OptiClimate RevomaxII Installation Manual

Image of the OptiClimate RevomaxII unit.

THE MOST STABLE CLIMATE THINKABLE. GUARANTEED.

Table of Contents

1. SPECIFICATIONS

MODEL6000 REV2 REGULAR & DEEP COOL10000 REV2 REGULAR & DEEP COOL15000S REV2 REGULAR & DEEP COOL15000 REV2 REGULAR & DEEP COOL
Nominal Power Capacity - kWatt6 kW10 kW15 kW15 kW
Maximum Power Capacity - kWatt7 kW12 kW19 kW19 kW
De-humidification Capacity - Liters/24Hrs*85 L105 L165 L165 L
Power Supply - Volt230v-400v230v-400v230v-400v400v
Phase1 or 31 or 31 or 33
Compressor (inverter) - VoltDC (230V)DC (230V)DC (230V)DC (400V)
Compr. Freq. Min (Max) - Hz30 (110) Hz30 (90) Hz30 (85) Hz30 (85)Hz
Fuse MCB single-phase (3-phase)C32 (C20)C40 (C25)C63 (C40)C25 3ph+N
Total 3-Phase Ampere17 A24 An/a23 A
Total 1-Phase Ampere28 A38 A68 An/a
Cable diameter (mm) 3 phase2,5 mm²4 mm²10 mm²6 mm²
Cable diameter (mm) 1 phase6 mm²6 mm²25 mm²n/a
Internal Glass Fuse Heater (3x) - Ampere16 A16 A16 A16 A
Internal Glass Fuse Main - Ampere5 A5 A5 A5 A
Power Factor cos φ0,90,90,90,9
Nominal (cooling) rated power - kWatt1,3 kW2,1 kW5,0 kW5,0 kW
Max cooling rated power - kWatt1,9 kW3,5 kW6,5 kW6,5 kW
Max current (cooling) - Ampere9 A16 A30 A16 A
Electrical Heating Power - kWatt3 x 1,3 kW3 x 1,6 kW3 x 2,7 kW3 x 2,7 kW
Electrical Heating Current - Ampere3 x 5,5 A3 x 8,0 A3 x 13,0 A3 x 13,0 A
De-Humidify 20 degrees WB - kg5 kg8 kg12 kg12 kg
Coefficient of Performance COP4,64,63,23,5
Total max power capacity (heating& cooling)10,9 kW16,8 kW17,6 kW17,6 kW
Rated Air Flow m³/h1300 m³/h1900 m³/h2200 m³/h2200 m³/h
Static Pressure Pascal0 Pa0 Pa0 Pa0 Pa
Rated Air Flow m³/h1100 m³/h1600 m³/h2450 m³/h2450 m³/h
Static Pressure Pascal100 Pa100 Pa100 Pa100 Pa
Refrigerant TypeR410AR410AR410AR410A
Charge Volume - kg2,3 kg2,7 kg3,45 kg3,85 kg
GWP number2088208820882088
CO₂ Equivalent - Ton4,85,647,27,2
Flow demand cold water (25 deg. Celcius Max) Cooling mode - Liters/min2,0 - 4,0 L/min3,0 - 6,0 L/min3,0 - 10,0 L/min3,0 - 10,0 L/min
Flow demand cold water (25 deg. Celcius Max) Heating mode - Liters/min0,0 - 4,0 L/min0,0 - 6,0 L/min0,0 - 10,0 L/min0,0 - 10,0 L/min
Flow demand recirculating water Cooling mode - m³/hour1,2 m³/h2 m³/h3 m³/h3 m³/h
Flow demand recirculating water Heating mode - m³/hour1,2 m³/h2 m³/h3 m³/h3 m³/h
Water Temperature Limits Temp In (recirculating) - ° Celcius Max25 (55) °25 (55) °25 (55) °25 (55) °
Water Temperature Limits Temp Out (recirculating) - ° Celcius Max65 (65) °65 (65) °65 (65) °65 (65) °
Delta (recirculating) - ΔT5 °5 °5 °5 °
Size L x W x H cm91 x 57 x 44 cm99 x 67 x 49 cm114 x 70 x 54 cm114 x 70 x 54 cm
Weight kg79 kg94 kg124 kg124 kg

* measured at 27 degrees Celcius / 60% humidity

MODEL21000 REV2 REGULAR & DEEP COOL30000 REV2 REGULAR & DEEP COOL30000 Free Air30000 SEP-FAN
Nominal Cooling Capacity - kWatt21 kW30 kW30 kW30 kW
Maximum Cooling Capacity - kWatt23 kW35 kW35 kW30 kW
De-humidification Capacity - Liters/24Hrs230 L315 L315 L315 L
Power Supply - Volt400v400v400v400v
Phase3333
Compressor (inverter) - VoltDC (400v)DC (400V)DC (400v)DC (400v)
Compr. Freq. Min (Max) - Hz30 (85) Hz30 (85) Hz30 (85) Hz30 (85) Hz
Fuse MCB single-phase (3-phase)C32 3ph+NC50 3ph+NC50 3ph+NC50 3ph+N
Total 3-Phase Ampere27 A36 A36 A36 A
Total 1-Phase Amperen/an/an/an/a
Cable Diameter (mm) 3 phase6 mm²10 mm²10 mm²10 mm²
Cable Diameter (mm) 1 phasen/an/an/an/a
Internal Glass Fuse Heater (3x) - Ampere16 A16 A16 A16 A
Internal Glass Fuse Main - Ampere5 A8 A8 A8 A
Power Factor cos φ0,90,90,90,9
Nominal cooling rated Power kWatt6,0 kW9,0 kW9,0 kW9,0 kW
Max cooling rated Power - kWatt6,3 kW15,0 kW15,0 kW15,0 kW
Max current cooling - Ampere20 A25 A25 A25 A
Electrical Heating Power - kWatt3 x 2,7 kW3 x 3,7 kW3 x 3,7 kW3 x 3,7 kW
Electrical Heating Current - Ampere3 x 13,0 A3 x 16,0 A3 x 16,0 A3 x 16,0 A
De-Humidify 20 degrees WB - kg17 kg19 kg19 kg19 kg
Coefficient of Performance w/w3,53,33,33,3
Total max Power capacity (heating & cooling) kW17,6 kW26,1 kW26,1 kW26,1 kW
Rated Air Flow m³/h3900 m³/h6500 m³/h6000 m³/h6500 m³/h
Static Pressure Pascal0 Pa0 Pa0 Pa0 Pa
Rated Air Flow m³/h3100 m³/h5000 m³/h5000 m³/h5000 m³/h
Static Pressure Pascal200 Pa200 Pa200 Pa200 Pa
Refrigerant TypeR410AR410AR410AR410A
Charge Volume - kg4,4 kg6 kg6 kg6 kg
GWP number2088208820882088
CO₂ Equivalent - Ton9,1912,5312,5315,53
Flow demand cold water (25 deg. Celcius Max) Cooling mode - Liters/min3,0 - 12,0 L/min3,0 - 20,0 L/min3,0 - 20,0 L/min3,0 - 20,0 L/min
Flow demand cold water (25 deg. Celcius Max) Heating mode - Liters/min0,0 - 12,0 L/min0,0 - 20,0 L/min0,0 - 20,0 L/min0,0 - 20,00 L/min
Flow demand recirculating water Cooling mode - m³/h4,5 m³/h6 m³/h6 m³/h6 m³/h
Flow demand recirculating water Heating mode - m³/h4,5 m³/h6 m³/h6 m³/h6 m³/h
Water Temperature Limits Temp In (recirculating) - ° Celcius Max25 (55) °25 (55) °25 (55) °25 (55) °
Water Temperature Limits Temp Out (recirculating) - ° Celcius Max65 (65) °65 (65) °65 (65) °65 (65) °
Delta (recirculating) - ΔT ° Celcius5 °5 °5 °5 °
Size L x W x H cm122 X 82 X 59 cm148 x 86 x 74,9 cm148 x 86 x 74,9 cm148 x 86 x 74,9 cm
Weight kg181 kg232 kg232 kg232 kg

* measured at 27 degrees Celcius / 60% humidity

2. SAFETY

CAUTION

Please read this manual carefully before attempting to install the Opticlimate Revomax II. The RevomaxII is a high performance climate control system, we strongly advice to seek the services of an installation professional.

