PowMr POW-SunSmart 10K

Contents

PowMr 10KW Split Phase Hybrid Solar Inverter User Manual

Models: POW-SunSmart 8KP, POW-SunSmart 10KP

Brand: PowMr

1. Introduction

The PowMr POW-SunSmart series is a new type of solar energy storage inverter control inverter, integrating solar energy storage, utility charging, energy storage, and AC sine wave output. It utilizes DSP control and features high response speed, reliability, and industrial standard through an advanced control algorithm. This inverter is suitable for various industrial and residential scenarios.

1.1 Key Features

  • Pure Sine Wave Inverter: Provides clean and stable power output.
  • High Output Power: Up to 10000W.
  • Dual Voltage Output: Supports 120/240Vac, compatible with single-phase or split-phase devices.
  • Fast Switching Time: 10ms for seamless power transfer.
  • Battery Compatibility: Compatible with 48V lithium-ion and lead-acid batteries, with user-defined settings.
  • High Charging Current: Max PV charging current up to 200A, Max AC charging current up to 120A, Max hybrid charging current up to 200A.
  • Wide Voltage Range: 90~140Vac AC input voltage range, 125~500Vdc wide voltage range for PV access.
  • Dual MPPT: Two Maximum Power Point Trackers with 99.9% efficiency, supporting up to 22A input DC current in a single circuit.
  • Energy Saving Mode: Function to reduce no-load energy losses.
  • Multiple Communication Interfaces: RS485, CAN, USB, and Dry Contact for versatile monitoring and control.
  • Robust Design: Durable finish with high anti-corrosion, effective forced air cooling.
  • 360° Protection: Comprehensive protection against short circuit, over current, over/under voltage, overload, and backfill.

1.2 Product Overview

The POW-SunSmart 10K is an all-in-one solar inverter combining the functions of a solar controller, AC controller, and inverter. It offers outstanding performance with a rated power of up to 10 KW and is suitable for both single-phase and split-phase applications. It also features a time-slot charging and discharging setting for optimizing the use of clean solar energy.

Video: Product Unboxing and Overview of the PowMr 10KW Hybrid Solar Inverter.

PowMr 10KW Hybrid Solar Inverter with labeled ports

Figure 1.1: Product Overview with Labeled Ports (1. LCD screen, 2. LED Indicators, 3. Touchable key, 4. ON/OFF Rocker Switch, 5. PV INPUT (1/1), 6. BAT INPUT (+), 7. BAT INPUT (-), 8. Dry contact, 9. CAN/RS485-2 port, 10. RS485-1 port, 11. USB-B port, 12. Grounding Screw, 13. AC OUT (L+L+N), 14. AC IN (L+L+N), 15. AC INPUT breaker).

2. Important Safety Instructions

Please save these instructions for future use!

  • Read all instructions and cautions in this manual before installation.
  • Installation and wiring must comply with Local and National Electric Codes (NEC) and be performed by a certified technician.
  • DO NOT disassemble or attempt to repair the inverter. There are no serviceable parts.
  • DO NOT parallel this device with other AC input sources to avoid damage.
  • DO NOT touch the unit while it is operating as temperatures will be very hot. Do not open the terminal cover during operation.
  • Ensure all connections going into and from the inverter are tight. Sparks may occur during connections; ensure no flammable materials or gases are near the installation.
  • Installing breakers or fuses outside of the unit is recommended.
  • After installation, check that all line connections are tight and secured.
  • DO NOT let the positive (+) and negative (-) terminals of the battery touch each other.
  • Use Lithium batteries or deep cycle Sealed Lead Acid, Flooded, Gel, AGM batteries.
  • Explosive battery gases may be present while charging. Ensure adequate ventilation to release gases.
  • Be careful when working with large lead acid batteries. Wear eye protection and have fresh water available in case of contact with battery acid.
  • Over-charging and excessive gas precipitation can damage battery plates. Carefully review specific requirements of the battery used.

