PowMr POW-SunSmart 8KP/12.5KP

Contents

PowMr Split-Phase Solar Inverter User Manual

Models: POW-SunSmart 8KP / POW-SunSmart 12.5KP

Brand: PowMr

1. Important Safety Instructions

Please save these instructions for future use!

  1. Before using the unit, read all instructions and cautionary marking on the unit, the batteries and all appropriate sections of this manual. The company reserves the right to void the warranty, if the unit is installed or operated not in accordance with the instructions in this manual, resulting in equipment damage.
  2. Please be clear which kind of battery system you want, lithium battery system or lead-acid battery system, if you choose the wrong system, energy storage system can't work normally.
  3. Do not disassemble the unit. Take it to a qualified service center when service or repair is required. Incorrect re-assembly may result in a risk of electric shock or fire.
  4. All operations and connections must be performed by a professional electrical or mechanical engineer. All the electrical installation must comply with the local electrical safety standards.
  5. CAUTION-To reduce risk of injury, charge only deep-cycle lead-acid type rechargeable batteries and lithium batteries. Other types of batteries may burst, causing personal injury and damage.
  6. To reduce risk of electric shock, disconnect all wirings before attempting any maintenance or cleaning. Turning off the unit will not reduce this risk.
  7. For optimum operation of this inverter, please follow required spec to select appropriate cable size. It's very important to correctly operate this inverter.
  8. GROUNDING INSTRUCTIONS -This inverter should be connected to a permanent grounded wiring system. Be sure to comply with local requirements and regulation to install this inverter.
  9. NEVER cause AC output and DC input short circuited. Do NOT connect to the mains when DC input short circuits.
  10. Do not install the inverter in harsh environments such as moist, oily, flammable or explosive, or heavily dusty areas.
  11. WARNING!! Only qualified maintenance personnel can repair this equipment. If the fault persists after troubleshooting according to the troubleshooting table, take this inverter/charger back to your local dealer or service center for repair.
  12. Do not reverse polarity of the battery input; otherwise, the device may be damaged or unpredictable risks may occur.
  13. Make sure the inverter is completely assembled before operation.
  14. It is necessary to confirm that the inverter's AC output is the only power source for the load, and it is forbidden to use it in parallel with other input AC power to avoid damage.
  15. Recommended to attach proper fuse or circuit breaker to the outside of the inverter.

2. Product Introduction

2.1 Product Description

The hybrid energy storage inverter series integrates and manages photovoltaic systems, storage batteries, the power grid, and connected loads. It delivers stable, safe, and clean electricity for residential, commercial, and industrial applications, meeting diverse energy needs.

2.2 Product Features

  • Supports various types of energy storage batteries, such as lead-acid batteries and lithium-ion batteries.
  • Supports single-phase and split-phase pure sine wave output.
  • Supports voltage adjustment for each phase within the range of 100 to 130V.
  • Supports single-channel photovoltaic input and features the function of simultaneously featuring a single MPPT tracker that can track the maximum power point. The MPPT efficiency reaches up to 99.9%, and the maximum current per channel is 27A.
  • Has two output modes of mains bypass and inverter output, with uninterrupted power supply function.
  • Offers two charging modes: photovoltaic only, and hybrid charging.
  • Supports timed battery charging and timed battery discharging.
  • The single unit energy saving mode function reduces no-load energy loss.
  • Equipped with multiple protection functions to comprehensively protect the safety of photovoltaic panels, batteries, loads, and the controller itself.
  • Features a capacitive intelligent touch screen, menu based operation, and intuitive and convenient parameter setting.
  • Supports 256 event records and 512 day historical data storage.
  • Built-in Bluetooth and WIFI, providing native cloud platform access capabilities. It can automatically synchronize time after connection.

2.3 System Connection Diagram

The following figure shows the system application scenarios of this product. A complete system consists of the following parts:

  1. Photovoltaic Modules: These convert light energy into DC electrical energy. They can charge the battery through the inverter or be directly inverted into AC power to supply power to the load.
  2. Mains Power or Generator: Connected to the AC input, it can supply power to the load and charge the battery simultaneously. When the battery and photovoltaic modules supply power to the load, the system can generally operate without mains power or a generator.
  3. Battery: The function of the battery is to ensure the normal power supply to the system load when the photovoltaic power is insufficient or there is no mains power.
  4. Loads: Various household and office loads can be connected, including refrigerators, lights, televisions, fans, air conditioners, and other AC loads.
  5. Inverter: It is the energy conversion device of the entire system.

Actual Application Scenario Diagram:

Diagram showing a solar power system with PV panels, inverter, battery, grid connection, and household loads.

