1. Introduction
This manual describes the assembly, installation, operation, and troubleshooting of the PowMr 6.2KW Hybrid Solar Inverter. Please read this manual carefully before installations and operations, and keep it for future reference.
1.1 Purpose
This manual provides safety and installation guidelines as well as information on tools and wiring for the PowMr 6.2KW Hybrid Solar Inverter.
1.2 Features
- Pure sine wave inverter
- Configurable input voltage range for home appliances and personal computers via LCD setting
- Configurable battery charging current based on applications via LCD setting
- Configurable AC/Solar Charger priority via LCD setting
- Compatible with mains voltage or generator power
- Auto restart while AC is recovering
- Overload/Over temperature/short circuit protection
- Smart battery charger design for optimized battery performance
- Cold start function
- Supports parallel operation for up to 9 units.
1.3 Product Overview
The PowMr 6.2KW Hybrid Solar Inverter is an all-in-one solar inverter designed to meet most household solar energy needs. It supports solar and bypass power supply, solar and grid charging, and keeps your battery safely charged as backup. The AC output voltage is adjustable (220V/230V/240V) with a rated AC output of 6200W, boosting to 6500W when solar input exceeds 2000W and the battery supports the load. It features dual output ports for stable power to critical loads and is compatible with 48V lead-acid or lithium batteries, supporting up to 120A charging current. It handles up to 8500W of PV input and allows up to 9 units in parallel for a total output of 55.8kW.


2. Safety Instructions
WARNING: This chapter contains important safety and operating instructions. Read and keep this manual for future reference.
- Before using the unit, read all instructions and cautionary markings on the unit, the batteries, and all appropriate sections of this manual.
- CAUTION: To reduce risk of injury, charge only deep-cycle lead acid type rechargeable batteries. Other types of batteries may burst, causing personal injury and damage.
- Do not disassemble the unit. Take it to a qualified service center when service or repair is required. Incorrect re-assembly may result in a risk of electric shock or fire.
- To reduce risk of electric shock, disconnect all wirings before attempting any maintenance or cleaning. Turning off the unit will not reduce this risk.
- CAUTION: Only qualified personnel can install this device with battery.
- NEVER charge a frozen battery.
- For optimum operation of this inverter/charger, please follow required specifications to select appropriate cable size. It's very important to correctly operate this inverter/charger.
- Be very cautious when working with metal tools on or around batteries. A potential risk exists to drop a tool to spark or short circuit batteries or other electrical parts and could cause an explosion.
- Please strictly follow installation procedure when you want to disconnect AC or DC terminals.
- One piece of 150A fuse is provided as over-current protection for the battery supply.
- GROUNDING INSTRUCTIONS: This inverter/charger should be connected to a permanent grounded wiring system. Be sure to comply with local requirements and regulations to install this inverter.
- NEVER cause AC output and DC input short circuited. Do NOT connect to the mains when DC input short circuits.
- Warning!! Only qualified service persons are able to service this device. If errors still persist after following troubleshooting table, please send this inverter/charger back to local dealer or service center for maintenance.
3. Setup and Installation
3.1 Unpacking and Inspection
Before installation, please inspect the unit. Be sure that nothing inside the package is damaged. You should have received the following items:
- The unit x 1
- User manual x 1
- Parallel communication cable x 1
- Share current wires x 1
- Expansion screw (M6*80mm) x 2
- Battery fuse x 1
3.2 Mounting the Unit
Consider the following points before selecting where to install:
- Do not mount the inverter on flammable construction materials.
- Mount on a solid surface.
- Install this inverter at eye level in order to allow the LCD display to be read at all times.
- For proper air circulation to dissipate heat, allow a clearance of approx. 20 cm to the side and approx. 50 cm above and below the unit.
- The ambient temperature should be between 20℃ and 35°C to ensure optimal operation.
- The recommended installation position is to be adhered to the wall vertically.
- Be sure to keep other objects and surfaces as shown in the diagram to guarantee sufficient heat dissipation and to have enough space for removing wires.
SUITABLE FOR MOUNTING ON CONCRETE OR OTHER NON-COMBUSTIBLE SURFACE ONLY.

Install the unit by screwing three screws:
- Use M6*80mm expansion bolts for suspending and securing the equipment from above.
