GivEnergy Hybrid Inverter Generation 1 Installation Manual

Models: HY 3.6, HY 5.0

Version: 1.0 (09/23)

Specifications

A TRUE MULTI-TASKER: Battery Inverter and Solar Inverter in One

The first generation hybrid inverter can be coupled directly with solar panels to generate electricity in the property during daylight hours, as well as store any excess energy for later use in our batteries to minimise export. Additionally, it will minimise import by discharging to meet demand in the property.

The Hybrid Inverter Gen 1 is connected to our Gen 1 batteries using a ring terminal to ring terminal cable, and ring terminal to all in one plug for our Gen 2 batteries.

SpecificationsDetails
Dimensions440H x 260D x 480W (mm)
Weight24 Kg
Warranty12 years
Operational temperature-25°C - 55°C
Max. DC Input Power15kW
Start Up Voltage3.6kW - 140V
5.0kW - 140V

Box Contents

ItemItem NameQty
AInverter1
BMounting Bracket1
CWiFi or 4G (additional)1
DBattery Terminal Cover1
EBMS, RS485 Communications Port Cover1
FAC Supply Terminal Cover1
GCover Screw14
HInverter Security Pin2
IMounting Frame Fixings4
JBattery Input Terminations2

Diagram showing the contents of the inverter box, labeled A through J.

General Information

Introduction

All information contained in this booklet refers to the assembly, installation, commissioning, and maintenance of the Generation 1 Hybrid Inverter. Please retain this manual for future reference.

Legal Disclaimer: This document is the property of GivEnergy, reproduction is prohibited.

Installation Requirements

Installation of all GivEnergy equipment must be carried out by a GivEnergy Approved Installer.

Unit Information

The Hybrid Inverter is a battery inverter and solar inverter in one. It is bi-directional, meaning it can charge from the grid (AC coupled) and from solar (DC coupled).

Storing the Inverter

The unit must be stored in its original packaging at temperatures between 5°C - 60°C. Do not stack more than 4 units on top of each other.

Packaging Contents

When unpacking, please check the following:

If any damaged or missing parts are found, please contact GivEnergy on 01377 252 874 or email support@givenergy.co.uk immediately. Returns must be provided in original or equivalent packaging. The cardboard packaging is recyclable.

Components

ItemItem Name
APower Flow Direction Indicators
BOperation Status Indicator
CBattery Input Terminals and Cover
DWiFi or 4G Communications Module and USB Port
EBat > NTC and RS485 Communication
FBMS Communications, Load Monitor Communications
GAC Supply Terminals/EPS Supply Terminals and Cover
HSerial No.
ISpecification Label

Diagram illustrating the components and connection points on the GivEnergy Hybrid Inverter.

Safety and Installation

Safety Instructions

Extra care and attention must be taken when installing and maintaining any GivEnergy equipment. The system is capable of retaining a high voltage, even when disconnected.

If you suspect something is wrong with the inverter, contact GivEnergy on 01377 252 874 or email support@givenergy.co.uk.

If any damaged or missing parts are found, please contact GivEnergy on 01377 252 874 or email support@givenergy.co.uk immediately. Returns must be provided in original or equivalent packaging.

All electrical installations must be carried out by a qualified and registered Electrician and in accordance with the IEE Wiring Regulations.

During operation, the heat sink may become hot. Do not touch the heat sink at the sides, or the top of the inverter when in operation.

The inverter is designed to be connected to the grid; connecting your inverter to a generator or other power source can result in damage to the inverter or external devices.

All GivEnergy equipment must be installed by a GivEnergy Approved Installer.

Precautions

It is very important for system safety and efficient operation to use appropriate cables for battery connections. 16mm² (minimum) tri-rated cables must be used for DC battery connections.

The voltage of the battery connected must not exceed 60V (or it will damage the inverter and void any warranty).

Only GivEnergy batteries should be connected to our inverters.

Reversed polarity will damage the inverter.

The battery must be installed in accordance with the Battery Installation Guide.

Installation Location Requirements

The inverter must be installed in an easily accessible location, the status display must be visible and not obstructed.

Please ensure that the wall to be mounted on is sufficient enough to hold the weight of the inverter and battery pack.