3. Product Overview

The image below illustrates the external components and connection points of the PowMr Hybrid Solar Inverter.

PowMr Hybrid Solar Inverter with numbered components and ports.
No.ComponentNo.Component
1Capacitive touch screen8Dry contact
2LED indicator9Battery port (positive)
3Terminal protection cover10Battery port (negative)
4ON/OFF rocker switch11Photovoltaic port
5Parallel communication port12AC output (L1+N+L2)
6RS485-1 port13AC input (L1+N+L2+PE)
7CAN/RS485-2 port

4. Installation

4.1 Unpacking and Inspection

Before installation, please inspect the unit. Be sure that nothing inside the package is damaged. You should have received the following items in the package:

  • The unit × 1
  • User manual × 1
  • Cable lug × 2
  • Parallel cable × 1
  • Spare screws × 4
  • Plastic expansion screws × 1
  • Stainless steel expansion screws × 2

4.2 Installation Tool List

Prior to installation, prepare the following tools:

  • Safety goggles
  • Protective Gloves
  • Safety Shoes
  • Dust Mask
  • RJ45 Crimping tool
  • Diagonal Pliers
  • Wire stripper
  • DC Terminal Crimping Tool
  • Hammer drill
  • Mark
  • Rubber Hammer
  • Level
  • DC Wiring Wrench
  • Multimeter
  • Cable Tie
  • Torque Wrench

4.3 Select the Mounting Location

This product is for indoor use only (protection level IP20). Before choosing an installation location, users should consider the following factors:

  • Choose a solid wall to install the inverter on.
  • Install the inverter at a height level with the line of sight.
  • Ensure adequate clearance around the inverter: at least 200 mm on both sides and 500 mm at the top.
  • Operating environment temperature: -10°C to 55°C. Avoid direct sunlight, humidity, and dust to ensure optimal performance.
Diagram showing recommended clearances for inverter installation on a wall.

DANGER

  • Do not install the inverter near highly flammable materials.
  • Do not install the inverter in potentially explosive areas.
  • Do not install the inverter and lead – acid batteries in an enclosed space.

WARNING

  • Do not install the inverter in direct sunlight.
  • Do not install or use the inverter in a humid environment.

4.4 Install the Expansion Bolts

Drill three mounting holes in the wall according to the specified dimensions and the mounting holes on the inverter (466mm height, 300mm width between top mounting points). The steps are:

  1. Drive the metal expansion bolt into the wall, tighten the nut to make the expansion bolt open its expanding feet; then remove the washer and nut.
  2. Drive the plastic expansion tube into the wall.

4.5 Install the Inverter

Align the inverter with the pre-drilled load-bearing wall and fix it in place. Tighten the nuts of the metal expansion bolts, then screw in the plastic expansion screws to ensure firm and reliable installation.

NOTICE

  • When the equipment is used in areas with poor air quality, the dust filter may become clogged by airborne particles. Please clean the dust filter regularly by removing it for maintenance. This helps prevent reduced airflow inside the inverter, which could trigger over-temperature protection, affect power supply performance, and shorten the inverter's service life.

5. Wiring

5.1 Split-phase Mode

The inverter supports split-phase output, providing 120V between Line 1 (L1) and Neutral (N), and 120V between Line 2 (L2) and Neutral (N), resulting in 240V between L1 and L2.

Diagram illustrating split-phase AC output with 120V and 240V connections.
ItemDescription
Applicable ModelsPOW-SunSmart 8KP
AC Output Phase Voltage (L - N)100~130V, 120V default
AC Output Line Voltage (L1 - L2)200~260V, 240V default

5.2 Single-phase Mode

The inverter can also operate in single-phase mode, providing 120V output. L1 and L2 are in the same phase and can be used in parallel.

Diagram illustrating single-phase AC output with 120V connection.
ItemDescription
Applicable ModelsPOW-SunSmart 8KP
AC Output Phase Voltage (L – N)100~130V, 120V default

NOTICE

  • Users can change the output voltage through the setting menu.
  • The output voltage can be set within the range of 100V to 130V.

5.3 Cable and Circuit Breaker Selection

Proper cable sizing and circuit breaker selection are crucial for safe and efficient operation. Refer to the tables below for guidance.

