therefore, when all power supplies are cut off to check and maintain the operating system and contacts, it is only necessary to pull the selector switch to the manual position. Under normal circumstances, please pull the selector switch to the automatic position. When operating manually, pull the selector switch to the manual position. After the manual operation is completed, pull the selector switch from the manual position to the automatic position.

Automatic switching after power failure, demonstrating uninterrupted power supply switching function
The ATS provides automatic switching after power failure, ensuring uninterrupted power supply.

7. Maintenance

7.1 Maintenance, Inspection and Storage

8.1 Maintenance and inspection shall be operated by professionals and all power supplies shall be cut off in advance.

8.2 In order to ensure the good performance of ATS, the first maintenance and inspection shall be carried out within 6 months after use, and shall be maintained and inspected at least once a year. In harsh installation conditions, the frequency of maintenance and inspection should be increased.

7.2 Maintenance and Inspection Items

  • Please remove dust and dirt in case of failure.
  • Please check whether the contact parts of the electrical contacts are deformed and damaged, and remove burnt metal particles attached to and around the surface.
  • Rust, acidification and dust on the contact surface may lead to poor contact. Please operate manually many times and measure the contact resistance if necessary.
  • Due to long-term moisture and suspension, please dry ATS before use. After removing dust and dirt, use a 500V megohmmeter to measure the insulation resistance between normal supply, alternating power supply, load side bar, including live parts and metal plate. And the insulation resistance should not be less than 10M.
  • ATS shall be stored in an environment equivalent to the normal working environment, with dust-proof, moisture-proof and collision-proof measures.

8. Troubleshooting

8.1 Matters Needing Attention

8.1.1 Control Circuit

ATS instantly becomes active. After the conversion is completed, the coil in the control circuit will be disconnected by the internal converter. Under the rated voltage of 80%-110%, the coil can operate normally. Low voltage will cause coil heating and even spontaneous combustion.

General Troubleshooting Tips:

  • If the device fails to switch, check the power supply to both sources.
  • Ensure all wiring connections are secure and free from corrosion.
  • Verify that the manual/automatic switch is in the desired position.
  • If the device overheats, check for proper ventilation and ensure the load does not exceed the rated capacity.
  • For persistent issues, consult a qualified electrician.

9. User Tips

  • Some users have reported successful operation without grounding the inverter, but always follow local electrical codes and safety standards.
  • Regularly inspect the device for any signs of wear or damage to ensure long-term reliability.

10. Warranty and Support

Product Certificate Information:

  • Model Name: Dual power automatic transfer switch
  • The product is qualified after inspection and meets the standard IEC60947-6-1, and it is allowed to leave the factory.
  • Inspection Date: See product packaging

Manufacturer Contact Information:

ZHEJIANG EARU ELECTRONICS CO., LTD

  • Address: GUACHUAN ROAD 228 1ST, LIUSHI TOWN, YUEQING CITY, ZHEJIANG PROVINCE, CHINA, 325604
  • Website: https://shop28909b0b26794.1688.com/
  • Manager: Bob Wu
  • Email: bob@earuelec.com
  • Phone Number: +86 15821639630
  • WeChat ID: totybest-2

A detailed user manual in PDF format is available for download here.

Ask a question about this manual

Ask about setup, troubleshooting, compatibility, parts, safety, or missing instructions. Manuals+ will review the question and use this page’s manual context to help answer it.

After a successful submission, we securely hash the supplied account or form email before sending it to Microsoft Advertising for conversion attribution. Privacy details.