These products may represent a possible shock or fire hazard if improperly installed or attached in any way. Products should be installed in accordance with the owners manual and local electrical guidelines and law.

When operating with a seperate humidifier, make sure that it is connected to a reverse osmosis filter or scale filer. Fan faults caused by lime deposits are not covered under our warranty.

2.1 SAFETY PRECAUTIONS

Installation

  • Make sure the Revomax is installed spirit level.
  • Make sure a P-trap is installed on the condensation outlet.
  • Make sure the return air filter and/or plenum box are clean without obstructions or high air resistance.
  • Make sure the supply air ducting and/or air distribution hose is of the correct diameter, typically the same diameter of the supplied flange.
  • Make sure all covers and panels are on the machine while in operation.

Electricity

  • Make sure the correct diameter cable is used to power the machine (see spec sheet, chapter 1/local code).
  • Make sure the correct MCB (miniature circuit breaker) is installed (see spec sheet, chapter 1/local code).
  • Make sure the correct RCD (residual current device) type B (earth-leak) is installed (see data sheet/local code).
  • Make sure the room temperature sensor is connected on the correct position on the circuit-board.
  • Make sure the room temperature sensor is in the room and shielded from direct light or air streams.

Water/glycol

  • Allays install the watercooler outside the building. We do not support indoor placed watercoolers.
  • Make sure flow and return piping has the correct diameter, check chapter 5 for more information.
  • Make sure there is no air trapped in the system. Use an air vent at the hight point of the circuit (closed loop only, chapter 5).
  • Never use water only, when outdoor temperatures are below freezing. (closed loop only, chapter 5).
  • Use dipswitch 3 to start the pump and open water valve to test for leaks/air before full operation (chapter 7).
  • Use water/glycol mix for below zero temperature protection (closed loop only, chapter 7).
  • Make sure fresh water supply is steady below 25 degrees all year round.

General

  • Keep distance from the fan / supply air. Turning parts and rotating fan blades are dangerous.
  • Do not power the machine when the electric compartment is open, circuit-boards and connectors might be charged.
  • In a food / agro environment always use food-grade glycol (propylene glycol) (closed loop only, chapter 7).
  • Make sure you are aware of all features and settings for correct day-to-day operation.
  • Electrical connections should be done by a certified electrician. In some regions this is required by law.
  • Water glycol setup should be done by a certified installer. In some regions this is required by law.
  • Operating the system should be done by personnel that is fully aware of it's functions.
  • Do not operate the unit without the filter or with a less effective filter. The heat exchange coils inside the unit become clogged and require disassembly to clean.

2.2 INTRODUCTION

The OptiClimate RevomaxII is a state-of-the-art climate control system designed to provide an optimal growing environment for a wide variety of plant species. Leveraging advanced Infinity DC inverter technology, this system offers unmatched flexibility in climate control, allowing for precise adjustments up to one tenth Hertz increments in cooling, heating, dehumidification, and air filtration. Its capacity to maintain super stable humidity, room temperature and output temperature ensures the health and productivity of your plants under any indoor condition.

Model Variations

Output Power

The RevomaxII is available in 6000 to 30000 Watt versions. The model you need with sufficient cooling capacity can be calculated by adding up the power outputs for all heat generating devices like fixtures. In most common situations, it's a 1-1 relationship. Example: 12 x 800 Watt HPS fixtures generate 9600 Watts of heat, whichs means you need a 10000 RevomaxII model to cool the growing area. LED is much more efficient per watt, so you need less watts and thus fxtures. This means a LED based installation generates less heat than an HPS one. The other factor is de-humidification capacity. To calculate the needed capacity for de-humidification, your can use a rough guideline of 650 watts per m² of green to get 50% of relative humidity (RH) in the night cycle (depending on your crop). Always check your personal needs before purchasing your RevomaxII.

Image of the OptiClimate RevomaxII unit.

Regular - Cultivation

All RevomaxII models are able to cool to a maximum of 0.2 degrees celcius deviation of the setpoint temperature. With the RevomaxII you are able to control humidity with a maximum 'swing' of 4% (depending on the humidity load) of the set humidity level. In case you use LED fixtures, you might even need to heat the room instead of cooling it. The RevomaxII is unique and can heat a room while de-humidifying.

Image of a Dimlux Xtremell LED Fixture.

Deep Cool - Storage

Normal Revomax units can cool a space to about 16 degrees Celsius, which is more than sufficient for all plants and vegetables, as they thrive in warmer conditions. But if you're looking to turn the space into a cold storage solution--keeping your harvest fresh, just like in a fridge--then we've developed the Revomax Deep Cooling system, designed specifically for your post-harvest needs. Depending on the insulation and capacity the unit can cool close to 0 degrees Celcius.

Image of a Dimlux Expert HPS Fixture.

Separate Fan - Flexible installation

With the sep-fan model (separate-fan) you are able to place the active fan in another location, combined with air hoses or air duct systems.

Image of a Separate Fan.

Free Air - Glass houses

The RevomaxII Free Air is made to blow air freely instead of using a ducting system or hoses. The Free Air is designed in such a way that it takes up as little volume as possible and thus takes up as little space as possible and at the same time intercepts as little light as possible.

Image of a Separate Fan on RevomaxII.

Image of RevomaxII Free-Air.

Product Features

  • Broad Capacity Range: We are able to adjust the cooling capacity in significantly smaller increments than our competition. We can reach 20-30 percent increments versus more than 60 percent at our competitors. This ensures a very stable climate all year round.
  • Optimized for LED Growing: Addresses the challenges of growing with LED lights by ensuring the room reaches optimal temperatures for photosynthesis more quickly and efficiently.
  • Advanced Safety Features: Includes built-in temperature protection, water leak safeguard (optional), and a fireproof system to ensure the operation is as safe as it is efficient.
  • Smart Remote Control: Comes with a smart remote controller for easy management of settings and receiving alarms and warnings via email, enhancing convenience and monitoring.
  • Superior Air Quality Management: Its built-in lightweight filter keeps the interior components clean ensuring your plants thriving at any moment during the growth cycle.