Photovoltaic Input

ModelWire DiameterMaximum Input CurrentCircuit Breaker Specification
POW-SunSmart 8KP6mm² / 10 AWG27A2P-32A

AC Input

ModelInput ModeMaximum CurrentWire DiameterCircuit Breaker Specification
POW-SunSmart 8KPSplit-phase45A (L1/L2/N)10mm² / 8 AWG (L1/L2/N)3P-50A
Single-phase45A (L1/L2)
90A (N)
10mm² / 8 AWG (L1/L2)
25mm² / 4 AWG (N)
2P-100A

Battery

ModelWire DiameterMaximum CurrentCircuit Breaker Specification
POW-SunSmart 8KP50mm² / 1 AWG120A2P-125A

AC Output

ModelOutput ModeMaximum CurrentWire DiameterCircuit Breaker Specification
POW-SunSmart 8KPSplit-phase45A (L1/L2/N)10mm² / 8 AWG (L1/L2/N)3P-50A
Single-phase45A (L1/L2)
90A (N)
10mm² / 8 AWG (L1/L2)
25mm² / 4 AWG (N)
2P-100A

5.4 AC Input and Output Wiring

Connect the live wire, neutral wire, and ground wire according to the position and sequence of the cables shown in the following figures.

AC Output Wiring Diagram

AC Output Wiring Diagram for PowMr Inverter

AC Input Wiring Diagram

AC Input Wiring Diagram for PowMr Inverter

DANGER

  • There must be only one neutral-to-ground connection in the system.
  • Reversing the L/N wiring will cause faults or equipment damage.
  • Incorrect wiring between the grid input and load output may result in faults or damage.
  • Do NOT leave any terminal unconnected or improperly connected.
  • Before connecting the AC input and output, turn off all breakers to avoid electric shock. Do not perform any wiring under live conditions.
  • Please ensure that the cables used meet the required specifications. Undersized or poor-quality cables pose serious safety risks.

5.5 Battery Wiring

Connect the positive and negative battery cables according to the cable positions and sequence shown in the figure below.

Battery Wiring Diagram for PowMr Inverter

DANGER

  • The lithium-ion battery must communicate properly with the inverter.
  • Before connecting the battery, the circuit breaker must be disconnected to avoid the risk of electric shock. Do not operate under live conditions.
  • Make sure the battery polarity is connected correctly. Reverse connection may damage the inverter.
  • Check whether the cables used meet the required specifications. Undersized or poor-quality cables may pose serious safety hazards.

5.6 Photovoltaic Wiring

Connect the positive and negative wires of one PV input according to the cable positions and sequence shown in the figure below.

Photovoltaic Wiring Diagram for PowMr Inverter

DANGER

  • Before connecting the PV modules, turn off the breaker to avoid the risk of electric shock. Do not perform any wiring under live conditions.
  • Ensure that the open-circuit voltage (Voc) of the PV modules connected in series does not exceed the inverter's maximum open-circuit voltage (500V); otherwise, the inverter may be damaged.
  • You must measure the PV voltage first (≤ the inverter's maximum PV input voltage) before closing the PV input breaker.
  • The PV modules connected to the same MPPT must have the same orientation, tilt angle, and specifications.
  • Each MPPT input should have the same number of PV modules.
  • The PV input ports and PV arrays must be used independently. Under no circumstances should different PV arrays or PV inputs be interconnected or shared.

5.7 Dry Contact Wiring

Use a small-sized screwdriver to push in the direction indicated by the arrow, and then insert the communication cable into the dry contact port. (The cross-sectional area of the communication cable is 0.2~1.5mm²).

Dry Contact Wiring Port on PowMr Inverter

5.8 Final Installation

After ensuring that the wiring is reliable and the wire sequence is correct, restore the terminal protection cover to its original position.

5.9 Inverter Start-up

  1. Step 1: Close the battery circuit breaker.
  2. Step 2: Press the rocker switch located at the bottom of the inverter. The screen and indicator lights will illuminate, indicating that the inverter has been activated.
  3. Step 3: Close the circuit breakers of photovoltaic, AC input and AC output in turn.
  4. Step 4: Start the loads one by one in ascending order of power.

5.10 Parallel Installation and Wiring

Introduction

  • Before parallel operation, ensure that the inverter software is updated to the latest version.
  • A maximum of six inverters can be connected in parallel.
  • When using the parallel function, ensure that the parallel communication cables are correctly and securely connected.
  • Recommended cable specifications for parallel connection:
    • RJ45 connector (8-pin modular plug)
    • Length: 2 meters
    • Cat-6 shielded twisted-pair cable (with ferrite bead shielding)

The following diagram illustrates the connection cable:

Parallel communication line:

Parallel communication cable for PowMr Inverter

Wiring Guidelines for Parallel Systems

  1. PV wiring: When connecting in parallel, each inverter must be connected to a separate PV array or PV source. The same PV source must not be connected to multiple inverters.
  2. Battery cable connection: In both split-phase and three-phase parallel configurations, all inverters must be connected to the same battery system. Connect BAT+ to BAT+ and BAT- to BAT- across all units. Before powering on the system, ensure that the wiring is correct, and that cable length and diameter are consistent, to avoid abnormal output operation in the parallel system.
  3. AC OUT connection:
    1. Split-Phase Parallel Wiring: When connecting in split-phase parallel mode, connect all inverters’ L1 terminals together, all L2 terminals together, N to N, and PE to PE. Ensure all connections are correct and that wiring length and conductor size are consistent before powering on, to prevent incorrect wiring that could cause abnormal operation of the parallel system.
    2. Three-Phase Parallel Wiring: For three-phase parallel systems, connect all inverters' N to N and PE to PE. Inverters assigned to the same phase must have their L lines connected together. Do not connect L lines between different phases. All other precautions are the same as for split-phase connections.
  4. AC IN connection:
    1. Split-Phase Parallel Wiring: For split-phase parallel systems, connect N to N and PE to PE. L1 terminals of all inverters must be connected to the L1 phase, and L2 terminals must be connected to the L2 phase. Ensure all connections are correct before powering on, and that wiring lengths and wire gauges are uniform to prevent abnormal operation of the parallel system. Do not connect multiple AC input sources simultaneously, as this may damage the inverters or other connected equipment. AC input sources must maintain consistent and unique configurations.
    2. Three-Phase Parallel Wiring: For three-phase parallel systems, connect N to N and PE to PE. L lines of inverters in the same phase must be connected together. Do not connect L lines from different phases.
  5. Parallel communication cable wiring: Communication cables should be connected according to the split-phase or three-phase parallel configuration. Each inverter must follow a one-in-one-out daisy-chain connection: the male connector (OUT) of one device must be connected to the female connector (IN) of the next. Reversing this order is not allowed. All communication cables must be securely fastened with screws to prevent loosening or poor contact, which could lead to system malfunctions or equipment damage. Reminder: Set the parallel communication DIP switch of the first and the last inverter to the ON position, and set the corresponding DIP switches of the two intermediate inverters to the OFF position. Switches in the ON position correspond to address 1, while switches in the OFF position correspond to address 0.

Split-phase Parallel Machine Connection Guide Diagram

The diagram for the connection of communication cables for inverter parallel operation is as follows:

Split-phase Parallel Machine Connection Diagram

DANGER

  • Read the instruction manual carefully and follow the guidelines strictly before parallel connection!

Two Inverters Connected in Parallel

When multiple units are connected in parallel, the connection diagram is as follows:

Wiring diagram for two inverters connected in parallel

Parallel Connection System with Six Inverters

This diagram illustrates a larger parallel system with six inverters:

Wiring diagram for six inverters connected in parallel

Split-Phase Parallel Connection UI Operation Steps

The following operations must be performed using only battery power after all cables are connected. All other circuit breakers must remain off. First, turn on the master unit's rocker switch while keeping the slave units off to configure the parallel settings on the master.

  1. Verify that both the UI and software versions are the latest.
  2. Ensure the AC output voltage and frequency match the local utility grid.
  3. Set Grid Type to 240V/120V.
  4. To change the Parallel Mode and Parallel Phase, navigate to: Settings > System Settings > System Parameters.

NOTICE

  • After completing the above steps and returning to the main interface, if the inverter reports a parallel fault, this is normal because the other parallel units are not powered on. No action is required.

Three-Phase Parallel Connection Diagram

The diagram for the connection of communication cables for inverter parallel operation is as follows:

Three-Phase Parallel Connection Diagram for PowMr Inverter

NOTICE

  • The PV input ports must always be used independently.
  • The wiring diagram in this manual illustrates a 3-unit configuration for reference only. For parallel systems exceeding 3 units, please consult technical support before installation to ensure proper system configuration and stable operation.

Three Units in Three-Phase Configuration

This diagram shows three units configured for three-phase operation:

Wiring diagram for three inverters in a three-phase configuration

UI Operation Steps for Three Inverters in Three-Phase Parallel System

The following operations must be performed using only battery power after all cables are connected. All other circuit breakers must remain off. First, turn on the master unit's rocker switch while keeping the slave units off to configure the parallel settings on the master.

  1. Verify that the UI and software versions are the latest.
  2. Ensure the AC output voltage and frequency match the local utility grid.
  3. Set the Grid Type to 208V/120V.
  4. To change the parallel mode and phase, navigate to: Settings > System Settings > System Parameters.