3. What's in the Box

Upon opening the packaging, you will find the following items:

  • PowMr POW-SunSmart 10K Inverter
  • Instruction Manual
  • Warranty Card
  • 2 Exploded Screws
  • 2 Terminal of the Battery Cables (Cable Lugs)
Contents of the PowMr 10KW Inverter box: solar inverter, instruction manual, cable lugs and screws

Figure 3.1: Contents of the Product Package.

4. Installation

4.1 Select the Mount Location

The POW-SunSmart series is designed for INDOOR USE ONLY (IP20). Consider the following before selecting a location:

  • Choose a solid wall for installation.
  • Mount the inverter at eye level.
  • Ensure adequate heat dissipation space.
  • The ambient temperature should be between -10°C to 55°C (14°F to 131°F) for optimal operation.

DANGER:

  • Do not install where highly flammable materials are nearby.
  • Do not install in potential explosive areas.
  • Do not install with lead-acid batteries in a confined space.

CAUTION:

  • Do not install in direct sunlight.
  • Do not install or use in a humid environment.
Mounting dimensions and clearances for the PowMr inverter

Figure 4.1: Recommended Mounting Dimensions and Clearances.

4.2 Mount the Inverter

Make 4 mounting holes in the wall according to the specified dimensions. Insert 2 expansion screws above and fix the inverter with 2 M5 screws below.4.3 Remove the Terminal Cover and Insect Screen

Using a screwdriver, remove the terminal protection cover and insect screen.

NOTICE:

  • When using the device in areas with poor air quality, the dust screen can easily become blocked by airborne particles. Please dismantle and clean the dust screen regularly to avoid affecting the internal air flow rate of the inverter, which may trigger an over-temperature protection fault (19/20 fault) and affect the power supply and service life.

4.4 Connection Overview

The inverter supports both Split-phase and Single-phase modes. The actual application scenario determines the specific system wiring method.

Split-phase mode wiring diagram showing PV panels, inverter, battery, and house load

Figure 4.2: Split-phase Mode Wiring Diagram. Notice: The open circuit voltage of PV panel in series connection must be below 500V. Over-voltage will cause damage to the inverter. Damage caused by improper configuration is not covered by warranty.

Single-phase mode wiring diagram showing PV panels, inverter, battery, and house load

Figure 4.3: Single-phase Mode Wiring Diagram. Notice: The open circuit voltage of PV panel in series connection must be below 500V. Over-voltage will cause damage to the inverter. Damage caused by improper configuration is not covered by warranty.

4.5 Cable & Circuit Breaker Requirements

The following table outlines the recommended cable diameters and circuit breaker specifications:

Connection TypeModelCable DiameterMax CurrentCircuit Breaker Spec
PV Input8KW Model5mm² / 10 AWG22A2P-25A
10KW Model5mm² / 10 AWG22A2P-25A
AC Input8KW Split-phase13mm² / 6AWG (L1/L2/N)63A (L1/L2/N)3P-63A
8KW Single-phase13mm² / 6AWG (L1/L2), 26mm² / 3AWG (N)63A (L1/L2), 126A (N)2P-125A
10KW Split-phase13mm² / 6AWG (L1/L2/N)63A (L1/L2/N)3P-63A
10KW Single-phase13mm² / 6AWG (L1/L2), 26mm² / 3AWG (N)63A (L1/L2), 126A (N)2P-125A
Battery8KW Model34mm² / 2 AWG180A2P-200A
10KW Model42mm² / 1 AWG220A2P-250A

NOTICE:

  • For PV Input, AC Input, and AC Output: Use a stripper to remove 6-8mm insulation from the cable. Fix a ferrule at the end of the cable (user-prepared).
  • For Battery: Use a stripper to remove 6-8mm insulation from the cable. Fix cable lugs (supplied with the box) at the end of the cable.
  • The wire diameter is for reference only. If the distance between the PV array and the inverter or between the inverter and the battery is long, using a thicker wire will reduce voltage drop and improve system performance.