3. INSTALLATION

3.1 PACKAGE CONTENTS

SYSTEM HARDWARE

All RevomaxII units are supplied with a model specific connectorset (chapter 3.2) containing the following items:

  • 1 Revomax II unit - in selected specification
  • 2 Mounting Brackets
  • 3 Rubber damping rings
  • 4 Smart Remote Controller with accessories
  • 5 Controller Cable
  • 6 Various Mounting Parts
  • 7 Humidity & Light Sensor
  • 8 Temperature Sensor
  • 9 Flange

Image of REVOMAX II UNIT.

Image of MOUNTING BRACKETS.

Image of RUBBER DAMPING RINGS.

Image of SMART REMOTE CONTROLLER.

Image of CONTROLLER CABLE.

Image of VARIOUS MOUNTING PARTS.

Image of HUMIDITY & LIGHT SENSOR.

Image of TEMPERATURE SENSOR.

Image of FLANGE.

3.2 CONNECTOR SET VARIATIONS

MODEL RANGEFLANGEINCLUDED CONNECTOR SET
REVOMAX 6000 & DEEP COOLØ250 AC 3-115STANDARD 3500/6000 1-7810K
REVOMAX 10000 & DEEP COOLØ315 AC 3-118STANDARD 10000/15000/21000 1-7810G
REVOMAX 15000 & DEEP COOLØ315 AC 3-118STANDARD 10000/15000/21000 1-7810G
REVOMAX 21000 & DEEP COOLØD398 AC 3-125STANDARD 10000/15000/21000 1-7810G
REVOMAX 30000 & DEEP COOLØD448 AC 3-126STANDARD 10000/15000/21000 1-7810G
REVOMAX 30000 FREE AIRØD448 AC 3-126STANDARD 10000/15000/21000 1-7810G

For the 21000 and 30000 models the Flange is sold separately

3.3 SUPPLIED SENSORS

Humidity Sensor with light cell

Detects actual humidity of the room, hang halfway between canopy and fixtures for optimal readings. Humidity level is shown on the Smart Remote Controller and is used to control the settings on the RevomaxII unit. Depending on the growing needs we can use the light sensor or the internal clock to determine the day and night cycle.

Air Temperature Sensor

Detects actual air temperature of the room, hang halfway between canopy and fixtures and in the shade (or weather housing) for optimal readings. The temperature is shown on the Smart Remote Controller in degrees Celcius and its values are used to control the settings on the RevomaxII unit.

Image of RevomaxII Flange.

Image of Humidity & Light Sensor.

Image of Temperature Sensor.

3.4 OPEN TAP & CLOSED LOOP WITH COOLER

The RevomaxII system is designed to be very flexible in setup and combinations while maintaining its trademark performance. This manual describes an overview of installation options. But we have near endless combinations and can scale up easily.

Possibilities are endless and all situations are different. For this reason we have created a collection of starter-kits for your convenience. All water-related piping and piping connectors are not part of our offer as we recommend different materials and diameters for different situations. Check our knowledgebase for a complete overview of everything you need.

3.5 DIMENSIONS

DIMENSIONS (MM)

ModelWDHØ1Ø2FGHI
600091057044024531055805405250
1000099067049024531055870500250
150001140700550310410701015535250
210001220820590398--1100660250
300001480860750448--1365675465
30000 FREE AIR14808607506007202801365675465

LINE DRAWING

Diagram showing unit dimensions (W: width, D: depth, H: height, Ø1: inlet diameter, Ø2: outlet diameter, F: clearance, G: clearance, H: clearance, I: clearance).

WEIGHT

ModelKGLB
600079174,1
1000094207,2
15000124273,3
21000181399,0
30000232511,5
30000 FREE AIR227511,5

3.6 PLACEMENT

The Revomax II is a high performance climate control system that needs 15 cm of open space for airflow to function properly. Please ensure to leave at least 15 cm of space on all sides (except at the bottom of the unit).

Mount the unit in any of the available options as described in chapter 3.7 to 3.11. Make sure the frame or structure is strong enough to carry the weight of your unit. For reference, check the table above. For specific instructions check chapter 3.7.

Diagram showing installation spacing for optimal airflow, indicating 15 cm clearance on sides and front.

3.7 PREPARING THE UNIT

  1. Place the transport casing on a flat, stable surface.
  2. Carefully remove the packaging from the unit.
  3. Unscrew the bolts from the wooden pallet the unit was supplied on.
  4. Choose mounting option:
    • A - Ceiling
    • B - Frame
    • C - Surface

Continue to the corresponding section below:

Image of RevomaxII delivered on wooden pallet.

3.8 INSTALLATION OPTION A > CEILING

Install the Revomax II to the ceiling to maximize floor space. The additional needed installation equipment is not included in the package. All materials are industry standard and readily available at any hardware store.

Needed additional equipment (not included)

  • 4 threaded rods M8 of desired length - bottom Revomax II to ceiling
  • 4 M8 nuts
  • 4 threaded rod ceiling plates
  • 4 rubber damping rings
  • 4 washing rings
  • Lifting equipment

Steps

  1. Mount the ceiling plates on the ceiling with corresponding spacing, check technical drawings (chapter 3.5) of your specific model.
  2. Use lifting equipment to raise the unit, spirit leveled, exactly below the ceiling plates.
  3. Use the equal length threaded rod and pass them through the casing on the edges of the casing.
  4. Connect the threaded rod to the ceiling plates.
  5. Use the rubber mounting rings below the holes to dampen vibrations.
  6. Use the mounting nuts and washer rings to secure the threaded rods.

Image showing pass-through threaded rods holes.

Image showing pass-through threaded rods holes.

3.9 INSTALLATION OPTION B > FRAME

For maximum flexibility and ease of install, use a 3rd party wall mount heavy duty air conditioning frame to mount the Revomax II on the wall. The Needed equipment:

Needed additional equipment (not included)

  • Heavy duty 3rd party wall mount frame
  • Lifting equipment
  • Brackets (included)

Steps

  1. Place or mount the frame on the wall, make sure to place with corresponding spacing.
  2. Lift the unit on the brackets.
  3. Securely attach the unit on the frame, use the supplied rubber rings to dampen vibrations.

Image of an example wallmount.

3.10 INSTALLATION OPTION C > SURFACE

The Revomax II system can also just be placed on any stable surface. Floors or heavy duty shelves. No extra equipment needed except for lifting the unit on the target surface.

Needed additional equipment (not included)

  • Lifting equipment
  • Brackets (included)

Image of RevomaxII on surface.

3.11 WATER COOLER PLACEMENT

When using a water cooler in a closed loop system as further explained in chapter 5, it is very important the water cooler is placed properly.

A watercooler needs room to suck air into its fans and dispatch the air on the other side. To provide the watercooler with sufficient free air to use for cooling, the watercooler needs to be placed outdoors and with sufficient room to operate.

We recommend, when possible, to place the watercooler outside of direct sunlight for best performance. Also, in snowy and sandy areas it's extremely important to keep the in- and outlet free of obstacles during operation. Build a roof or shelter to protect the watercoolers in- and outlet and/or direct sunlight.

Opticlimate has several types of watercoolers in its range. There are compact models, industrial grade models and two types of alignment: horizontal and vertical. Make sure to use the type of alignment correctly.

To ensure proper heat dissipation, the water cooler requires a minimum of 3 meters of unobstructed space in front of the unit. This clearance allows for adequate airflow, which can extend up to 50 meters. It is essential to ensure that the heated air can freely exit the area without obstruction.