NOTICE

  • After completing the above steps and returning to the main interface, if the inverter reports a parallel fault, this is normal because the other parallel units are not powered on. No action is required.

6. Operation

6.1 LED Indication

The inverter features LED indicators to provide quick status updates:

Indicator LightColorsDescription
AC/INVGreenSteady on: Mains bypass output
Flashing: Inverter output
CHARGEGreenSteady on: Charging completed
Flashing: Charging is underway
FAULTRedFlashing: A fault has occurred

6.2 LCD Display and Operation

Home Page

The LCD display provides real-time information and allows for system configuration. The home page shows an overview of the system status.

LCD Home Page Display
No.Descriptions
1Displays the current time on the device.
2When the device operates in standalone mode, this icon is not displayed. In parallel mode, the icon displays “M” when the device is in master status and "S" when in slave status.

PV Data

Long press the PV icon for about 1s to enter the detailed PV data interface. This screen shows real-time PV total power and voltage of PV1.

Grid Data

Long press the Grid icon for about 1s to enter the detailed data interface of the power grid. The grid data displayed may vary depending on the equipment model. For split-phase systems, it shows voltage and current of L1 and L2, active and apparent power for each phase. For single-phase systems, it shows grid current, frequency, and voltage.

Battery Data

Long press the Battery icon for about 1s to enter the detailed data interface. This screen displays battery capacity percentage, real-time voltage, current, and charge status. "FULL" indicates the battery is fully charged.

Load Data

Long press the Load icon for about 1s to enter the load detailed data interface. For split-phase inverters, it displays current, active power, and apparent power for load L1 and L2, and overall load rate. For single-phase inverters, it shows load current, active power, apparent power, and load rate. The icon appears when the device is operating under overload conditions.

Data Interface

Click the Data icon to access the data menu interface, which includes real-time data, statistical data, historical data, event records, and control functions.

Real-Time Data Interface

Tap “<” or “>” to turn pages. The dots at the bottom of the screen indicate the current page. When the user enters this interface, it opens on the page last viewed. The interface is divided into 6 pages, displaying device status, total charging power, load state, grid frequency, inverter frequency, alarm information, current data, temperature data, voltage data, and communication status.

Statistical Data Interface

The interface is divided into 2 pages, showing daily and total accumulated ampere-hours charged/discharged, inverter/bypass work time, charge capacity, electricity consumption, last power-on time, last battery equalization time, total operating days, fault records, and historical data entries.

Historical Data Interface

If there is a large amount of historical data, click the current page number and enter the desired record number using the on-screen keyboard to jump directly to that record. This interface shows daily charge/discharge AH, inverter operating time, bypass operating time, total load power consumed, time, total PV power generated, total grid-connected power, total utility charging power, and total load power consumed from utility.

Event Log Interface

Click the "Event Data Record" menu to enter the event record list interface. Click any record in the list to jump to the details interface and view the detailed information of that record. If the time for a record is 0, it indicates that no fault has occurred for this record.

Control Function

The control functions are shown in the table below. After the user clicks the “>” arrow, all functions can be executed directly upon confirmation, except for “Time setting,” which will redirect to an additional interface for configuration. Functions include immediate equalization charge, time setting, clear events, clear statistics, clear historical records, restore factory settings, and reset.

Device Information

This interface displays hardware and software versions, UI version, device SN, max supported battery voltage, and language settings. Users can check for updates and change the display language.

Setting Interface

The setting interface allows configuration of communication data, time settings for charging/discharging, battery parameters, and system parameters.

Communication Setting Interface

In the parameter settings, selecting the input field displays the on-screen keyboard for data entry, while selecting the switch icon toggles the function on or off. Parameters include device communication address, Bluetooth enable, WIFI enable, LCD backlight set time, RS485-1 communication parameter, and RS485-2 communication parameter.

Time-Slot Charging and Discharging Settings

In the time-of-use charge/discharge setting interface, the time parameters for each charge/discharge period can be set only when the corresponding enable function is active. If the enable function is not turned on, the configured period parameters will not take effect. Supports switching between charge and discharge modes. Allows customization of multiple charge/discharge periods for any day of the week: after checking the desired weekday(s), set the start and end times for charging and discharging, and the system will automatically control battery charging/discharging according to the settings.

Battery Settings

When "Setting Parameters” or “Type Parameters” is highlighted in green, it indicates that the interface is in editable mode, and parameters can be configured via drop-down lists or input fields. Settings include battery type, system voltage, nominal capacity, temperature compensation, SOC capacity for mains/battery switch, maximum allowed charge current, stop charging current/SOC, equalization charging timeout, activation current for lithium battery, and charging activation method.