- Use M4 or M5 screws in the 3 holes to secure the equipment, as shown in the figure.
NOTICE: To avoid potential damage to the terminal base and internal electronic components, it is recommended not to install screws in the mounting hole located at the lower left corner.
3.3 Grounding
Please make sure to connect the equipment grounding first, ensuring the device enclosure is reliably grounded before the system is powered on to effectively prevent personal injury caused by accidental leakage.
3.4 Battery Connection
CAUTION: For safety operation and regulation compliance, it's requested to install a separate DC over-current protector or disconnect device between battery and inverter. All wiring must be performed by qualified personnel. It's very important for system safety and efficient operation to use appropriate cable for battery connection. To reduce risk of injury, please use the proper recommended cable and terminal size.
| Rated Capacity | Typical Amperage | Battery Capacity | Wire Size | Cable(mm²) | Ring Terminal D(mm) | Ring Terminal L(mm) | Torque Value |
|---|---|---|---|---|---|---|---|
| 6.2KVA | 143A | 200Ah | 1*2AWG | 38 | 8.4 | 39.2 | 5 Nm |
| 2*4AWG | 25 | 8.4 | 33.2 |
Please follow below steps to implement battery connection:
- Assemble battery ring terminal based on recommended battery cable and terminal size.
- The 6.2KW model supports 48VDC battery systems. Connect all battery banks as shown in the diagram below.
- Insert the battery wires flatly into battery connectors of inverter and make sure the bolts are tightened with a torque of 2 Nm in a clockwise direction. Make sure polarity at both the battery and the inverter/charger is correctly connected and conductors are tightly screwed into the battery terminals.

3.5 AC Input/Output Connection
CAUTION: Before connecting to AC input power source, please install a separate AC breaker between the inverter and AC input power source. This will ensure the Inverter can be disconnected during maintenance and fully protected from over current of AC input. The recommended spec of breaker is 63A for 48V system. There are two terminal blocks with "IN" and "OUT" markings. Please do NOT mis-connect input and output connectors. All wiring must be performed by qualified personnel. It's very important for system safety and efficient operation to use appropriate cable for AC input connection. To reduce risk of injury, please use the proper recommended cable size.
| Rated Capacity | Gauge | Torque Value |
|---|---|---|
| 6.2KW | 10 AWG | 1.4~1.6 Nm |
Please follow below steps to implement AC input/output connection:
- Before making AC input/output connection be sure to open DC protector or disconnector first.
- Remove insulation sleeve 10mm for six conductors. And shorten phase L and N 3 mm.
- Insert AC main output wires according to polarities indicated on terminal block and tighten terminal screws. Be sure to connect PE protective conductor (
) first.
→Ground (yellow-green)- L→LINE (brown or black)
- N→Neutral (blue)

WARNING: Be sure that AC power source is disconnected before attempting to hardwire it to the unit.
3.6 PV Connection
CAUTION: Before connecting to PV modules, please install separately a DC circuit breaker between the inverter and PV modules. All wiring must be performed by qualified personnel. It's very important for system safety and efficient operation to use appropriate cable for PV module connection. To reduce risk of injury, please use the proper recommended cable size.
| Rated Capacity | Typical Amperage | Gauge | Torque Value |
|---|---|---|---|
| 6.2KW | 30A | 12 AWG | 1.4~1.6 Nm |
When choosing the right PV module, be sure to first consider the following requirements:
- The open circuit voltage (Voc) of the PV modules does not exceed the maximum PV array open circuit voltage of the inverter.
- The maximum supply voltage of the PV modules should be close to the optimal PV access voltage range of the inverter for best performance. If one PV module cannot meet this requirement, it is necessary to connect multiple PV modules in series.
| Model | POW-HVM6.2KP |
|---|---|
| PV Charging Mode | MPPT |
| MAX.PV Input Power | 8500W |
| MPPT Tracking Range | 60~500Vdc |
| Operating voltage | 360~430V |
| MAX.PV Input Voltage | 500Vdc |
| PV max input current | 27A |
| MAX.PV Charging Current | 120A |
| MAX.AC Charging Current | 100A |
| MAX. Charging Current | 120A |
Please follow below steps to implement PV modules connection:
- Remove insulation sleeve 10 mm for positive and negative conductors.