In situations where there is insufficient horizontal space for effective airflow dissipation, we offer vertical discharge models. These units redirect airflow upward rather than sideways, eliminating the requirement for horizontal clearance.

Diagram showing water cooler placement clearances: ABOVE - 40 CM, BACK - 40 CM, SIDE - 60 CM, SIDE - 30 CM, FRONT - 300CM.

3.12 EXAMPLE INSTALLATIONS

Image: Ceiling mounted RevomaxII unit.

Image: Ceiling mounted RevomaxII unit with airhose, inside growing area.

Image: Wall mounted RevomaxII unit.

Image: Wall mounted RevomaxII unit with airhose inside growing area.

Image: Surface mounted RevomaxII unit with plenumbox (needs hoses).

Image: Surface mounted RevomaxII unit outside the growing area with plenumbox (check chapter 6.6 for connecting air hoses).

4. WATER AND CONFIGURATIONS

4.1 WATER SUPPLY

The RevomaxII needs a clean, continuous and cool water supply to operate properly. This can be achieved in two distinct operation methods: tap water or a closed loop with an OptiClimate watercooler. Both are viable options, depending on your growing needs and surrounding situations like the availability of clean water and climate. In this chapter we will explore the first option. The closed loop is described in chapter 5 with a focus on a single RevomaxII and a single water cooler. Other configurations are possible as shown in chapter 4.4.

Check the specifications of your model in chapter 1 to determine the cool water supply in m³ per hour. In the case that your basic water supply is below 25 degrees celcius all year round without exception, you can operate without a separate water cooler.

Note that when you want to create a closed loop, the RevomaxII heats the water when in cooling mode. Make sure to have sufficient cooling power for your situation. When the inlet water temperature rises above 25 degrees Celcius, the Revomax cannot cool to specification and more cooling power is needed.

Diagram of Revomax Backside showing water connections: 1. Water Outlet, 2. Water Inlet, 3. Condensation Outlet.

4.2 PIPING

Piping is not included in the RevomaxII package as every situation is different. The system can be connected with industry-standard PE Tyleen or other type of water piping. We recommend using at least 32mm PE (Poly-Ethylene) piping with 'quick-connectors' for easy and flexible installation. A great alternative is to use PVC-C. We recommend using a certified plumber for the installation of the loop.

To determine the correct diameter for your setup, two key factors must be considered: length and complexity. We always recommend keeping the loop as short and straightforward as possible, since every bend and every additional meter reduces water flow.

There is no universal rule, as every installation differs. When in doubt, contact your dealer or local plumber for advice. As a general guideline, use 32 mm piping for shorter loops with few bends, and 40+ mm piping when length and complexity increase.

Diagram illustrating pipe sizes: 32 MM - SHORT/SIMPLE.

Diagram illustrating pipe sizes: 40+ MM - LONG/COMPLEX.

4.3 3RD PARTY WATER CONNECTIONS

To connect all piping and sensors to your system, you also need a list of water connections and accessories that fit your piping of choice. We have a comprehensive list of needed items on our knowledgebase at https://opticlimate.com/knowledge-base/in the checklist section.

4.4 SPECIAL CONFIGURATIONS

Beside the basic options, take a brief look at what we can do with the RevomaxII. All variations are perfectly viable and scalable and need a professional design and preparation from your dealer or find us at airluxtechnologies.com. The high-performing RevomaxII system needs to be installed with all hardware and guidelines (chapter 2.1) in mind to ensure long-term reliable operation.

Multi-RevomaxII setup with single cooler

Install two or more RevomaxII units in multiple growing areas or rooms, combined with one big watercooler unit.

Multi-RevomaxII setup with multiple coolers

Install multiple RevomaxII units in multiple growing areas combined with multiple watercoolers.

Option 3: RevomaxII unit outside growing area

Install the RevomaxII unit outside the growing area with our Plenumbox and airhose system.

Diagrams showing multiple views of a Plenumbox based multi-room setup, indicating components: 1. RevomaxII unit, 2. PlenumBox, 3. Airhose system, 4. Growing Area.

Whatever your growing needs

With the flexibility of the RevomaxII system you can easily scale to whatever situation you might have. There is no growing area too complex or difficult for us! Challenge us for your next project. Contact your dealer or find us at airluxtechnologies.com to guide you through the next level of indoor farming.

Image of a RevomaxII sep-fan and custom aluminium airhoses. The fan is installed integrated in the airhoses.

4.5 OPEN TAP

The most basic option is to use an open tap, continuous and steady water supply that is under 25 degrees Celsius year round. The source can be a public watersupply or a fresh watersource like a lake or river.

Solenoid valve & water leak sensor - Optional

Use our magnetic solenoid valve and water leak sensor for safety. When a leak is detected the system will shut down to prevent damage. Place the valve directly after the water source in a fixed, easy to access location. The magnetic coil of the valve must be placed upwards or alternatively to the side. Never downwards.

Strainer & Insulation - Optional

It's highly recommended to use a strainer to filter the water and insulate the water supply piping to prevent condensation build-up and optimize efficiency.

Connection diagram

Connect the system in following sequence to operate correctly:

  1. Water source
  2. Solenoid (magnetic) Valve - optional - closes when the water leak sensor detects water leakage
  3. Water strainer - optional - filters particles that could be present in the water source like a river
  4. RevomaxII water inlet
  5. RevomaxII water outlet
  6. Drainage / water recycling

Schematic overview of an open-tap installation showing numbered components.

5. BUILDING A CLOSED LOOP

5.1 WATER COOLER

The most common option is a closed loop water system. When cool fresh water is not available, economically viable or when the water temperature is above 25 degrees Celcius regularly, watercooler is mandatory for stable operation to specification.

Water cooler capacity

The needed capacity of the water cooler depends on variables like climate, season, sunshine, humidity, ambient temperatures and other hardware in operation that generates heat. Therefore, the needed cooler's capacity needs to be assessed per case.

In most moderate operating situations the rule of thumb is for the water cooler to have the same level or slightly exceeded power output versus the Revomax II unit. For example: a Revomax II 30000 (30kw) needs a watercooler that at least has the same 30 kw capacity. All our water coolers are designed with a small amount of headroom so the 32 kw industrial grade water cooler is usually a good fit.

It's possible to connect multiple Revomax unit's to a single cooler as long as the cooling capacity is met. For more information or specific watercooling questions needs contact your dealer or find us at airluxtechnologies.com.

Image of an OptiClimate Watercooler.

5.2 STEPS TO CREATE A CLOSED LOOP

After determining the correct piping diameter (chapter 4.2) and acquiring all 3rd party piping and connectors, we can start building our closed loop system. For reference to all piping diameters check our knowledgebase at https://opticlimate.com/knowledge-base/in the checklist section.

For video instructions on all steps, refer to our airluxtechnologies YouTube channel.

1. Install the pump, water cooler and RevomaxII

Install the pump, water cooler and RevomaxII in an upright position and make sure the RevomaxII has a very slight angle (1%) to the back so condensation water can run off. Instructions on placement are in chapter 3.

2. Connect the RevomaxII in- and out and air-bleeder

Install connectors from the RevomaxII in- and output to your specified piping diameter. Also install the air-bleeder on the highest point of the installation. Make sure you use teflon in all metal connections and properly glue all PVC-C piping when used. Optional but highly recommended is to install drainage taps at in- and outlet to be able to shut down water supply to the RevomaxII when needed.