The inverter must be installed in a well ventilated area, the ambient temperature should be below 40°C to ensure optimal operation.

The inverter must be installed vertically with connections always positioned at the bottom, never install horizontally, and avoid tilting the unit.

The inverter must be installed under a canopy if installing externally. Avoid direct sunlight and near water sources.

Mount the inverter at least 3 feet above ground level (outside only).

Step-by-Step Installation

  1. Wall thickness for mounting the inverter must be no less than 100mm. Remove the wall mounting bracket from the back of the inverter and place horizontally onto the wall and mark the position of the bracket holes.

    Diagram showing the dimensions for marking mounting bracket holes on a wall (338mm width, 169mm height).

  2. Drill 4 holes at the marked positions, at least 75mm deep. Fix the mounting bracket to the wall using 4 x M6x50 expansion bolts.

    Please note: If fitting the inverter to a non-masonry wall, different fixings will be required.

    Diagram illustrating drilling 4 holes at marked positions, at least 75mm deep, for M6x50 expansion bolts. Shows M6 bolt size.

  3. Mount the inverter onto the mounting bracket.

    Illustration of mounting the inverter onto the wall bracket.

  4. Insert the 2 x M4 safety locking screws on the left and right side to prevent the inverter from being lifted off the bracket.

    Diagram showing the insertion of 2 x M4 safety locking screws on the left and right side to secure the inverter to the bracket.

Clearance and Maintenance

Space Clearance

There must be adequate clearance around the inverter to allow for heat dissipation. The diagram below illustrates the space required around the inverter.

Diagram illustrating required clearance around the inverter: 300mm top/bottom, 250mm sides.

Maintenance

When maintaining and cleaning the inverter, the whole system must be powered down. Please refrain from using cleaning products on the surface of the inverter.

To ensure your inverter operates optimally at all times, annual maintenance checks need to be carried out. Check for visible damage or discolouration of the switch, and that the cables are intact. Please ensure that the top of the inverter is not obstructed in any way.

Whilst the inverter is powered down, we recommend operating the PV rotary isolator from ON to OFF 2-3 times, this cleans the contacts of the rotary switch. Please note: do not carry out this maintenance while the inverter is switched on.

Connections Overview

ItemItem Name
APV Input
BBattery DC Terminals
CPV Isolation Switch
DCommunication/DRM Ports
EUSB Port
FEPS Supply Terminals
GAC Supply Terminals

Diagram showing the connection ports on the rear of the inverter, labeled A through G.

AC Utility Grid Connection

Cable size requirements for the Hybrid Inverter are dependent on the model:

The recommended maximum cable length should not exceed 50m as the resistance of the cable will consume inverter output power and reduce the inverter efficiency.

You must install a separate AC circuit-breaker per inverter in order to ensure that it is adequately protected and can be safely disconnected under load.

Diagram showing the AC supply connection terminals.

Diagram showing the backup connection terminals.

Connecting to the EPS

The Emergency Power Supply (EPS) can provide a maximum output power of 5000W (dependent on inverter model, see table below) during a grid failure. This output must be protected as close to the inverter as possible, with a double pole 30mA RCD rated at up to 20A.

There are four approved methods to connect to the EPS, please refer to the EPS Connection Guide on our Knowledge Base for more information.

Maximum Power Output
Hybrid Gen 1 2.6
Max. Power Output (Battery & Solar)5000W
Max. Power Output from Battery2600W
Hybrid Gen 1 5.0
Max. Power Output (Battery & Solar)3600W
Max. Power Output from Battery2600W

If the backup terminals are used, please ensure the following:

The EPS MAX output power is 5000W (dependent on inverter model, see table above). If the load is greater than 5000W the inverter will stop outputting and go into fault. The EPS output will only operate when the battery(s) have capacity available. Any other grid tied generation must be supplied from the grid side of the changeover switch to avoid damage to the inverter, and voiding any warranty (see the following diagrams for reference).

Full Property Backup

Diagram illustrating incorrect wiring for full property backup with a manual or automatic changeover switch, showing a cross [X] on the connection path.