- Suggest to put bootlace ferrules on the end of positive and negative wires with a proper crimping tool.
- Insert PV input wires according to polarities indicated on terminal block and tighten the terminal screws.
- Check correct polarity of wire from PV modules and PV input connectors. Then, connect positive pole (+) of connection wire to positive pole (+) of PV input connector. Connect negative pole (-) of connection wire to negative pole (-) of PV input connector.

3.7 Final Assembly
After connecting all wirings, please install the bottom cover back by screwing four screws.
4. Operating Instructions
4.1 Power ON/OFF
Once the unit has been properly installed and the batteries are connected, follow the power-on sequence below to start the inverter safely:
- Close the battery circuit breaker.
- Press the On/Off switch (located on the bottom of the case) to turn on the unit. Wait until the inverter starts up and enters normal operation (inverting).
- Close the PV and AC input circuit breakers.
- Finally, close the AC output circuit breaker.
To shut down the system, turn off the circuit breakers in the reverse order.
Steps to Start Up
Connect the battery that meets the requirements (battery voltage needs to be beyond 46V) or AC (AC needs to confirm the suitable input range depending on the output mode), then you can start up the inverter.
- Mains power on: Connect to normal AC power, press the switch, the system will automatically turn on. If you set AC output power priority, after waiting for a period of time, the panel will display AC mode that represents successful machine turn-on, then it will enter AC mode.
- Battery boot: Connect to battery, press the power-on button to establish a working power source. The system will automatically turn on, after waiting for a period of time, the panel will display battery mode that represents successful machine turn-on, then it will enter battery mode.
Shutdown Steps
When the system is in battery mode or AC mode output, press the switch again, then the system will be turned off.
4.2 Operation and Display Panel
The operation and display panel, shown in the figure below, is on the front panel of the inverter. It includes three indicators, four function keys, and an LCD display, indicating the operating status and input/output power information.

| Function Key | Description |
|---|---|
| ESC | To exit setting mode |
| UP | To go to previous selection |
| DOWN | To go to next selection |
| ENTER | To confirm the selection in setting mode or enter setting mode |
| LED Indicator | Messages |
|---|---|
| AC/INV (Green, Solid On) | Output is powered by utility in Line mode. |
| AC/INV (Green, Flashing) | Output is powered by battery or PV in battery mode. |
| CHG (Yellow, Solid On) | Battery is fully charged. |
| CHG (Yellow, Flashing) | Battery is charging. |
| FAULT (Red, Solid On) | Fault occurs in the inverter. |
| FAULT (Red, Flashing) | Warning condition occurs in the inverter. |
4.3 LCD Display Icons and Information
The LCD display provides various information about the inverter's status, input/output, battery, and load. Information can be cycled through using the UP/DOWN keys.
Input Source Information
- AC: Indicates the AC input.
- PV1: Indicates the PV panel input.
Middle Digital Display Information
- Indicates input voltage, input frequency, battery voltage, PV voltage, charger current.
- Indicates the setting programs.
- Indicates warning and fault codes.
Right Digital Display Information
- Indicates the output voltage, output frequency, load percent, load VA, load W, PV charger power, DC discharging current.
Battery Information
- Indicates battery level by 0-24%, 25–49%, 50–74%, 75–100% and charging status.
- Indicates the battery type: AGM, Flooded or User-defined battery.
Load Information
- Indicates overload.
- Indicates the load level by 0–24%, 25–50%, 50–74% and 75%-100%.
Mode Operation Information
- Indicates unit connects to the mains.
- Indicates unit connects to the PV panel.
- Indicates the solar charger is working.
- Indicates the DC/AC inverter circuit is working.
Mute Operation
- Indicates unit alarm is disabled.
4.4 LCD Setting Programs
After pressing and holding the ENTER button for 3 seconds, the unit will enter setting mode. Use the "UP" or "DOWN" buttons to select setting programs, and then press "ENTER" to confirm the selection or "ESC" to exit.
Key settings include:
- Program 00: Exit setting mode.
- Program 01: Output source priority selection:
- SUB priority (default): Solar energy provides power to loads first. If insufficient, utility supplies power.
- SBU priority: Solar energy provides power to loads first. If insufficient, battery supplies power. Utility only supplies power when battery voltage drops below a set level or solar/battery are insufficient.