Image of a Drainage tap.

Image of an Air Bleeder.

Image of a Tapsaddle.

3. Connect RevomaxII in to water cooler out

Continue to connect the RevomaxII input to the water cooler output and make sure you install a temperature sensor in this part of the loop. Use a t-connector or tap saddle to install the temperature sensor between the watercooler (out) and RevomaxII (in). Note the water flow direction (orange arrows). Make sure the loop is empty before installing the temperature sensor. We designate the water temperature as OUT because it is installed after the watercooler. Always install sideways to prevent measuring air.

Diagram showing Step 3 install sequence with Watercooler, Temperature-OUT sensor, and RevomaxII.

Image of a Tapsaddle side-view.

4. Connect the pump, air separator and two ports

Now connect the air separator to the pump and start to connect the water pump output to the water cooler input. In between we'll install a manometer and the pressure (mandatory for advanced control systems) sensor the same way as the temperature sensor in the previous step. Optionally install a manual valve to shut down water flow when needed.

Diagram showing Step 4 install sequence with Air Separator, Waterpump, Pressure Sensor, Manometer, and Watercooler.

5. Complete loop from water pump in to RevomaxII out

The loop is nearly complete. From the water pump in where the Air Separator is connected, lead the loop to the RevomaxII output. Optionally install a manual valve to shut down water flow when needed. Here we need two ports: a manometer, a pressure sensor and an extra temperature sensor in case you want to build an advanced control setup (chapter 6.7).

Diagram showing Step 5 install sequence with Revomaxll, Pressure Sensor, Temperature, Manometer, Air Separator, and Waterpump.

6. Filling Tap & Optional: Expansion Vessel and Pressure Relief Valve

First make sure to install a filling tap so your loop can be filled later on. The location of the filling tap has no impact of the operation, install it in a convenient location, preferable at a low point to be able to drain the loop. Optionally for more stable operation you can install an expansion vessel and pressure relief valve. When temperature rises, water expands. The vessel compensates for this effect. The vessel must be installed outside the loop.

Diagram showing Step 6 install sequence with RevomaxII, Pressure Valve (optional), Expansion Vessel (optional), and Filling Tap.

5.3 CONNECTION DIAGRAM

The complete loop now should look like the schematic below, you'll find all the elements in their logical locations. Make sure to install all hardware, sensors, and other components in these exact positions unless stated otherwise.

The following items are optional but recommended:

  • Pressure Valve – Releases excess pressure and prevents the loop from building up too much pressure.
  • Expansion Vessel – Collects and regulates excess pressure.
  • Drain Valve - Allows the water/glycol mix to be drained from the system when needed. Should be installed at the lowest point of the loop.

The following items are mandatory when installing a closed loop with advanced control:

  • Temperature Sensor – A second temperature sensor is required when using the advanced control setup.
  • Pressure Sensors – Detect current water pressure drops and warns the user to take action to prevent possible damage to the system.

Diagram of the complete closed loop connection.

6. CONTROL SETUP

6.1 CONNECTION BOARD

Remove the front panel to connect the supplied Smart Remote Controller and sensors. Lead the sensors to the growth area and place on crop level, outside the range of a direct lighting source. The connection board is accessible behind the front panel.

Connect the following cables to the corresponding connection ports:

  1. Smart Remote Controller
  2. RH Humidity & Light sensor - to be placed in the grow area. Detects optimal settings for humidity and night/day cycle.
  3. Room temperature sensor - to be placed in the grow area. Do not position the sensor a direct light source.
  4. Compressor start sensor
  5. Solenoid Valve (magnetic valve)
  6. Water leak sensor
  7. Dipswitch 3

Image of the RevomaxII connection board with numbered ports.

Testing & Discharge Water

When used in a closed loop setup with a cooler the system can be tested with dipswitch nr 3. When dipswitch 3 is turned on, the pump starts pumping and the valve opens without having the system fully booted up. Use this mode to discharge water, test for leaks or to vent the system from air. For more information check chapter 5.3.

Note: the system needs to be fully installed and connected for the test to work. Use dipswitch 3 for testing and discharge purposes only. When the system is in normal operation make sure to turn off dipswitch 3.

6.2 SELECT POWER CABLE

Applies to: Open Tap, Basic controlled closed Loop, Inverter controlled closed Loop

All Revomax II units must be connected to a 3-phase 400 volt power supply. Alternatively, the 6000, 10000 and 15000S model can also be powered by a standard 1-phase 230v domestic power supply.

Allways use at least the specified cable diameter for connecting the power supply to the RevomaxII. In the specification overview in chapter one you can find the specificiation for your model.

Ask assistance from a certified electronic engineer when connecting a 400v 3-phase system.

NOTE: always use a dedicated MCB and RCD type B for the Revomax II. Do not combine with other devices on the same circuit.

6.3 CONNECT POWER CABLE

Applies to: Open Tap, Basic controlled closed Loop, Inverter controlled closed Loop

Find the pass-trough on the bottom right of the front panel. Lead the open-end power cable through and lead it to the power connection board that is behind the front panel. Connect the power cable to the connection board using the schematic below. Do not forget to connect the PE ground connector.

Diagram of the Power Connection Board for 400v models.

Connect the cable in following schematic. Make sure to use the grounding PE cable for safety. Local rules and code apply.

Diagram of the Power Connection Board for 230v models (6000, 10000, 15000S only).

Image of a 400v open-end power cable.

6.4 SMART REMOTE CONTROLLER

Applies to: Open Tap, Basic controlled closed Loop, Inverter controlled closed Loop

For open tap installations, this is the final step for the control hardware. After this chapter, skip to chapter 8.

Use the supplied controller cable (USB to UTP) to connect the Smart Remote Controller (USB connector) on port 1 (UTP connector) on the control board in the Revomax unit (chapter 4.1). After powering up the Smart Remote Controller (use the supplied power adapter) and RevomaxII, the unit will first initialize, this can take a few minutes. All valves and sensors are automatically tested during startup. The remote controller cannot be operated during this initializing phase. You will see several screens pop-up and close again, this is normal.

Check the RevomaxII user manual for daily operation and configuration of the Smart Remote Controller.

Image of a Controller cable.

Image showing connection to Power Supply.

6.5 BASIC CONTROLLED - CLOSED LOOP

Applies to: Basic Closed Loop

The water based elements of the basic closed loop system are now installed and need to be connected to its central control hardware. For the advanced control setup, skip to chapter 6.7.

The basic setup is controlled by a SmartBox 6/3 and controls the water pump and water cooler via a power outlet. You already selected and connected power, and the Smart Remote Controller. For reference we'll recap these steps and add some final steps.

1. Select correct cable and install an MCD and RCD-B

Check the required cable diameter in the specifications and install the power cable, MCD and RCD-B as described in chapter 6.2. Ask a certified electrician to install these elements.

2. Install the correct power cable using

Use the pass-through to install the open-end power cable to the connection board as described in chapter 6.3. Ask a certified electrician to install these elements.

Image of P1 port on Smartbox 6/3.

3. Install and connect sensors

Connect the temperature sensor, the one installed in front of the RevomaxII to the P1 port on the SmartBox 6/3. The port is located in the bottom-left of the Smartbox 6/3.