4.6 AC Input & Output Connection

Connect the live, neutral, and ground wires according to the cables' position and order shown in the diagram. Apply 1.5NM torque.

AC Input and Output Connection Diagram

Figure 4.4: AC Input and Output Connection.

DANGER:

  • Before connecting AC inputs and outputs, the circuit breaker must be opened. Do not operate with electricity.
  • Check that the cable used is sufficient for the requirements. Too thin or poor-quality cables are a serious safety hazard.

4.7 Battery Connection

Connect the positive and negative cables of the battery according to the diagram. Apply 3NM torque.

Battery Connection Diagram

Figure 4.5: Battery Connection.

DANGER:

  • Before connecting the battery, the circuit breaker must be opened. Do not operate with electricity.
  • Ensure positive and negative terminals are connected correctly and not reversed, otherwise the inverter may be damaged.
  • Check that the cable used is sufficient for the requirements. Too thin or poor-quality cables are a serious safety hazard.

4.8 PV Connection

Connect the positive and negative wires of the two strings of PV according to the diagram. Apply 1.2NM torque.

PV Connection Diagram

Figure 4.6: PV Connection.

DANGER:

  • Before connecting PV, the circuit breaker must be opened. Do not operate with electricity.
  • Ensure the open circuit voltage of the PV modules in series does not exceed the Max. Open Circuit Voltage of the inverter (500V for POW-SunSmart series), otherwise the inverter may be damaged.

4.9 Dry Contact Connection

Use a small screwdriver to push back the direction indicated by the arrow, then insert the communication cable into the dry junction port. The communication cable diameter should be 0.2-1.5mm².

4.10 Grounding Connection

Ensure the grounding terminal connects to the Grounding Busbar. Apply 2NM torque.

NOTICE:

  • The grounding cable should have a diameter of not less than 4mm² and be as close as possible to the grounding point.

4.11 Inverter Start Procedure

After confirming reliable wiring and correct wiring sequence, restore the terminal cover to its original position:

  1. Close the circuit breaker of the battery.
  2. Press the rocker switch at the bottom of the inverter. The screen and indicator will light up, indicating that the inverter is enabled.
  3. Close the circuit breakers for PV input, AC input, and AC output in sequence.
  4. Start loads one by one in order of power from small to large.

4.12 Parallel Connection Wiring Diagrams

The inverter supports parallel operation for up to six units. When using the parallel function, it is necessary to connect the parallel communication cable in a correct and reliable manner. Refer to the diagrams below for specific configurations.

WARNING:

  • PV Wiring: In parallel connection, the PV array of each inverter must be independent, and the PV array of PV1 and PV2 for one inverter must also be independent.
  • Battery Wiring: In single-phase or three-phase parallel connection, all solar storage inverters must be connected to the same battery, with BAT+ connected to BAT+ and BAT- to BAT-. Before power on and start-up, check and ensure correct connection, wiring length, and cable size to avoid abnormal operation.
  • AC OUT Wiring: In single-phase parallel connection, all solar storage inverters must be connected L-to-L, N-to-N, and PE-to-PE. Check connections, wiring length, and cable size. In three-phase parallel connection, all solar storage inverters must be connected N-to-N and PE-to-PE. The L lines of all inverters in the same phase shall be connected together, but the AC output L lines of different phases shall not be connected together.
  • AC IN Wiring: Similar to AC OUT wiring, ensure consistent connections and no multiple AC source inputs.
  • Communication Wiring: Use a DB15 standard computer cable with shielding. Each inverter connects one out to one in. Tighten terminal screws.
  • Adding New Inverter: To add a new inverter to an existing system, disconnect battery input, PV input, AC input, and AC output, and power off all solar storage inverters before reconnecting.
Wiring diagram for two parallel inverters in split-phase mode

Figure 4.7: Example Wiring Diagram for Two Parallel Inverters (Split-Phase Mode).