- Program 02: Maximum charging current: Configures total charging current for solar and utility chargers (10A to max, 10A increments).
- Program 03: AC input voltage range:
- Appliances (default): 90–280VAC.
- UPS: 170–280VAC.
- Program 04: AC output mode:
- Single (default): For single phase operation.
- Parallel: For parallel operation with single phase (select "PAL").
- L1, L2, L3 phase: For three-phase equipment (requires at least 3 inverters, max 9).
- Program 05: Battery type: Selects battery type (AGM, Flooded, User-Defined, LIA-protocol, Pylontech, Techfine, Growatt, Felicity, LIB-protocol, 3rd party lithium).
- Program 06: Auto restart when overload occurs: Enable/Disable.
- Program 07: Auto restart when over temperature occurs: Enable/Disable.
- Program 08: ECO function: Temporarily stops system when load is low in battery mode (Enable/Disable).
- Program 09: Output frequency: 50Hz or 60Hz.
- Program 10: Output voltage: 220V, 230V, or 240V.
- Program 11: Maximum utility charging current: Setting range is 2A, then from 10A to max AC charging.
- Program 12: Setting voltage point back to utility source (SBU priority): 44V to 51V (1V increments).
- Program 13: Setting voltage point back to battery mode (SBU priority): 48V to 58V (1V increments).
- Program 16: Charger source priority:
- Solar first: Solar energy charges battery first. Utility charges only when solar is unavailable.
- Solar and Utility (default): Solar and utility charge battery simultaneously.
- Only Solar: Solar energy is the only charger source.
- Program 18: Auto return to default display screen: Enable/Disable.
- Program 19: Stay at latest screen: Enable/Disable.
- Program 20: Backlight control: On/Off.
- Program 22: Beeps while primary source is interrupted: On/Off.
- Program 23: Overload bypass: Enable/Disable.
- Program 24: Battery low voltage: 40.0V-54.0V for 48V system.
- Program 25: Record Fault code: Enable/Disable.
- Program 26: Bulk charging voltage (C.V voltage): 48.0V to 60.0V for 48V system (0.1V increments).
- Program 27: Floating charging voltage: 48.0V to 54.0V for 48V system (0.1V increments).
- Program 28: Reset factory setting: Turn on/off.
- Program 29: Low DC cut-off voltage: 40.0V to 52.0V for 48V system (0.1V increments).
- Program 30: Battery equalization: Enable/Disable.
- Program 31: Battery equalization voltage: 48.0V to 60.0V (0.1V increments).
- Program 33: Battery equalized time: 5min to 900min (5min increments).
- Program 34: Battery equalized timeout: 5min to 900min (5min increments).
- Program 35: Equalization interval: 0 to 90 days (1 day increments).
- Program 36: Equalization activated immediately: Enable/Disable.
- Program 37: BMS Function Switch: On/Off.
- Program 38: Bat Soc Under Lock: If any type of lithium battery is selected in program 05.
- Program 39: Bat Soc Turn to AC: If any type of lithium battery is selected in program 05.
- Program 40: Bat Soc Turn to DC: If any type of lithium battery is selected in program 05.
- Program 41: Bat Restart Soc: If any type of lithium battery is selected in program 05.
- Program 43: Solar supply priority: When solar energy is available, it will prioritize charging the battery or powering the loads.
- Program 44: Solar energy feed to grid configuration: Enable/Disable.
- Program 45: Reset PV energy storage: Reset.
- Program 46: Start charging time for AC charger: 00:00 to 23:00 (1 hour increments).
- Program 47: Stop charging time for AC charger: 00:00 to 23:00 (1 hour increments).
- Program 48: Scheduled time for AC output on: 00:00 to 23:00 (1 hour increments).
- Program 49: Scheduled time for AC output off: 00:00 to 23:00 (1 hour increments).
- Program 50: Set country customized regulations: Various modes for feed-in grid voltage and frequency ranges.
- Program 51-54: Time setting (Minute, Hour, Day, Month).
- Program 55: Time setting (Year).
- Program 56: GRID-tie current: 20A (1A increments).
- Program 57: External CT Function: Not supported.
- Program 58: Set the input power of mains power: 150W (Not supported).
- Program 60: Dual output: Enable/Disable.