Also connect the humidity/light sensor to the RevomaxII on position 2 as described in chapter 6.1. Route the humidity/light sensor to the growing area and hang halfway between the plant canopy and the fixtures for optimal readings.

Image of Humidity/Light Sensor.

Last part of this step is the compressor start stop sensor. Connect it to position 4 of the connection board (chapter 6.1). Now lead the communication cable to the Smartbox 6/3 and connect it to the in/out port.

Image of a Start-stop sensor.

4. Communication cable to Smart Remote Controller

Connect the Smart Remote Controller with the supplied UTP-USB cable as described in chapter 6.4.

5. Connect the water cooler and water pump to the SmartBox 6/3

The last step is to connect the water cooler to the smart 230v power connector port OUT-1 and the water pump to the smart 230v port OUT-3. It is important you use these specific ports as they are pre-configured.

Complete control schematic

The complete control schematic now must look like this.

Diagram of the complete control schematic.

Diagram of the Basic control setup.

6.6 BASIC CONTROLLED - CLOSED LOOP - FIRST USE

Before we can start using the system we first need to check some basic settings. In 6 steps we'll guide you through all steps to get your RevomaxII operational.

1. Check essential settings

A few settings need to be checked. First make sure the system is in water cooler mode. Navigate to MENU > SETTINGS > OPTICLIMATE SETTINGS > S.06 and make sure it is set to ON.

The second setting is the internal pressure, which is in the same menu under S.64. Make sure it is set to 23 bar.

2. First Run

First use chapter 7 to fill the loop. Now we need to force the RevomaxII into cooling mode. Use heaters and/or fixtures to heat the room to around 25 degrees Celcius and is stable. Now set the RevomaxII to 16 degrees Celcius to force it into cooling mode. The pump and fan should be activated automatically.

3. Water pressure and internal valve

The water pressure must be at least 0.5 bar during operation. Add mode water/glycol if the threshold is not met. Now check the internal valve which must be open. Navigate to: MENU > SETTINGS > OUTPUTS > Q.05 (water valve). The bar must be filled out to 1600 steps.

4. Delta Temperature

On the SmartBox 6/3, check the reference temperature which must be set to 32 degrees Celcius. Click UP, ENTER, ENTER and use the UP/DOWN keys to change the temperature if needed.

Now, on the Smart Remote Controller navigate to: MENU > SETTINGS > ALL SENSORS

Set target temperatures I:11 to 32 degrees Celcius and I:08 to 37 degrees Celcius. This means the delta (difference) is 5 degrees, which is optimal. Control the delta temperature by changing the water flow.

  • When the delta is too LOW (less than 5 degrees): CLOSE the valve, there is too much flow.
  • When the delta is too HIGH (more than 5 degrees): OPEN the valve, there is too little flow.

Adjust in small increments and wait for the system to respond. This can take a few minutes. After all temperatures are stable for a few hours, adjust the room temperature to the desired temperature.

Diagram showing Water valve control.

Diagram showing Water temperature control.

Diagram of Manual valve install sequence.

5. Base settings

To make sure the system responds correctly to operating settings like the timer, we need to set the time and date. On the Smart Remote Controller, navigate to: MENU > SETTINGS > USER PREFERENCES . SET TIME/DATE.

Also set the target temperature and humidity for both day and night. From the main menu click on the respective value and use the + and - icons to adjust. Click the sun and moon icons to switch settings for day and night.

The user manual goes further in depth and addresses more options and features.

Image of the Time and date menu.

Image showing Set target values.

6.7 INVERTER CONTROLLED - CLOSED LOOP

For systems above 15 kWatts of cooling power, you can install inverters for more precise control over the temperature and a more stable climate overall in your growing area. The advanced setup automates the water flow control and seamlessly and continuously adjusts the pump and the watercooler fan.

When using the advanced setup with inverters, contact your dealer or our professionals at Airlux Technologies for additional support and system design.

The advanced control method differ in a few key areas. Follow these steps.

1. Select correct cable and install an MCD and RCD-B

Check the required cable diameter in the specifications and install the power cable, MCD and RCD-B as described in chapter 6.2. Ask a certified electrician to install these elements.

2. Install the correct power cable using

Use the pass-through to install the open-end power cable to the connection board as described in chapter 6.3. Ask a certified electrician to install these elements.

3. Install and connect sensors

In the advanced control setup make sure to have installed the second temperature sensor as instructed in chapter 5.2. Connect the first sensor, the one installed in front of the RevomaxII to the P1 port on the SmartBox 8/0. The port is located in the bottom-left of the Smartbox 8/0. The second temperature sensor goes to P2.

Diagram showing Temperature sensors install sequence.

Also connect the humidity/light sensor to the RevomaxII on position 2 as described in chapter 6.1. Route the humidity/light sensor to the growing area and hang halfway between the plant canopy and the fixtures for optimal readings.

Last part of this step is the compressor start stop sensor. Connect it to position 4 of the connection board (chapter 6.1). Now lead the communication cable to the Smartbox 8/0 and connect it to the in/out port.

4. Pressure sensors

In the advanced setup we also install two pressure sensors on the positions as described in chapter 5.2. Connect the first one (pressure low - in front of the water pump) on P5 and the second one (pressure high) after the water pump) to P6. The pressure sensors can sense a drop in pressure and can automatically shut down the system to prevent damage.

Image of Operating mode menu.

Image of an Inverter.

Image of a SmartBox 8/0.

Image of a Tapsaddle.

Image of a Tapsaddle sideview.

Image of a Pressure Sensor.

Diagram showing Pressuresensors install sequence.

4. Communication cable to Smart Remote Controller

Connect the Smart Remote Controller with the supplied UTP-USB cable as described in chapter 6.4.

5. Connecting Smartbox 8/0 to Inverters

The system contains two inverters: a 400V 3-phase version for the water pump (inverter 1) and a 230V 1-phase version for the water cooler (inverter 2). Both must be connected using the supplied BLUE interlink cable that is labeled on both sides. The cable end labeled VFD must be connected to the inverter, the cable end labeled Smartport must be connected to the SmartBox.

Connect the 230V water cooler inverter to P3 on the Smartbox and the 400V water pump inverter to P4 on the Smartbox.

Image of a Custom labeled interlink cable.

6. Connecting Inverter 1 to water pump

The inverter must be connected to the pump with a custom power cable setup. Pumps must be connected with a 3-phase inverter. Make sure to order a 3-phase pump in this situation. Connect the power cable in the correct manner, as stated below.

Diagram showing Power schematic inverter to pump.

7. Connecting Inverter 2 to water cooler fan

The inverters must be connected to the watercooler(fan) with a custom power cable setup. Cooler fan must be connected to a single-phase inverter. Make sure to connect the power cable in the correct manner, as stated below.

Diagram showing Power schematic inverter to watercooler fan.

6.8 INVERTER CONTROLLED - CLOSED LOOP - FIRST USE

The first use sequence of the inverter controlled setup is the same as the sequence for the basic controlled option (chapter 6.4). Follow the same steps with the exception that the delta temperature is automated. Just skip that step.

Diagram of the Advanced control schematic.

7. FILLING THE LOOP

7.1 GLYCOL

The RevomaxII closed loop systems are compatible with a water-glycol mix. When the system is used in areas that have below zero degrees Celcius temperatures regularly (Winter-time), a Water-Glycol Mix is mandatory to prevent the system from freezing up and corrosion.

