ដើម្បីដំឡើង BlueWalker Cable Management Tray for RLP, follow these steps:
1. Position the cable management tray so that its mounting hole aligns with the tapping hole of the UPS.
2. Connect the left side of the cable management tray to the UPS using 2PCS M3X6 screws, but do not tighten them yet.
3. Adjust the position of the cable management tray as needed.
4. Connect the right side of the cable management tray to the UPS using another 2PCS M3X6 screws.
5. Tighten all screws on both the left and right sides to secure the cable management tray in place.
6. Connect the input/output cables to the rear panel of the UPS.
7. Use the provided strap ties to fix the cables to the cable management tray, ensuring they are organized and secure.
By following these installation steps as outlined in the user guide, you can effectively set up the BlueWalker Cable Management Tray for RLP to help manage and organize your cables efficiently.