- Program 61: Enter the dual output functional voltage point: 44.0V (0.1V increments).
- Program 62: Enter the dual output functional SOC point: 20% (If any type of lithium battery is selected in program 05).
- Program 63: Battery voltage recovery threshold for dual output: 52.0V (Default 52V).
- Program 64: SOC recovery threshold for dual output: 50% (Default 50%).
- Program 65: Setting discharge time on the second output: Disable to 990 min (5 min increments).
- Program 66: Dual Recover Delay Time: 0-60min.
- Program 67: Output Open Time: 0-23.
- Program 68: Output Stop Time: 0-23.
- Program 70: Set the Rated power: 6.5KW (100W increments).
5. Maintenance
5.1 Battery Equalization
Equalization function is added into the charge controller. It reverses the buildup of negative chemical effects like stratification, a condition where acid concentration is greater at the bottom of the battery than at the top. Equalization also helps to remove sulfate crystals that might have built up on the plates. If left unchecked, this condition, called sulfation, will reduce the overall capacity of the battery. Therefore, it's recommended to equalize battery periodically.
How to Apply Equalization Function
You must enable the battery equalization function in monitoring LCD setting program 30 first. Then, you may apply this function in the device by either one of the following methods:
- Setting equalization interval in program 35.
- Active equalization immediately in program 36.
When to Equalize
In this stage, when the setting equalization interval (battery equalization cycle) is reached, or equalization is active immediately, the controller will start to enter the Equalize stage.

Equalize charging time and timeout
In the Equalize stage, the controller will supply power to charge the battery as much as possible until the battery voltage raises to the battery equalization voltage. Then, constant-voltage regulation is applied to maintain the battery voltage at the battery equalization voltage. The battery will remain in the Equalize stage until the setting battery equalized time is reached.
However, in the Equalize stage, when the battery equalized time is expired and the battery voltage doesn't rise to the battery equalization voltage point, the charge controller will extend the battery equalized time until the battery voltage achieves the battery equalization voltage. If the battery voltage is still lower than the battery equalization voltage when the battery equalized timeout setting is over, the charge controller will stop equalization and return to the float stage.
6. Troubleshooting
6.1 Fault and Alarm Description
Faults Descriptions
If the inverter enters fault mode, the red LED light is always on and the LCD displays a fault code.
| Fault Code | Fault Event | Action |
|---|---|---|
| 01 | Fan is locked when inverter is off. | Replace the fan. |
| 02 | Over temperature or NTC is not connected well. | Check whether the air flow of the unit is blocked or whether the ambient temperature is too high. |
| 03 | Battery voltage is too high. | Return to repair center. Check if battery specifications meet requirements. |
| 04 | Battery voltage is too low. | Return to repair center. Check if battery specifications meet requirements. |
| 05 | Output short circuited or over temperature is detected by internal converter components. | Check if wiring is connected well and remove abnormal load. |
| 06 | Output voltage is too high. | 1. Reduce the connected load. 2. Return to repair center. |
| 07 | Overload time out. | Reduce the connected load by switching off some equipment. |
| 08 | Bus voltage is too high. | Return to repair center. |
| 09 | Bus soft start failed. | Return to repair center. |
| 51 | Over currents or surge. | Restart the unit. If the error happens again, please return to repair center. |
| 52 | Bus voltage is too low. | Restart the unit. If the error happens again, please return to repair center. |
| 53 | Inverter soft start failed. | Return to repair center. |
| 55 | Over DC voltage in AC output. | Return to repair center. |
| 57 | Current sensor failed. | Return to repair center. |
| 58 | Output voltage is too low. | 1. Reduce the connected load. 2. Return to repair center. |
| 59 | PV voltage is over limitation. | Reduce the number of PV modules in series. |
Warning Descriptions
If the red LED flashes, and the LCD displays an alarm code, the inverter does not enter the failure mode.
| Warning Code | Warning Event | Audible Alarm |
|---|---|---|
| 01 | Fan is locked when inverter is on. | Beep three times every second |
| 02 | Over temperature | None |
| 03 | Battery is over-charged | Beep once every second |
| 04 | Low battery | Beep once every second |
| 07 | Overload | Beep once every 0.5 second |
| 10 | Output power derating | Beep twice every 3 seconds |
| 15 | PV energy is low. | Beep twice every 3 seconds |
| 16 | High AC input (>280VAC) during BUS soft start | None |
| E9 | Battery equalization | None |
| bP | Battery is not connected | None |
Code Reference (Communication)
Related information code will be displayed on the LCD screen. Please check the inverter LCD screen for the operation.