For each potential degree Celcius below zero, you need 1% of glycol in your mix. For example, in the Netherlands temperatures rarely, if ever, reach below -15 degrees Celcius. So a safe mix and a bit of headroom a 20% mix is advised.

Add the correct amount of glycol to the system first, then water until static pressure is 1.5 bar (The installed manometer, not the manometer on the RevomaxII unit). In the case the system is already filled with water, drain double the amount of calculated glycol of water first, then add the glycol and re-fill the water until pressurized at 1.5 bar again.

NOTE: on the market you can obtain pure glycol or pre-mixed water-glycol. Make sure to use the correct type. Airlux Technologies strongly recommend PROPYLENE glycol, not ETHYLENE.

Image of Propylene Glycol.

7.2 FILLING THE LOOP

Note: when the temperature at the cooler location is below zero Celcius, do not fill the system. This can lead to permanent damage to the cooler.

Steps

  1. Check all water connections before filling the loop.
  2. Connect water supply to the filling tap.
  3. Open the air bleeder that is installed on the highest point of the installation.
  4. Open the water supply and start filling the loop, wait for pressure to build to 1 bar and for all excess air to escape.
  5. Make sure the RevomaxII is powered but not turned on. Start the pump with dipswitch 3 (chapter 6.1). Run the RevomaxII for two hours and check for leaks. Check the manometer during the test run and make sure pressure never drops below 0.5 bar.
  6. Disable dipswitch 3 and drain the loop. Collect the water to determine the amount of glycol that needs to be added.
  7. Re-fill the loop with the water-glycol mix with a submersible pump.
  8. Activate the pump again with dipswitch 3 and make sure the system builds up pressure to 1.5 bar on the manometer that is located before the pump.
  9. Close the filling tap and remove any water sources and submersible pump. Your system is now filled up correctly.

Image of a Manometer - Check Pressure in Bar.

Image of a Submersible Pump.

8. SPECIALS

8.1 MULTIPLE REVOMAXII UNITS, SINGLE COOLER

For efficiency purposes you are able to install multiple RevomaxII units on a single cooler in a single closed loop. As long as the water cooler has sufficient cooling capacity to cool the combined heated water generated by the RevomaxII units. All install instructions from chapter 6.2 or 6.3 still apply. Only add extra piping and the second and/or third RevomaxII Unit. The setup must be built with identical models to work properly.

Diagram illustrating a setup with Waterpump, Watercooler, Tichelmann Principle, and multiple RevomaxII units.

8.2 CONNECTING A PLENUMBOX

When the RevomaxII unit is placed outside of the growing area, you need a PlenumBox to connect the unit to an air hose system. It is important that the incoming air flow is at least twice the diameter of the output of the air distribution. This is important to ensure proper air pressure inside the unit.

For example: when the output diameter is 250 mm, the plenumbox needs a minimum of two 250mm air intake hoses for proper cooling power. Note, when calculating air intake capacity, the actual double air intake cannot be calculated by diameter only. Always calculate the total surface of the hoses to actually find the correct diameters.

Diagram of a Plenum Box.

9. CONNECTION KITS

Both the installation with and without water cooler require a basic installation package that is needed for installing the respective option. Without this package the system cannot be installed to a normal operating situation. All RevomaxII units come with the Smart Remote Controller.

9.1 WITHOUT WATERCOOLER

For basic operation on a continuous tap water installation acquire all needed piping as recommended in chapter 4.2. The tap-water leak prevention kit is optional.

SKU 1-7811 'tapwater leak-prevention kit'

  • R-7962 water leakage sensor
  • A1-41 Solenoid (magnetic) valve
  • A1-101 connectorset

Image of Smart Remote Controller (included).

Image of Solenoid (Magnetic) Valve.

9.2 WITH WATERCOOLER, BASIC CONTROLLED

For a closed loop with basic control installation acquire all needed piping as recommended in chapter 4.2. One of the connection kits is mandatory to create a working setup.

SKU 1-85805 'Water cooler kit - Basic Control - 5 mtr'

  • 2-587 Smartbox 6/3 EU
  • 1-7850 Start Sensor
  • 2-557 Water temperature sensor G1/4" 5 mtr
  • 2-360 Communication cable 5 mtr

SKU 1-85810 'Water cooler kit - Basic Control - 10 mtr'

  • 2-587 Smartbox 6/3 EU
  • 1-7850 Start Sensor
  • 2-556 Water temperature sensor G1/4" 10 mtr
  • 2-361 Communication cable 10 mtr

9.3 WITH WATERCOOLER, INVERTER CONTROLLED

For a closed loop with advanced control installation acquire all needed piping as recommended in chapter 4.2. One of the connection kits is mandatory to create a working setup.

SKU 1-85705 'Water cooler kit - Inverter Controlled - 5 mtr'

  • 2-586 Smartbox 8/0 EU
  • 1-7850 Start Sensor
  • 2-557 Water temperature sensor G1/4" 5 mtr (2x)
  • 2-559 Water pressure sensor G1/4" 5 mtr (2x)
  • 1-861 Fan/Pump Inverter 1.5kW 1-phase
  • 1-862 Fan/Pump Inverrter 1.5kW 3-phase
  • 1-578 Blue Interlink Cable VFD 5 mtr (2x)
  • 2-360 Communication cable 5 mtr

SKU 1-85705 'Water cooler kit - Inverter Controlled - 10 mtr'

  • 2-586 Smartbox 8/0 EU
  • 1-7850 Start Sensor
  • 2-556 Water temperature sensor G1/4" 10 mtr (2x)
  • 2-558 Water pressure sensor G1/4" 10 mtr (2x)
  • 1-861 Fan/Pump Inverter 1.5kW 1-phase
  • 1-862 Fan/Pump Inverrter 1.5kW 3-phase
  • 1-579 Blue Interlink Cable VFD 10 mtr (2x)
  • 2-361 Communication cable 10 mtr

9.4 AIRHOSES

Hoses are available in different materials, lengths and diameter sizes. There are two material variants:

  1. LPDE foil - Economical option
  2. Fabric - LVS - Prevents condensation, anti-bacterial and washable

Ask your dealer for available options, lengths and diameters or find us at airluxtechnologies.com.

Image of an OptiClimate watercooler.

Image of a Plenum Box.

Image of an Example with Plenum Box.

10. ACCESSORIES COMPATIBILITY

The RevomaxII has endless possibilities and configurations. In the matrix below you can find what accessories are compatible with what setup. Make sure to order one of the available connection kits as described in chapter 9.

For specific needs ask your dealer or find us at airluxtechnologies.com.