Diagram illustrating correct wiring for full property backup with a manual or automatic changeover switch, showing a checkmark [✓] on the connection path.

Connecting the Battery to the Inverter

  1. A DC MCB must be installed between the master battery and the inverter of Gen 1 batteries (not less than 100A), this will ensure the inverter can be safely disconnected during maintenance. Please note that a separate DC MCB is not required with Gen 2 batteries as they have one integrated, unless Gen 1 batteries are installed after a Gen 2 battery pack.

  2. Check the battery nominal voltage and polarity. When connecting a Gen 1 inverter to a Gen 1 battery (2.6kWh, 5.2kWh, 8.2kWh), a ring terminal to ring terminal cable must be used.

    Diagram showing the connection of a Gen 1 inverter to a Gen 1 battery using a ring terminal to ring terminal cable.

  3. When connecting a Gen 1 inverter to a Gen 2 battery (9.5kWh), a ring terminal to all in one cable must be used. Connect the ring terminal cable onto the battery terminal connection on the inverter. The other end can then be connected to the A-socket on the Gen 2 battery (ensure that the red clip is facing away from the inverter, and is pushed in securely).

    Diagram showing the connection of a Gen 1 inverter to a Gen 2 battery using a ring terminal to all-in-one cable.

  4. If connecting additional Gen 1 batteries after a Gen 2 battery, you must install a DC MCB in between the Gen 2 and the Gen 1 battery to ensure that the Gen 1 battery can be safely isolated, as it has no in-built isolation.

    Diagram illustrating the installation of additional Gen 1 batteries after a Gen 2 battery, showing the placement of a DC MCB.

Connecting MID Approved Meter to Inverter

In the system, a MID approved meter must be installed to ensure correct monitoring of the grid power. The inverter uses this information to decide whether to charge or discharge the battery.

The CT clamp that is connected to the MID approved meter must be installed around the live incoming supply to the property, with the arrow pointing in the direction of grid import, in order to monitor the complete consumption of the building.

Diagram showing the connection of a MID-approved meter to the inverter.

Communication Connections

Diagram showing the communication and network ports: BMS, DRM, Meter, CT.

Start-Up and Shut-Down of the Inverter

Start-Up Procedure

  1. Connect the AC circuit breaker, ensure that the system is powered and commissioned using the portal/App. Ensure that the grid power is reading identical to that of the MID approved meter (this can be found on the screen of the meter).
  2. Turn on the PV switch [power switch symbol].
  3. Turn on the battery breaker [power switch symbol].
  4. Turn on the battery [power switch symbol].
  5. The inverter will start automatically when the PV voltage is higher than 150V, and the battery voltage is higher than 46.4V.

Shutdown Procedure

  1. Turn off the battery [power switch symbol].
  2. Disconnect the AC circuit breaker to prevent it from being reactivated.
  3. Disconnect the battery breaker to prevent it from being reactivated.
  4. Turn off the PV switch [power switch symbol].
  5. Check the inverter operating status.
  6. Wait until all LEDs have gone out. The inverter is now shut down.

Commissioning & Decommissioning a System

All systems must be commissioned to ensure correct battery and meter communications, as well as connection to the online portal. Note: Without commissioning, the system may not operate correctly.

Check that all the wires are securely connected before the battery breaker and the AC isolator is switched on. You MUST set the parameters of the battery according to your battery system.

Accessing the Commissioning Portal

Sign into the online portal at https://portal.givenergy.cloud [link] with your GivEnergy Engineer login. If you are a first time user, and you do not have an account or Engineer login, please consult your supplier to get this set up.

To download a fully illustrated guide, please visit our Knowledge Base at www.givenergy.co.uk [link].

Uninstalling the Inverter

  1. Follow the shut-down procedure.
  2. Remove all connections and cables from the inverter.
  3. Remove the locking pins which are securing the inverter to the bracket.
  4. Lift the inverter off the bracket.
  5. Remove the wall bracket.

Packaging the Inverter

If possible, always pack the inverter in its original packaging and secure it with tension belts. If this is not available, you may also use an equivalent sized box. The box must be capable of being closed completely and be strong enough to support both the weight and the size of the inverter.