| Code | Description |
|---|---|
| 60 | If battery status is not allowed to charge and discharge after successful communication between the inverter and battery, code 60 will show to stop charging and discharging battery. |
| 61 | Communication lost. After battery is connected, communication signal is not detected for 1 minute, buzzer will beep. Communication lost occurs after the inverter and battery are connected successfully, buzzer beeps immediately. |
| 69 | If battery status is not allowed to charge after successful communication between the inverter and battery, code 69 will show to stop charging battery. |
| 70 | If battery status must charge after successful communication between the inverter and battery, code 70 will show to charge battery. |
| 71 | If battery status is not allowed to discharge after successful communication between the inverter and battery, code 71 will show to stop discharge battery. |
| 72 | Current sharing fault. |
| 80 | CAN fault. |
| 81 | Host loss. |
| 82 | Synchronization loss. |
| 83 | Battery voltage detected different. |
| 84 | AC input voltage and frequency detected different. |
| 85 | AC output current unbalance. |
| 86 | AC output mode setting is different. |
7. Technical Specifications
| Feature | Specification (POW-HVM6.2KP) |
|---|---|
| AC Input | |
| Input Sources | L+N+PE |
| Rated Input Voltage | 220/230/240VAC |
| Voltage Range | 90-280VAC±3V (APL Mode); 170-280VAC±3V (UPS Mode) |
| Frequency | 50Hz/60Hz (Auto Adaptive) |
| Inverter Output | |
| Rated Power (Battery Inverter) | 6200W |
| Rated Power (Photovoltaic Inverter) | 6500W |
| Output Voltage | 220/230/240VAC±5% |
| Output Frequency | 50Hz/60Hz±0.1% |
| Waveform | Pure Sine Wave |
| Transfer Time (Adjustable) | Computers (UPS Mode) 10ms, Appliance (APL Mode) 20ms |
| Peak Power | 12400VA |
| Overload Capacity | Battery mode: 11s@105%~150%Load; 2s@150%~200%Load; 400ms@>200%Load |
| Grid-Connected Operation | |
| Output Voltage | 220/230/240VAC±5% |
| Feed Into the Grid Voltage Range | 100-280VA |
| Feed Into the Grid Frequency Range | 47-53±1Hz/57-62±1Hz |
| Nominal Output Current | 26.9A |
| Power Factor Range | >0.99 |
| Maximum Conversion Efficiency (DC/AC) | 98% |
| Battery | |
| Battery Voltage | 48Vdc |
| Constant Charging Voltage (Adjustable) | 56.4Vdc |
| Float Charging Voltage (Adjustable) | 54Vdc |
| PV Input | |
| PV Charging Mode | MPPT |
| MAX. PV Input Power | 8500W |
| MPPT Tracking Range | 60~500Vdc |
| Operating Voltage | 360~430V |
| MAX. PV Input Voltage | 500Vdc |
| PV Max Input Current | 27A |
| MAX. PV Charging Current | 120A |
| MAX. AC Charging Current | 100A |
| MAX. Charging Current | 120A |
| Display | |
| LCD Interface | CAN display running mode/load/input/output, etc. |
| Interface | |
| RS232 | Baud Rate 2400 |
| Extend the Socket | Lithium Battery BMS Communication Card, WiFi Card, Dry Contact |
| Communication Interface | Parallel Machine (network) function |
| General Specifications | |
| Operating Temperature | -10°C~50°C |
| Humidity | 20%~95% (Non-condensing) |
| Storage Temperature | -15°C~60°C |
| Altitude | Not Over 1000m, Derating over 1000m, Max 4000m, Refer to IEC62040 |
| Noise | ≤50db |
| Standards and Certification | EN-IEC 60335-1, EN IEC 60335-2-29, IEC 62109-1 |
| Size | 450x300x130 mm |
| Weight | 9.6KG |
8. Parallel Function (Appendix I)
8.1 Mounting the Unit for Parallel Operation
When installing multiple units, ensure proper clearances for air circulation: approx. 20 cm to the side and approx. 50 cm above and below each unit. All units must be installed at the same level.