OptiClimate RevomaxII - All accessories & compatibility

SKUPeripheralConfig opt.1 Open TapConfig opt. 2 Basic Contr.Config opt. 3 Inverter Controlled
CABLES
2-360Revomax Communication cable 5 mtr
2-361Revomax Comminication cable 10 mtr
2-362Revomax Communication cable 20 mtr
1-578Interlink Inverter Cable Blue VFD 5 mtr
1-579Interlink Inverter Cable Blue VFD 10 mtr
1-580Interlink Inverter Cable Blue VFD 20 mtr
2-363Interlink Extension Cable Black VFD 5 mtr
2-364Interlink Extension Cable Black VFD 10 mtr
2-396Interlink Extension Cable Black VFD 20 mtr
WATER COOLER ACCESSORIES
A 1.8171Waterpump 32kw P5S-120/4 - No Inverter 230V-Phase 1 (basic cntrol)
A 1.87171Waterpump 32kw P5S-120/4T - Inverter 400V-Phase3 (advanced control)
2-587Smartbox 6/3 EU
2-586SmartBox 8/0
1-592Repeaterbox 8
2-557Pressure Sensor 0-10 bar G1/4" thread Smartport 5 mtr
2-558Pressure Sensor 0-10 bar G1/4" thread Smartport 10 mtr
1-861Fan/Pump Inverter VFD 1.5KW, 200V~240V (1 phase)
1-862Fan/Pump Inverter VFD 1.5kW, 380-480V (3 phase)
1-7851Temperature sensor Aluminium Revomax 5mt
1-7852Temperature sensor Aluminium Revomax 10mt
1-7853Humidity (RH) sensor + Lightcel 5m Revomax
1-7804Smart Remote Controller SILVER Revomax
1-7803Smart Remote Controller cable 7 mtr Revomax
INSTALLATION PARTS
VariousDustfilters - Various sizes and models
VariousAirhose distribution hoses, different sizes, LPDE or Textile
VariousInsulator Springs for 6000, 10000 and 15000
VariousPlenumboxes, different sizes

Extension guide

When expanding your system outside of the common one RevomaxII on one water cooler you need extra accessories to get everything connected. For example, for every extra RevomxII to one water cooler, you need an extra start sensor and a communication cable. Another example: 3 RevomaxII systems to 2 water coolers need (on top of the connection kits) 2 repeaterboxes to expand control ports, 2 black interlink cables to connect the repeaterboxes to the Smartbox, an extra set of inverters and their respective blue interlink cables.

Contact your dealer or find us at airluxtechnologies.com when installing a system that is connected with more than one RevomaxII and/or water cooler.

11. TROUBLESHOOTING

Most common errors are easily resolved. For more advanced troubleshooting check our knowledgebase at https://opticlimate.com/nl/knowledge-base/

Error/SymptomPossible CauseCheckSolution
RevomaxII does not turn onRevomaxII is not properly poweredAre any LED's lighting up on the control board (chapter 4)Make sure the power supply is connected properly to all three phases (chapter 4)
No valid firmware is installedIs 230v connected to all three phases of the powerboard (chapter 4)Make sure the power supply is connected properly to all three phases (chapter 4)
Does the remote controller show 'RevomaxII is missing firmware' messageExecute the update process from the remote controller
OptiClimate communication is lostNo communication between the USB side of the communication cable, possible cable defectIs the communication cable properly connected on the Smart Remote Controller (USB) Chapter 4Properly (re)connect the communication cable or replace the cable when still in error
Connection lost with RevomaxII 'OptiClimate 1'No communication between the UTP side of the communication cable, possible cable defectIs the communication cable properly connected on the RevomaxII (UTP) Chapter 4Properly (re)connect the communication cable or replace the cable when still in error
The power connection on the RevomaxII was lostIs 230v connected to all three phases of the powerboard (chapter 4)Make sure the power supply is connected properly to all three phases (chapter 4)
During update process: Update file is corrupt (Smart remote controller)The UDP (update) file cannot be read from the USB memory stickIs the UDP file the same as you have received from our servicedeskRe-download the UDP you received from us to the USB memory stick and retry the update process
The USB drive was disconnected during the update processIs the USB drive firmly connected to the USB port on the Smart Remote ControllerRetry the update process
Is the USB drive readable on a Windows PCFormat the USB memory stick as FAT32 on a Windows PC, re-download the UDP file and retry the update.
Error while flashing firmwareDuring the update process, the connection between the RevomaxII and Smart Remote Controller was lostWas the power connection lost on the RevomaxIIRe-boot the whole system (power-cycle) and retry the update process.
Was the communication lost during the update processRe-connect and/or replace the communication cable and retry the update process.
The OptiClimate 0 is missing firmwareThe update process was interruptedWas the power lost on the Smart Remote Controller during the update processMake sure the power supply is connected to the Remote Controller and retry the update process.
Was the power lost on the RevomaxII during the update processMake sure the power supply is connected to the RevomaxII and retry the update process.
Was the communication lost between the RevomaxII and Smart Remote ControllerRe-connect and/or replace the communication cable and retry the update process.
Temperature reading remains on zero degrees and humidity on 50%. This does not change.No communication between the RevomaxII and Smart Remote Controller, possible cable defectIs the communication cable properly connected on the Smart Remote Controller (USB) Chapter 4Properly (re)connect the communication cable or replace the cable when still in error.
Is the communication cable properly connected on the RevomaxII (UTP) Chapter 4Properly (re)connect the communication cable or replace the cable when still in error.
Was the power lost on the Smart Remote Controller during the update processMake sure the power supply is connected to the Remote Controller and retry the update process.
The Smart Remote Controller does not respond and/or boots up when powered.The Smart Remote Controller is disabled with hardware turn-off.Press the physical on/off button on the right-hand side for 10 seconds.The Smart Remote Controller should now activate and boot-up.
The power supply adapter is defect.Replace the power supply adapter.The Smart Remote Controller should now activate and boot-up.

10. WARRANTY

The Revomax II series and accessories are designed and manufactured with maximum care and craftsmanship. Airlux Technologies warrants the delivered goods to be free of defects for the duration of the applicable warranty period under normal use and conditions after the original purchase date. When the product shows any defects within this period that is not due to improper use, Airlux Technologies will replace or repair the defect product with a suitable replacement with at least the same functionality and specifications. Warranty of the replaced products will remain under warranty for the remaining period from the original product and purchase date. For service, the owner ships the unit to the closest Airlux Technologies service location, to be determined by the service desk. Airlux Technologies will require the original receipt to determine the warranty eligibility.

Contact your dealer for warranty information or find us at airluxtechnologies.com

By Phone: +31 20 776 6006

By e-mail: support@airluxtechnologies.com

Direct link: https://www.opticlimate.com/nl/knowledge-base/

Scan the QR-code to go to our online knowledge base for the latest manuals and information.

Models: 6000 REV2, REVOMAXII Grow Room Air Conditioning Unit, REVOMAXII, Grow Room Air Conditioning Unit, Room Air Conditioning Unit, Air Conditioning Unit, Conditioning Unit, Unit

PDF preview unavailable. Download the PDF instead.

opticlimate-revomaxii-installation-manual-v1-5-online Adobe InDesign 20.5 (Macintosh) iLovePDF

Related Documents

PreviewOptiClimate RevomaxII User Manual: Advanced Climate Control for Growing
Comprehensive user manual for the OptiClimate RevomaxII, detailing its advanced climate control features, specifications, operation, and maintenance for optimal growing environments.
PreviewOptiClimate PRO3 and PRO4 Split (Inverter) Series Installation and User Guide
Comprehensive installation and user guide for the OptiClimate PRO3 and PRO4 Split (Inverter) Series, covering setup, electrical connections, operation, settings, and troubleshooting for optimal climate control.
PreviewOpticlimate REVOMAX II Installation and User Guide
Comprehensive installation and user guide for the Opticlimate REVOMAX II climate control system, detailing setup, electrical connections, and operation for optimal performance.