ចម្លើយ

ថ្ងៃទី 02 ខែតុលា ឆ្នាំ 2025 - ម៉ោង 01:21 យប់
According to the user manual, here are the steps to ensure your រោងចក្រថាមពលពន្លឺព្រះអាទិត្យ TECHNAXX TX-212 is installed correctly and functioning properly:
1. **Initial State Check:**
- Make sure the micro inverter is connected to the solar panels.
- Ensure the micro inverter is connected to the house mains via the recommended plug (Wieland or Schuko).
- Check that all cables are securely fixed and protected from rain and sunlight.
- Verify that the feed line is connected to the mains via a circuit breaker.
2. ** កម្រៃជើងសារ៖ **
- Turn on the circuit breaker and any other switches present.
- Switch on the main AC switch.
- The unit LED should start flashing green after turning on the AC circuit breaker.
- The micro inverter should start feeding (grid synchronization) within 2 minutes if there is sufficient sunlight.
3. **LED Status:**
- A fast green flashing LED indicates normal status and active feed into the grid.
- If the LED remains flashing red after 3 minutes, it indicates an error with low solar panel voltage or a missing AC voltage.
- Troubleshoot by checking all connections, ensuring the solar panel voltage is above 22V, and verifying the grid frequency matches the micro inverter's requirements.
4. **ការដោះស្រាយបញ្ហា៖**
- If the micro inverter is not functioning properly, follow the troubleshooting steps provided in the manual.
- Check all AC fuses, connection cables, and AC side connections for damage or errors.
- Measure the voltage of the solar panel to the micro inverter with a suitable multi-meter.
- If issues persist, contact support or an electrician for further assistance.
By following these steps and monitoring the LED status, you can ensure that your រោងចក្រថាមពលពន្លឺព្រះអាទិត្យ TECHNAXX TX-212 is installed correctly and operating as intended.
បន្ថែមមតិយោបល់ថ្មី។