8.2 Wiring Connection for Parallel Operation
NOTICE: It's required to connect to battery for parallel operation. The cable size for each inverter is shown in the table below.
| Rated Capacity | Wire Size | Cable(mm²) | Ring Terminal D(mm) | Ring Terminal L(mm) | Torque Value |
|---|---|---|---|---|---|
| 6.2KW | 1*2AWG | 38 | 8.4 | 39.2 | 2-3Nm |
WARNING: Be sure the length of all battery cables is the same. Otherwise, there will be voltage difference between inverter and battery to cause parallel inverters not working.
You need to connect the cables of each inverter together. For battery cables, use a connector or bus-bar as a joint to connect the battery cables together, and then connect to the battery terminal. The cable size used from the joint to the battery should be X times the cable size in the tables above, where "X" is the number of inverters connected in parallel. The same principle applies to AC input and output wiring.
CAUTION: Make sure all output N wires of each inverter must be connected all the time. Otherwise, it will cause inverter fault (error code #72). Please install the breaker at the battery and AC input side. This will ensure the inverter can be securely disconnected during maintenance and fully protected from over current of battery or AC input.
| Recommended Breaker Specification of Battery for Each Inverter | |
|---|---|
| Rated Capacity | 1 unit* |
| 6.2KW | 150A/70VDC |
*If you want to use only one breaker at the battery side for the whole system, the rating of the breaker should be X times current of 1 unit. "X" indicates the number of inverters connected in parallel.
| Recommended Breaker Specification of AC Input with Single Phase | ||||||||
|---|---|---|---|---|---|---|---|---|
| Rated Capacity | 2 units | 3 units | 4 units | 5 units | 6 units | 7 units | 8 units | 9 units |
| 6.2KW | 80A/230VAC | 120A/230VAC | 160A/230VAC | 200A/230VAC | 240A/230VAC | 280A/230VAC | 320A/230VAC | 360A/230VAC |
Note 1: Also, a circuit breaker should be installed at the AC input of each inverter, and the selection of the circuit breaker should refer to the AC input current of the machine nameplate.
Note 2: Regarding three-phase system, you can use a 4-pole breaker directly and the rating of the breaker should be compatible with the phase current limitation from the phase with maximum units.
8.3 PV Connection for Parallel Operation
NOTE: Each inverter should be connected to an independent photovoltaic array. Multiple inverters must not share the same photovoltaic array, as this may cause irreversible damage to the inverters.

8.4 Commissioning Parallel Units
Parallel in single phase:
Step 1: Check the following requirements before commissioning:
- Correct wire connection.
- Ensure all breakers in Line wires of load side are open; each Neutral wire of each unit is connected together.
Step 2: Turn on each unit and set "PAL" in LCD setting program 4 of each unit. Then shut down all units.
NOTE: It's necessary to turn off the switch when setting the LCD program. Otherwise, the setting cannot be programmed.
Step 3: Turn on each unit.
NOTE: Master and slave units are randomly defined.
9. User Tips
- The inverter's output voltage is 220V, 230V, or 240V, configurable via LCD settings (Program 10). This addresses questions about the 220V output.
- The inverter supports Wi-Fi monitoring, which can be enabled or disabled via LCD settings (Program 175:353309 for No Wi-Fi, 175:353310 for With Wi-Fi).
- For optimal performance and safety, always ensure all wiring is done by qualified personnel and follows the recommended cable sizes and torque values.
- When operating in parallel, ensure all battery cables are of the same length to prevent voltage differences that could affect performance.
- The new inverter model (POW-HVM6.2KP) cannot be used in parallel with older inverter models.
10. Warranty and Support
For technical support, service, or warranty inquiries, please contact the manufacturer directly using the information below. This manual does not cover specific warranty terms or conditions.
Manufacturer Contact Information
- Company: SHENZHEN HEHEJIN INDUSTRIAL CO.,LTD
- Tel/Fax: +86755-28219903
- Email: support@powmr.com
- Web: www.powmr.com
- Address: Henggang Street, Longgang District, Shenzhen, Guangdong, China 55304-200-931