System Settings

System settings allow configuration of AC output mode (Mains priority, Inverter priority), AC output voltage, frequency, parallel mode (Single, Split-phase master, Three-phase master, Slave), parallel phase (A Phase, B Phase, C Phase), battery charging mode (Hybrid, PV only), charge current limit, BMS protocol, PV output priority (Load priority, Charge priority), BMS communication fault shutdown, AC input mode, grid type, and energy saving mode.

7. Communication

7.1 Overview

The inverter provides various communication ports for system integration and monitoring.

Communication Ports Overview
No.PortNo.Port
1Parallel port3CAN/RS485-2 port
2RS485-1 port4Dry contact

7.2 RS485-1 Port

The RS485-1 port serves as a data expansion port. The RJ45 pin definitions are as follows:

RJ45 PinDefinition
Pin 15V
Pin 2GND
Pin 3/
Pin 4/
Pin 5/
Pin 6/
Pin 7RS485-A
Pin 8RS485-B

7.3 CAN/RS485-2

The CAN/RS485-2 port can be used to connect to the BMS (Battery Management System) of lithium-ion batteries. The RJ45 pin definitions are as follows:

RJ45 PinDefinition
Pin 15V
Pin 2GND
Pin 3/
Pin 4CANH
Pin 5CANL
Pin 6/
Pin 7RS485-A
Pin 8RS485-B

When the communication cable is correctly connected and the protocol matches, communication is successful, and the battery icon in the upper-right corner of the inverter display will be illuminated. If communication fails (e.g., cable not connected, incorrect protocol), the communication status icon will be illuminated.

NOTICE

  • If you need the inverter to communicate with the lithium battery BMS, please contact us to learn about the communication protocol or upgrade the inverter to the corresponding software program.
  • If you use a common RJ45 network cable, please check the pin definition. Pins 1 and 2 typically need to be cut off for normal operation.

7.4 Dry Contact Port

The dry contact port provides a signal for generator remote start/stop. The function and output are as follows:

FunctionDescription
Generator Remote Start/StopWhen the battery voltage reaches the undervoltage alarm level or the voltage point for battery to mains switching, Pin 2 to Pin 1 is in normally open (NO) state, and Pin 3 to Pin 1 is in normally closed (NC) state. When the battery voltage reaches the voltage point for mains-to-battery switching or the battery is fully charged, Pin 2 to Pin 1 is in normally closed (NC) state, and Pin 3 to Pin 1 is in normally open (NO) state. (Pins 1/2/3 output 125V/1A, 230V/1A, 30V/1A respectively).

NOTICE

  • If you need to use the remote start/stop function of the generator with dry contacts, please ensure that the generator is equipped with an ATS and supports remote start/stop.

7.5 Bluetooth

The inverter has a built-in Bluetooth module, which can be connected to the EnerWise APP (EnerWise APP can be downloaded from the website or contact us to obtain the installation package).

7.6 WIFI

To connect to Enerwise Cloud Platform, set up the network via the APP. When setting the WiFi name within the app, the WiFi name must consist of English letters and numbers (name length < 32 characters) and cannot contain Chinese characters or special symbols. The password must consist of English letters and numbers (password length ≥ 8, < 16 characters) and cannot contain Chinese characters or special symbols. For stable communication, ensure the home Wi-Fi operates on 2.4GHz and support WPA2 protocol. 5GHz is not supported.

8. Protection Function

8.1 Protective Features

The PowMr Hybrid Solar Inverter is equipped with multiple protective features to ensure safe and reliable operation:

No.Protective featuresInstructions
1PV Current Limiting ProtectionWhen the charging current or power of the configured PV array exceeds the rated current or power of the inverter, it will be charged at the rated current or power.
2PV Overvoltage ProtectionIf the PV voltage exceeds the maximum allowed by the hardware, the machine will report a fault and stop the PV boost to output a sinusoidal AC wave.
3Night Anti-Backflow ProtectionAt night, because the battery voltage is higher than the voltage of the photovoltaic module, it will prevent the battery from discharging to the photovoltaic module.
4AC Input Overvoltage ProtectionWhen the mains voltage exceeds 140V per phase, the mains charging will be stopped and the inverter output will be switched.
5AC Input Undervoltage ProtectionWhen the mains voltage per phase voltage is lower than 90Vac, the mains charging will be stopped and the inverter output will be switched.
6Battery Overvoltage ProtectionWhen the battery voltage reaches the over-voltage disconnect voltage point, the PV and the mains will automatically stop charging the battery to prevent the battery from being damaged by overcharging.
7Battery Undervoltage ProtectionWhen the battery voltage reaches the low voltage disconnect voltage point, the battery will automatically stop discharging to prevent the battery from being damaged by excessive discharge.
8Battery Overcurrent ProtectionAfter the battery current exceeds the range allowed by the hardware, the machine will turn off the output and stop discharging the battery.
9AC Output Short-Circuit ProtectionWhen a short circuit fault occurs at the output end of the load, the output AC voltage will be turned off immediately, and the output will be output again after 1 minute. If the output load is still in a short circuit state after 3 attempts, the short circuit fault of the load must be eliminated first and then manually powered on again to restore the normal output.
10Heat Sink Overtemperature ProtectionWhen the internal temperature of the inverter is too high, the inverter will stop charging and discharging; when the temperature returns to normal, the inverter will resume charging and discharging.
11Overload ProtectionAfter overload protection is triggered, the inverter will resume output after 3 minutes. If overload occurs 5 times consecutively, the output will be shut down until the inverter is restarted. (102% < Load < 110%) ±10%: Fault, output will be shut down after 5 minutes.
12AC Backfeed ProtectionPrevent the battery inverter AC from backflow to the bypass AC input.
13Bypass Overcurrent ProtectionSoftware detection.
14Bypass Wiring Error ProtectionWhen the phase of the bypass input differs from that of the inverter's split-phase output, the inverter will block the bypass switchover to prevent load power failure or short circuit during the transition.

9. Product Maintenance

9.1 Troubleshooting

Refer to the table below for common issues and their solutions:

Trouble CodesMeaningReasonsSolutions
/The screen is not displayingNo power input, or device switch is not turned on.Check whether the battery circuit breaker or PV circuit breaker is closed. The switch is in the "ON" state.
01Battery voltage lowThe battery voltage is lower than the value set in the "battery under-voltage warning voltage" parameter.Charge the battery until the battery voltage is higher than the value set in the parameter.
03Battery no connectThe battery is not connected, or the lithium battery BMS is in discharge protection mode.1. Check that the battery is reliably connected;
2. Check that the battery's circuit breaker is closed;
3. Make sure the BMS of the lithium-ion battery can communicate normally.
04Battery undervoltage stops dischargingThe battery voltage is lower than the value set in over discharge voltage.1. Manual reset: Turn off the power and restart
2. Automatic reset: Charge the battery so that the battery voltage is higher than the value set in the parameter "Overcharge Return Voltage".
06Battery charge overvoltage protectionThe battery is overvoltage.Manually turn off the power and restart it. Check whether the battery voltage exceeds the limit. If so, discharge the battery until the voltage is below the over voltage of the battery.
13Bypass overload protectionThe bypass output power or output current is overloaded for a certain period of time.Reduce the load power and restart the device. Refer to item 11 in Protection Features for more details.
14Inverter overload protectionThe power or output current of the inverter is overloaded within a certain period.Reduce the load power and restart the device. Refer to item 11 in Protection Features for more details.
19PV radiator over-temperature protectionThe temperature of the photovoltaic radiator exceeds 80°C for 3s.When the temperature of the radiator cools below the over-temperature recovery temperature, normal charging and discharging are resumed.
20Inverter radiator over-temperature protectionThe temperature of the inverter heat sink exceeds 80° C for 3s.When the temperature of the radiator cools below the over-temperature recovery temperature, normal charging and discharging are resumed.
21Fan faultThe hardware has detected a fan failure.After shutting down the system, manually start the fan and check for any foreign objects obstructing it.
26Inverter AC output is fed back to bypass AC outputThe AC output relay is stuck.Restart manually, if the fault occurs again after restarting, you will need to contact after-sales service to repair the machine.
27Mains input phase errorPhase mismatch detected between AC input and output.Ensure that the AC input phase configuration matches the AC output phase configuration. For example, if the output is configured for split-phase operation, the input must also be in split-phase mode.

9.2 Maintenance

To maintain optimal long-term performance, it is recommended to perform the following checks twice a year:

  1. Ensure that airflow around the inverter is not obstructed, and remove any dirt or debris from the radiator.
  2. Inspect all exposed wiring for damage caused by sun exposure, friction with surrounding objects, dry rot, or insect or rodent activity. Repair or replace any damaged wiring as necessary.
  3. Verify that the display and instructions are consistent with the actual operation of the equipment. Pay attention to any faults or incorrect displays, and take corrective action if necessary.
  4. Check all terminals for signs of corrosion, insulation damage, high temperature, or burning/discoloration, and tighten the terminal screws.
  5. Check for dirt, nesting insects, and corrosion. Clean the insect netting regularly as needed.
  6. If the lightning arrester has failed, replace it promptly to prevent lightning damage to the inverter or other user equipment.