NOTE on Parallel Connection Setup:

  • Before powering on, check for correct wiring according to the diagrams.
  • Check all connections for firm fixing.
  • When connecting AC output to the load, complete wiring according to electrical load requirements.
  • Set item [38] to the same parameter, or only set it in the host inverter. During parallel operation, the voltage set in the host prevails.
  • The inverter defaults to single mode at the factory. For parallel or three-phase function, set item [31] on the screen. Power on one inverter at a time, turn off others, set item [31], then turn off and set others one by one. Power on all at once to enter working state.
  • For split-phase parallel operation, set item [31] to PAL, and item [68] to 180°. When setting item [38] to "120 V," the L1-L2 voltage is 240 V, and the L1-N voltage is 120 V.
  • For three-phase parallel operation, set item [31] to "3P1" for P1, "3P2" for P2, and "3P3" for P3. Item [68] cannot be set and defaults to "0". The P1-P2, P1-P3, and P2-P3 phase difference is 120°. When setting item [38] to "120 VAC," the voltage between L1 of P1 phase and L2 of P2 phase is 120*1.732=208 VAC. Similarly, L1-L3 and L2-L3 voltage is 208 VAC.

5. Operation

5.1 Operation and Display Panel

The operation and display panel includes 1 LCD screen, 3 indicators, and 4 touchable keys.

Inverter LCD screen, LED indicators, and touchable keys

Figure 5.1: Inverter Display Panel.

Touchable Keys

  • ⚙️: Enter/exit the setting menu
  • △: Go to the next selection
  • ▽: Go to the previous selection
  • ✔️: Confirm/Enter the selection in setting menu

LED Indicators

  • AC/INV (Yellow): Steady on (utility grid bypass output), Flash (inverter output).
  • CHARGE (Green): Steady on (charging complete), Flash (charging).
  • FAULT (Red): Steady on (level-1 fault), Flash (level-2 fault), Off (level-3 or level-4 fault).

5.2 View Real-time Data

From the main screen, press the UP / DOWN keys to view real-time data such as PV input voltage/current/power, battery voltage/current, AC input/output voltage/current/frequency, load power, battery SOC, and more. Refer to the full manual for a complete list of display panel icons and their descriptions.

LCD HD Display Screen showing real-time data

Figure 5.2: LCD HD Display Screen showing various system data.

5.3 Settings

The inverter offers a comprehensive settings menu to customize its operation. Access the settings menu using the touchable keys on the display panel. Key parameters include:

  • AC Output Source Priority (Parameter 01):
    • UTI (Utility Priority): Utility is first priority. Solar and utility provide power to the load. Battery powers load only when utility is unavailable. (Priority: utility > solar > battery)
    • SBU (Inverter Priority): Solar provides power to loads first. If solar is insufficient, battery is used. When battery voltage reaches a set point, it switches to utility. (Priority: solar > battery > utility)
    • SOL (Solar Priority): Solar provides power to loads first. If solar is insufficient, utility is used as a supplement. Maximizes solar energy use. (Priority: solar > utility > battery)
  • AC Output Frequency (Parameter 02): Set to 50.0Hz or 60.0Hz (default).
  • AC Input Voltage Range (Parameter 03): UPS default (110/120V, 90-140V input) or APL (100/105V, 85-140V input).
  • Battery Charging Mode (Parameter 06):
    • SNU (Hybrid Charging - default): Solar and utility charge the battery simultaneously, with solar as the first priority. Fastest charging.
    • OSO (Only Solar Charging): Solar charging only, no mains charging. Most energy-efficient.
  • Max. Charging Current (Grid+PV) (Parameter 07): 0-180A for 8KW, 0-200A for 10KW.
  • Battery Type (Parameter 08): Options include USER, SLD (Sealed Lead-Acid), FLD (Flooded Lead-Acid), GEL (Gel Lead-Acid - default), L14/L15/L16 (Lithium-ion), N13/N14 (Ternary Li-ion), NOb (No battery mode, requires grid connection).
  • Parallel Mode (Parameter 31): Set for single, two, or three-phase parallel operation (SIG default, PAL, 2P0/2P1/2P2, 3P1/3P2/3P3).
  • BMS Communication (Parameter 32): Select protocol (SLA default, 485, CAN).