Storing the Inverter

Store the inverter in a dry place where ambient temperatures are always between -25°C and +60°C.

Work Modes

Eco Mode

[eco mode symbol] The system optimises the delivery of generated PV power and battery power to prioritise the home load. Grid power is used as a last resort if solar and battery power are unavailable.

Off Peak Charging / Peak Discharging

[charging mode symbol] This is prioritised to charge the battery during off peak times when energy is cheaper, greener, and cleaner. The battery will start to discharge outside of the off peak time when energy is more expensive to support the home, otherwise the battery can be discharged at full power to support a variable export tariff.

Back Up / Island Mode

[backup mode symbol] The system has the ability to be used in the event of a power cut. To utilise this feature, circuits must be connected to the inverter's EPS terminals.

To download a fully illustrated guide on connecting the inverter to the EPS, please visit our Knowledge Base at www.givenergy.co.uk [link].

Manufacturer Warranties

This inverter is covered by a 12-year warranty.

Products Covered

Diagrams showing the GivEnergy Hybrid Inverter Gen 1 3.6 and Gen 1 5.0 models, each with a 12-year warranty.

Legal Disclaimer: This document is the property of GivEnergy, reproduction is prohibited.

Models: HY 3.6 Hybrid Inverter Gen 1, HY 3.6, Hybrid Inverter Gen 1, Inverter Gen 1, Gen 1

File Info : application/pdf, 13 Pages, 3.13MB

PDF preview unavailable. Download the PDF instead.

Gen-1-Hybrid-Inverter-Manual

References

Adobe PDF Library 17.0 Adobe InDesign 18.1 (Macintosh)

Related Documents

PreviewGivEnergy Hybrid Inverter Installation Manual for HY 3.6 and HY 5.0
This manual provides comprehensive instructions for the installation, commissioning, and maintenance of the GivEnergy Hybrid Inverter models HY 3.6 and HY 5.0. It covers product overview, specifications, safety guidelines, components, step-by-step installation procedures, connections, maintenance, and troubleshooting.
PreviewGivEnergy Hybrid Inverter Installation Manual (HY 8.0, HY 10.0)
This manual provides comprehensive instructions for the installation, setup, and maintenance of the GivEnergy Hybrid Generation 3 Inverters, models HY 8.0 and HY 10.0. It covers specifications, safety precautions, component identification, connection procedures, and operational modes.
PreviewGivEnergy Hybrid Inverter Installation Manual: HY 8.0 & HY 10.0
This installation manual provides comprehensive guidance for setting up the GivEnergy Gen 3 Hybrid Inverter (models HY 8.0 and HY 10.0). It details safety procedures, connection diagrams, operational modes, and maintenance for efficient solar and battery energy management.
PreviewGivEnergy Hybrid Inverter Installation Manual (V1.0)
Comprehensive installation, operation, and maintenance manual for GivEnergy Hybrid Inverters (models HY2.5, HY3.6, HY4.6, HY5.0). Covers safety, electrical connections, technical data, and warranty.
PreviewGivEnergy Commercial Power Conversion System (PCS) Installation Manual
This installation manual provides comprehensive guidance for the GivEnergy Commercial Power Conversion System (PCS), covering models from 30kW to 500kW. It details safety instructions, handling procedures, environmental requirements, electrical and data connections, final assembly, power-on and shutdown procedures, operational settings, and maintenance. Essential reading for installers and technicians.
PreviewGivEnergy All in One and Giv-Gateway Installer Training Manual
Comprehensive installer training manual for GivEnergy's All in One and Giv-Gateway energy storage systems, covering installation, connection, specifications, and operation.
PreviewGivEnergy Installer Training Manual 2022 - Learn to Install Energy Storage Systems
Comprehensive installer training manual for GivEnergy inverters and batteries (Version 10.0). Covers product specifications, installation, electrical connections, commissioning, and troubleshooting for solar energy storage systems.
PreviewGivEnergy WiFi Dongle Setup Guide: Connect Your Inverter
This guide provides essential instructions for setting up your GivEnergy WiFi dongle, enabling remote monitoring and control of your solar energy system. Learn how to connect your AC coupled or GEN 1 hybrid inverters to your network.