DANGER

  • Prior to any inspection or operation, it is essential to disconnect the inverter from all power sources and ensure that internal capacitors are fully discharged to prevent the risk of electric shock.

The following causes of machine issues are not covered under the standard warranty:

  1. The product is beyond the warranty period (except for extended warranty services agreed upon by both parties);
  2. Failures or damages resulting from failure to follow the product instructions or installation and maintenance requirements, or caused by operating, storing, or using the product in an environment that does not meet the specified conditions such as improper installation distance, inadequate ventilation, or failure to use waterproof caps correctly;
  3. Unauthorized disassembly, repair, or modification of the product;
  4. Products obtained through unauthorized channels;
  5. Failures or damages caused by unforeseeable circumstances, human factors, or force majeure events, such as storms, floods, lightning strikes, overvoltage, insect infestation, or fire;
  6. Unauthorized design changes, modifications, or part replacements;
  7. Intentional damage, defacement, permanent markings, or theft;
  8. Normal wear and tear;
  9. Failure to use the product in accordance with applicable safety standards (e.g., VDE standards);
  10. Any other failures or damages not caused by product quality issues;
  11. Damage incurred during transportation (including scratches on the casing caused by movement of the packaged product during transit);
  12. Rust or corrosion of the enclosure due to exposure to harsh environmental conditions.

10. Specifications

Detailed specifications for the PowMr Hybrid Solar Inverter models:

CategorySpecificationPOW-SunSmart 8KPPOW-SunSmart 12.5KP
Inverter OutputRated Output Power8000 W12500 W
Max. Peak Power16000 W25000 W
Rated Output Voltage100/110/120/127V; 200/220/240V; 208V; 220V
Rated Frequency50/60Hz
Output WaveformPure sine wave
Switching TimeTypical Value: 10ms, Max Value for Single Machine: 20ms, Max Value For Parallel Machine: 30ms
BatteryBattery TypeLithium-ion battery/lead-acid battery
Rated Battery Voltage48Vdc
Battery Voltage Range40~60Vdc
Max. PV Charging Current120A200A
Max. Mains/ Generator Charging Current100A
Max. Hybrid Charging Current120A200A
PV InputNumber of MPPT12
Max. Input Power10500 W9000W+9000W
Max. Input Current27A22A+22A
Max. Open Circuit Voltage500Vdc500Vdc+500Vdc
MPPT Operating Voltage Range125~425Vdc
Mains/Generator InputInput Voltage Range90~275Vac
Input Frequency Range60/55~65Hz
Bypass Overload Current45A
EfficiencyMPPT Tracking Efficiency99%
Max. Efficiency of Battery InverterMax. Efficiency of Battery Inverter93%
GeneralDimensions (H*W*D)472*412*130mm
Net Weight16kg
Level of ProtectionIP20
Ambient Temperature-10 ~ 55°C
Noise≤45dB @25°C(77°F)
Cooling MethodCooling MethodIntelligent Air Cooling
Warranty TimeWarranty Time1 years
CommunicationCommunication MethodWIFI/Bluetooth/RS485/CAN/4G(Optional)

11. User Tips

  • Ensure all components are securely connected for optimal performance and to prevent any issues.
  • For a flawless DIY setup, use 2/0 AWG battery cables with a 250A breaker and 6 AWG wires for AC input/output.
  • When planning a high-capacity solar system, consider the inverter's ability to parallel up to 6 units for scalability.

12. Frequently Asked Questions

Q: Do I need to purchase the battery and connectors separately?
A: Yes, the inverter typically comes as a standalone unit. You will need to source compatible batteries and appropriate connectors (e.g., 2/0 AWG battery cables with a 250A breaker) separately.

13. Support & Contact

For further assistance or inquiries, please contact:

  • Company: SHENZHEN HEHEJIN INDUSTRIAL CO.,LTD
  • Tel/Fax: +86755-28219903
  • Email: support@powmr.com
  • Web: www.powmr.com
  • Address: Henggang Street, Longgang District, Shenzhen, Guangdong, China

Ask a question about this manual

Ask about setup, troubleshooting, compatibility, parts, safety, or missing instructions. Manuals+ will review the question and use this page’s manual context to help answer it.

After a successful submission, we securely hash the supplied account or form email before sending it to Microsoft Advertising for conversion attribution. Privacy details.