Refer to the full user manual (pages 25-37) for a complete list and detailed descriptions of all parameters.

5.4 Time-slot Charging/Discharging Function

The POW-SunSmart series is equipped with a time-slot charging and discharging function, allowing users to set different charging and discharging periods according to local peak and valley tariffs. This optimizes the use of utility power and PV energy.

  • When mains electricity is expensive, the battery inverter powers the load.
  • When mains electricity is cheap, mains electricity charges the battery.
  • This function can be enabled/disabled via parameters 46 and 53. Charging and discharging slots are set in parameters 40-45 and 47-52.
Peak-Valley Electricity Tariff and Timed Charging/Discharging Functions

Figure 5.3: Time-slot Charging/Discharging Function Overview.

5.5 Communication Interfaces

  • USB-B Port: Connect to a computer to read and modify device parameters using the upper computer software (available from PowMr website).
  • WIFI Port: Used to connect to a Wi-Fi/GPRS data acquisition module (purchased separately) for remote monitoring and parameter viewing via a mobile app.
  • RS485/CAN Port: Used to connect to the Battery Management System (BMS) of Li-ion batteries. Contact PowMr for communication protocols or software upgrades if needed.
  • Dry Contact Port: Has two functions: battery temperature sampling (Pins 1 & 4) and remote generator start/stop (Pins 5, 6, 7). Ensure the generator has an ATS and supports remote start/stop for this function.

6. Maintenance

To maintain optimum and long-lasting working performance, we recommend checking the following items twice a year:

  1. Ensure that the airflow around the inverter is not blocked and remove any dirt or debris from the radiator.
  2. Check that all exposed conductors are not damaged by sunlight, friction with other surrounding objects, dry rot, insect or rodent damage, etc. Repair or replace conductors if necessary.
  3. Verify that the indications and displays are consistent with equipment operation. Note any faults or incorrect displays and take corrective action.
  4. Check all terminals for signs of corrosion, insulation damage, high temperatures, or burning/discoloration and tighten terminal screws.
  5. Check for dirt, nesting insects, and corrosion. Clean as required, and clean the insect screen regularly.
  6. If the lightning arrester has failed, replace it in time to prevent lightning damage to the inverter or other equipment.

DANGER:

  • Before conducting any inspection or operation, ensure the inverter is disconnected from all power sources and that the capacitor is fully discharged to avoid electric shock.

7. Troubleshooting

This section provides common fault codes and their remedies. For any faults not listed or unresolved, contact PowMr after-sales service. DO NOT disassemble the device yourself.

7.1 Fault Codes and Response Measures

Fault CodeMeaningCausalityRemedy
/No screen displayNo power input, or device switch is off.Check battery/PV air-switch, ensure switch is ON, press any button to exit sleep mode.
01Battery under-voltage (BatVoltLow)Battery voltage is lower than parameter [14].Charge the battery until voltage is higher than parameter [14].
03Disconnected battery (BatOpen)Battery not connected or BMS in discharge protection.Check connections, battery circuit breaker, and BMS communication.
15Inverter over-current hardware protection (AcOverCurrHw)Inverter over-current.Reduce load power and restart the device.
19MPPT heat sink over-temperature protection (OverTemperMppt)MPPT heat sink temperature exceeds 90°C for 3s.Resume normal charge and discharge when temperature cools below recovery temperature.
21Fan failure (FanFail)Fan failure detected by hardware for 3s.Manually toggle the fan to check for blockage. Power off/restart. If fault recurs, contact service.
28Utility input phase fault (LinePhaseErr)AC input phase does not coincide with AC output phase.Ensure AC input phase is the same as AC output phase (e.g., split-phase input for split-phase output).

