Installation Guide for TECO models including: Pro-9900_QIG_EN.pdf, Pro-9900 Automatic Vibration Measurement and Acceptance Instrument, Pro-9900, Automatic Vibration Measurement and Acceptance Instrument

Pro-9900 QIG

MOCET Network Inc.

Pro-9900 Quick Installation Guide - Tecom

Page 3 Tecom Pro-9900 Quick Installation Guide Illustration: After opening the toolbox, perform the following steps 1. Connect the Power Back to the 2.

PDF preview unavailable. Download the PDF instead.

Pro-9900 QIG EN
Tecom Pro-9900 Quick Installation Guide
Pro-9900 Quick Installation Guide
TECO Group Pro-9900 Portable Vibration Acceptance Instrumentcan be applied in analysis & acceptance of vibration problems for rotary machines. Setup is quick and easy. Technicians just go thru simple steps with Pro-9900 Auto software running on tablet to understand potential vibration issues.
It is an essential tool for technicians working in technical support, maintenance, repair and related fields.

Product contents

a. Tool Box :

x1

­ xDAQ-600

x1

­ IEPE Vibration Gauge x1

­ Double head screw

x1

­ Magnet holder

x1

­ Winding line

x1

­ Power Bank

x1

­ Vibration Pole

x1

­ Power Bank

x1

10"Tablet (with Auto & PMS Software)

b. Tablet Pack

x1

­ Windows Tablet w/keypro x1

c. Action Pack

(soft case 2 pieces)

x1

d. Power Charger

(for Tablet)

x1

Page 1

Tecom Pro-9900 Quick Installation Guide
Pro-9900
Quick Settings and Connection
1. Connect the Power Bank to the power jack (DC) of the Smart IoT Gateway xDAQ600, and then turn on the Power Bank. The default password of the tablet is demo.
2. After the WAN LED (orange) is on and wait for around 30 seconds. Then search Wi-Fi AP and start the Wi-Fi connection.
3. On the Tablet, please enterWi-Fimode to find TECOM_XXXXXX Wi-Fi SSID. Then, confirm "XXXXXX" 6-digits are exactly the same as the last 6-digits of MAC address, printed on the serial number label of the Smart IoT Gateway. Select "TECOM_XXXXXX" for network connection. The Tablet will show "Connected" to indicate a successful Wi-Fi connection between the Tablet and the Gateway. This procedure only needs to be done once. The Tablet will automatically connect to the Gateway after on.
This 6-digit number must be the same as the TECOM_XXXXXX 6-digit number on the Tablet Wi-Fi network.
4. Install the magnetic vibration gauge (or w/vibration pole) to the correct position of the device under measure.
5. After the completion of steps 1 to 4, the Measure and Acceptance procedures by using Pro-9900 Auto software on Tablet is ready.
Page 2

Tecom Pro-9900 Quick Installation Guide

Illustration: After opening the toolbox, perform the following steps

1. Connect the Power Back to the

2. Insert keypro into Type C interface

the gateway and wait for about 30

seconds for the gateway to start.

3. Turn on the power on the tablet

4. Find xDAQ-600 Wi-Fi SSID and connect. 5. Select PMS APP to open

Page 3

Tecom Pro-9900 Quick Installation Guide
Page 4