NOTICE:

  • If you encounter product faults that cannot be solved by the methods listed above, please contact our after-sales service department for technical support. Do not disassemble the device yourself.

8. Specifications

Below are the detailed technical specifications for the PowMr POW-SunSmart 8KP and 10KP models.

CategoryParameterPOW-SunSmart 8KPPOW-SunSmart 10KP
INVERTER OUTPUTRated Output Power8,000W10,000W
Max. Peak Power16,000W20,000W
Rated Output Voltage120/240Vac (split phase/single phase)Y
Load Capacity of Motors5HP6HP
Rated AC Frequency50/60HzY
WaveformPure Sine Wave
Switch Time10ms (typical)
BATTERYBattery TypeLi-ion / Lead-Acid / User DefinedY
Rated Battery Voltage48Vdc
Voltage Range40-60VdcY
Max. MPPT Charging Current180A200AY
Max. Mains/Generator Charging Current100A120AY
PV INPUTNum. of MPP Trackers2
Max. PV array power11,000W
Max. input current22/22A
Max. Voltage of Open Circuit500Vdc
MAINS/GENERATOR INPUTInput Voltage Range90-140Vac
Frequency Range50/60Hz
Bypass Overload Current63A
EFFICIENCYMPPT Tracking Efficiency99.9%
Max. Battery Inverter Efficiency92%
GENERALDimensions620*445*130mm (2*1.5*0.4ft)
Weight27KG (59.5lb)
Protection LevelIP20, Indoor Only
Operating Temperature Range-10~55℃, >45℃ derated (14~131°F, >113°F derated)
Noise<60dB
Cooling MethodInternal Fan
COMMUNICATIONEmbedded InterfacesRS485 / CAN / USB / Dry contactY
External Modules (Optional)Wi-Fi / GPRSY
CERTIFICATIONSafetyIEC62109-1, IEC62109-2, UL1741
EMCEN61000-6-1, EN61000-6-3, FCC 15 class B
RoHSYes

9. User Tips

  • Installation: Users have found the installation process to be straightforward. Always refer to the manual for detailed wiring diagrams and safety precautions to ensure correct setup.
  • Battery-less Operation: The inverter can operate solely with solar panels, providing flexibility for various system designs.
  • Dual Voltage Output: The inverter supports both 110V and 220V output simultaneously, catering to diverse household appliance needs.
  • Parallel Capability: For increased power or specific phase configurations, the inverter can be connected in parallel with up to six units. Ensure proper communication and power wiring as detailed in the manual.
  • Overheating Issues: If you encounter fault code 15 (overheating), check the fan for blockages and ensure adequate ventilation around the unit. Regular cleaning of the insect screen is crucial for maintaining optimal airflow and preventing over-temperature faults.
  • System Monitoring: Utilize the Wi-Fi module (if purchased) and mobile app for convenient remote monitoring of system data and operational status.

10. Warranty and Support

10.1 Warranty Information

The PowMr POW-SunSmart 10K Inverter comes with a 1 Year Warranty.

Our company will not be held responsible for damage due to the following reasons:

  • Damage caused by improper use or use in the wrong location.
  • The open circuit voltage of the PV module exceeds the maximum allowable voltage.
  • The operating temperature exceeds the limited operating temperature range.
  • Unauthorized personnel dismantle and repair the inverter.
  • Force majeure: damage during transportation or handling of the inverter.

10.2 Contact Information

For technical support, warranty claims, or any inquiries, please contact:

SHENZHEN HEHEJIN INDUSTRIAL CO.,LTD

  • Tel/Fax: +86 755-28219903
  • Email: support@powmr.com
  • Website: www.powmr.com
  • Address: Henggang Street, Longgang District, Shenzhen, Guangdong, China

Ask a question about this manual

Ask about setup, troubleshooting, compatibility, parts, safety, or missing instructions. Manuals+ will review the question and use this page’s manual context to help answer it.

After a successful submission, we securely hash the supplied account or form email before sending it to Microsoft Advertising for conversion attribution. Privacy details.